Developed by Janna Bastow and Simon Cast around the end of 2012 for their roadmap tool ProdPad, and described by Bastow in The Birth of the Modern Roadmap (2019) and Why I Invented the Now-Next-Later Roadmap (2022).
Arranges a product plan in three horizons, Now, Next, and Later, ordered by how certain the work is, so that a team shows its priorities and direction to others without promising delivery dates it cannot keep.
Eight product items sorted into Now, Next, and Later by how well the team knows them
Select an item, then the column it belongs in: Now is work the team is sure of and can detail, Later is a problem seen but not yet defined. Show the sort to compare yours. Illustrative.
- Not placedPlacedNowNextLater
- Not placedPlacedNowNextLater
- Not placedPlacedNowNextLater
- Not placedPlacedNowNextLater
- Not placedPlacedNowNextLater
- Not placedPlacedNowNextLater
- Not placedPlacedNowNextLater
- Not placedPlacedNowNextLater
Items
Horizon, ordered by certainty
Your sort matched 0 of 8.Your sort matched 1 of 8.Your sort matched 2 of 8.Your sort matched 3 of 8.Your sort matched 4 of 8.Your sort matched 5 of 8.Your sort matched 6 of 8.Your sort matched 7 of 8.Your sort matched 8 of 8.
- Now
- Being worked on. Defined, owned, and broken into detailed pieces of work.
- Next
- Expected to start when Now clears. Described loosely, and it may change depending on what Now teaches.
- Later
- A problem the team can see and has not defined or committed to. No date, and no solution yet.
The sort
- Fix checkout timeouts: Now. Known, owned, and in progress: the team can detail the work.
- Saved payment methods: Next. Expected soon and dependent on a Now item, so it stays loosely described until then.
- Onboarding drop-off: Later. A real problem with no solution. It gets explored when it moves closer.
- Invoice export bug: Now. Clear, urgent, and owned, so it belongs with the work in progress.
- Partner integrations: Later. Interest with no shape. Leaving it here keeps it visible without promising anything.
- Role-based permissions: Next. A clear next step that is not yet detailed enough to start.
- Churn reporting: Later. A wish. It needs exploration before it can be sized.
- Single sign-on: Next. Likely and wanted, but its start depends on Now clearing.
An example
A software company's sales team asked for a date on every item of the product roadmap, and every date the product team gave slipped. By the third quarter the head of product had spent more time defending dates than deciding what to build. She replaced the Gantt-style plan with a board of three columns.
Now held four items with owners and detailed work. Next held the work that would start when those finished, described more loosely. Later held a handful of large, hazy problems the team had noticed, such as customers leaving during onboarding, with no solution attached. In the first review the sales director asked for the date of one Later item and was told it had none, and that it would be shaped once it moved into Next. The conversation moved to which problem mattered most. Within two quarters the sales team was quoting direction to customers in place of dates, and the roadmap review had stopped being an argument about slippage.
The core idea
The roadmap has three columns, and each is a statement of how much the team knows. Now holds the work being done. It is well defined and broken into detailed pieces. Next holds what is expected to start when Now is complete. It is less detailed, and it may depend on how the Now items turn out. Later holds larger and vaguer problems the team wants to keep in view without having committed to them or broken them down.
The insight is that certainty falls with distance, and a plan should say so. A dated timeline treats a guess about next year with the same confidence as next week's work, which invites false precision and then the padding of estimates that follows. Three horizons let a plan grow more certain as work approaches. An item is explored and specified as it moves closer, and it can be reordered or dropped with no missed date to explain. Bastow's own test of the format is that a stakeholder should grasp the plan in about ten seconds.
The thinking behind it
Janna Bastow Janna Bastow came to product management by accident and found that the roadmaps she could copy were all timelines, Gantt charts in effect. When dates slipped, she added more buffer to cover the slipped work. In early 2010 she met Simon Cast, a fellow product manager in London. They ran ProductCamp London together and began building the tool that became ProdPad. In late 2012, in a cafe in south London, Cast turned over a napkin and sketched three undated columns, Current, Near term, and Future. An early customer suggested the names Now, Next, and Later, and ProdPad made them its defaults.
Where it sits in the layers
The Now-Next-Later roadmap sits in Layer 9, Tools and Techniques: a planning artifact, three columns ordered by certainty, that a product team can adopt inside whatever method it runs. From above it takes the view of the Agile Manifesto in Layer 6 that responding to change matters more than following a plan, and the habit of Continuous Discovery, also in Layer 6, which supplies the learning that moves an item from Later to Next. It serves Layer 8 methods such as Scrum, whose backlog draws from the Now column. Below it, the roadmap is put into practice in the quarterly roadmap review and in backlog refinement. The common mistake is asking it to be a commitment device. A roadmap without dates cannot settle a contract, and dated delivery to a customer needs another plan.
How organizations put it to work
A product organization adopts Now-Next-Later by replacing the dated roadmap with three columns that the head of product owns and the leadership team reviews. The structural change is small. The change in decisions is real. Leaders discuss which problems deserve a place in Next, and stop arguing about which dates were missed. The routine is a regular review in which items move, with a short reason for each move, and a rule that nothing enters Now without a clear owner and an outcome.
Sustaining it takes a firm line with stakeholders who ask for dates, a habit of attaching each item to a problem or outcome, and a regular clear-out of Later, which fills with ideas quickly. It works best beside a separate list of commitments that must hit a date, such as a regulatory deadline.
In the first year a leader should expect some resistance from sales and finance teams, who plan against dates. They should also expect shorter and more candid planning meetings. The business gains a plan it can read quickly and trust more, because it does not promise what the team does not know.
Where it goes wrong
The first failure is dates in disguise. Teams label the columns by quarter and the roadmap becomes a timeline again. The sign is a stakeholder asking which quarter a Later item lands in, and getting an answer.
The second is a Later column that becomes a dumping ground. Hazy items pile up with no owner, and none of them ever gets explored. The sign is a Later list that has not changed in two quarters.
The third is hiding real commitments. Some work has a date that cannot move, such as a legal change or a contracted delivery. Putting it in Now or Next without a date misleads the people who depend on it. The sign is a surprised customer.
A fair limit of the format is that it shows priority and leaves capacity out, so it cannot say how much fits into Now. Leaders should pair it with an honest view of team size.
Related and rival frameworks
- Continuous Discovery. Supplies the weekly learning that decides what moves from Later to Next. The better pick when the question is how a team finds out what to build.
- Outcome-Driven Innovation. Ranks unmet customer needs by importance and satisfaction. Use it to decide what belongs on the roadmap before the roadmap sorts it by certainty.
- Lean Startup. Treats the plan as a set of hypotheses to test. Fits an early product where the roadmap is mostly learning goals.
Go to the source
- The Birth of the Modern Roadmap, ProdPad blog, 2019
- Why I Invented the Now-Next-Later Roadmap, ProdPad blog, 2022