From Barry M. Staw's experiment in Knee-Deep in the Big Muddy: A Study of Escalating Commitment to a Chosen Course of Action (1976) and his review The Escalation of Commitment to a Course of Action (1981); his later work with Jerry Ross sorted its causes and remedies.
Explains why decision makers keep putting money and effort into a failing course of action, most of all when they chose it themselves, since each setback raises the personal cost of admitting the first decision was wrong.
Three requests for more money for a failing service, and the board's three decisions
The sponsor comes back three times, each ask resting on a different pull: money already spent, work nearly done, and appearances. Pick the board's move at each review: the verdict names the trap or the remedy, and the meter adds up the money committed after the first miss. Illustrative.
Sponsor
Board
Sponsor
Board
Moves that check escalation: 0 of 3Moves that check escalation: 1 of 3Moves that check escalation: 2 of 3Moves that check escalation: 3 of 3
Money committed after the first miss, $ million0of 7
- First ask (Sponsor). At the first review the service has 25 paying customers against a plan of 150. The sponsor asks for $2 million more, pointing to the $3 million already spent.
- First review (Board). The board decides whether to release another $2 million.
- Approve it: stopping now would waste the $3 million already spent The money is released and the plan is reset to next year. Sunk cost: the $3 million is gone whatever the board decides.
- Judge the $2 million as if the project were proposed today The sponsor's own forecast shows 70 customers a year out, far short of the case for the money. Forward-looking: only future costs and returns count.
- Second ask (Sponsor). The sponsor returns with 40 customers: the platform is 80 percent built and two large dealers are close to signing. Stopping now, the sponsor says, would leave nothing to show.
- Second review (Board). The board decides on the second request, from the same sponsor, for the same project.
- Approve it: the platform is almost finished The platform is finished on time. The dealers do not sign. The completion trap: nearly built says nothing about whether it will sell.
- Give the decision to directors who did not back the project The panel asks to see the dealers' signed terms. There are none yet. Separating the decision from its sponsor removes the need to defend the first call.
- Approve it, and leave the shortfall out of the board pack The shortfall stays out of the minutes, and the next request arrives in six months. Saving face: hiding the miss makes the next extension easier.
- Third ask (Sponsor). Customers stand at 60. The sponsor warns that dealers and staff will read a stop as failure, and that the twelve people hired for the service would have to be moved.
- Third review (Board). The board decides whether the service gets a third extension.
- Fund one more year to avoid a write-off this quarter The write-off moves to next year, $3 million larger. Social and structural pull: appearances and a team built around the project keep it alive.
- Stop the service, keep the sensor work, and give the sponsor the next launch The sensor work goes into the next sprayer, and the sponsor leads its launch. Stopping is made survivable, which removes the reason to escalate.
An example
A maker of agricultural sprayers approved $3 million for a telematics service that would sell farmers data from their machines. Eighteen months and two extensions later it had spent $7 million and signed 60 paying customers against a plan of 150. The sponsor, the vice president who had pitched it, came back for $3 million more, arguing that the platform was nearly built and that stopping would waste what had been spent. The board had approved both earlier extensions on similar arguments.
This time the chair handed the decision to two directors and the finance head, none of whom had backed the project, and asked one question: knowing what the company knew now, would it start this project today for $3 million? The panel said no. It kept the sensor work for the next sprayer model and closed the service. The sponsor was given that model's launch, and the board added a rule that every project over $1 million carries a stop condition, written before the money is released.
The core idea
A decision to continue should look only forward: money already spent is gone whatever happens next. Staw showed that people look back. In his experiment, business students acting as a financial vice president chose which of two divisions got research money, saw five years of results, and then split a second, larger budget. Those whose own pick had declined gave it the most, an average of $13.07 million of $20 million, more than students who saw the same decline in a division someone else had chosen. Staw read this as self-justification: a setback threatens the decision maker's competence, and more investment can still prove the first call right.
Later work grouped the causes into four kinds. Project features, such as a payoff that comes only on completion. Psychological forces, such as responsibility and the pull of nearly finished work. Social ones, such as saving face and the admiration given to leaders who stay the course and win. Structural ones, once a project has staff, budgets, and allies who depend on it.
The thinking behind it
Barry M. Staw Barry M. Staw, then at Northwestern University, reported the experiment in Knee-Deep in the Big Muddy (1976), whose title borrows from a protest song about the Vietnam War. Two hundred forty business students at the University of Illinois played the financial vice president of a fictional company, and Staw varied whether they had made the first allocation themselves and whether it had prospered. In The Escalation of Commitment to a Course of Action (1981) he set the finding beside other evidence and proposed four determinants of commitment: the motive to justify earlier decisions, norms for consistency, and the probability and value of future outcomes.
Where it sits in the layers
Escalation of commitment sits in Layer 5, the explanatory models, because it explains one recurring failure: why organizations keep funding courses of action that have stopped paying. It assumes the picture of decision making in Layer 3's Behavioral Theory of the Firm, where choices are made by people with limited information, goals of their own, and a record to defend. Below, it is managed by methods with stopping points built in, such as the pivot-or-persevere decision of the Lean Startup in Layer 8 and the Premortem of Layer 9, run before money is committed. The common mistake is using it to condemn persistence. It explains biased persistence and cannot say whether a given project should continue, which is a question for forecasting and strategy.
How organizations put it to work
Escalation is managed through the governance of large commitments, usually owned by the chief financial officer or a portfolio committee and backed by the board. Four changes do most of the work. Stop conditions are written before money is released: the milestones, the dates, and the result below which the project ends. Money is released in tranches, each decided on future costs and returns alone. The decision to continue is separated from the people who started the project, through a review panel or a change of sponsor, since the person most responsible has the strongest need to be proved right. And stopping is made survivable: a sponsor who ends a project on good evidence is credited for the call, and the team is placed well.
Expect the first year to stop or rescope a few projects that had been extended more than once, and to meet resistance from sponsors who read the new rules as distrust. Expect the stop conditions to be argued over when they bite. Sustaining it takes a chair willing to enforce a condition against a popular sponsor and a record of early stops treated as good management. The return is capital that moves to better uses sooner and losses that stay small.
Where it goes wrong
The first failure is treating all persistence as escalation. Some projects need patience, and a rule that ends anything behind plan ends the long bets too. The sign is a portfolio with nothing older than two years.
The second is a separation in name only: the review panel reports to the sponsor, or the stop conditions are rewritten each time they are reached. The sign is a stop condition that has never stopped anything.
The third concerns the evidence. The 1976 finding came from a classroom case, and a 2021 replication with 365 participants found no escalation at all: people backed whichever division looked stronger. A 2012 meta-analysis found the responsibility effect across many studies, stronger when decision authority was shared, and warned that pointing out what else the money could buy can backfire. The sign is one remedy applied to every case.
Related and rival frameworks
- Sunk Cost Reasoning. The narrower error inside escalation: letting money already spent decide the next dollar. Use it for a single decision; escalation explains the pattern across rounds and people.
- Loss Aversion. Explains why a sure write-off feels worse than a gamble to recover it. Use it to frame the choice, and escalation to see the responsibility and face behind it.
- Groupthink. A team's drive for agreement can carry a failing course past every warning. The better lens when the momentum belongs to a group more than to one sponsor.
Go to the source
- Knee-Deep in the Big Muddy: A Study of Escalating Commitment to a Chosen Course of Action, Organizational Behavior and Human Performance 16(1), 27 to 44, 1976
- The Escalation of Commitment to a Course of Action, Academy of Management Review 6(4), 577 to 587, 1981
- Knowing When to Pull the Plug, Harvard Business Review, March 1987, with Jerry Ross, 1987
- Cleaning Up the Big Muddy: A Meta-Analytic Review of the Determinants of Escalation of Commitment, Academy of Management Journal 55(3), 541 to 562, by Dustin J. Sleesman, Donald E. Conlon, Gerry McNamara, and Jonathan E. Miles, 2012