Stage-Gate Process

Layers of Management ThoughtLayer 8: Methodologies and Operating SystemsMethodologyAlso known as Stage-Gate, Idea-to-launch process, Phase-gate process

From Robert G. Cooper's research on why new products succeed and fail, reported in Winning at New Products (1986) and set out as the Stage-Gate system in his 1990 Business Horizons article.

Organizes new product development into stages, each ended by a gate where managers decide to go, kill, hold, or recycle a project against set criteria before committing the next tranche of money.

One dishwasher-controller project through three gates

The team brings evidence at the end of each stage, and at each gate you choose to go, hold, recycle, or kill. The reply shows what the gate's criteria say about that call. Illustrative.

Project team

Gate reviewers

Project team

Gate reviewers

Select a stage to read it, or play the sequence.Scoping. The team finds demand in hospital kitchens, a fit with the company's service strategy, and one open question: whether the core parts can be bought at the target cost.Gate 2. The criteria at this gate are strategic fit and market size. Cost is the question the next stage exists to answer.Pick a move to see the reply.Funded for ten weeks, with the parts-cost question as the first task.Right: the criteria are met and the open question has a stage to answer it.The project stops, and a market the company wanted goes to a competitor.Too early: cost is not yet a criterion at this gate.Development opens with no business case, and cost surprises appear in month four.A skipped stage: the money is committed before the question is answered.Business case. Customers will pay 20 percent above the target price, but unit cost is 15 percent above the limit, and the return is below the company's hurdle. One part drives most of the gap.Gate 3. The criterion is a return above the hurdle with a clear product definition. The gap is real and traced to a single part.Pick a move to see the reply.A three-week redesign brings the unit cost inside the limit.Right: a fixable gap belongs in a recycle, with a short date.Development begins with a known loss built in, and the fix takes four months.The hurdle is not met, and hope is not a criterion.A fixable project ends at the cost of three weeks of work.Premature: the gap has a named cause and a cheap check.Testing. After redesign and nine months of development, field tests go well. Meanwhile a competitor has launched a similar controller at 40 percent below the planned price. The return cannot be restored. Development spending to date is $3.1 million.Gate 4. The criterion is a return above the hurdle at launch. The spending to date is the same whether the project continues or stops.Pick a move to see the reply.The team is reassigned within the month and the learnings go into the next project.Right: the money spent is gone either way, and only the future return counts.The launch proceeds and sells at a loss for two years.Sunk cost: past spending is not a reason to spend more.The team sits idle for a quarter and the rival gains share.A hold needs a condition and a date. This one has neither.

Gate calls that matched the criteria: 0 of 3Gate calls that matched the criteria: 1 of 3Gate calls that matched the criteria: 2 of 3Gate calls that matched the criteria: 3 of 3

  1. Scoping (Project team). The team finds demand in hospital kitchens, a fit with the company's service strategy, and one open question: whether the core parts can be bought at the target cost.
  2. Gate 2 (Gate reviewers). The criteria at this gate are strategic fit and market size. Cost is the question the next stage exists to answer.
    • Go: fund the business case stage Funded for ten weeks, with the parts-cost question as the first task. Right: the criteria are met and the open question has a stage to answer it.
    • Kill: the parts cost looks too high The project stops, and a market the company wanted goes to a competitor. Too early: cost is not yet a criterion at this gate.
    • Go straight to development to save time Development opens with no business case, and cost surprises appear in month four. A skipped stage: the money is committed before the question is answered.
  3. Business case (Project team). Customers will pay 20 percent above the target price, but unit cost is 15 percent above the limit, and the return is below the company's hurdle. One part drives most of the gap.
  4. Gate 3 (Gate reviewers). The criterion is a return above the hurdle with a clear product definition. The gap is real and traced to a single part.
    • Recycle: redesign the one part, return in three weeks A three-week redesign brings the unit cost inside the limit. Right: a fixable gap belongs in a recycle, with a short date.
    • Go: the market is strong, fix cost in development Development begins with a known loss built in, and the fix takes four months. The hurdle is not met, and hope is not a criterion.
    • Kill: the return is below the hurdle A fixable project ends at the cost of three weeks of work. Premature: the gap has a named cause and a cheap check.
  5. Testing (Project team). After redesign and nine months of development, field tests go well. Meanwhile a competitor has launched a similar controller at 40 percent below the planned price. The return cannot be restored. Development spending to date is $3.1 million.
  6. Gate 4 (Gate reviewers). The criterion is a return above the hurdle at launch. The spending to date is the same whether the project continues or stops.
    • Kill: the return is gone, whatever has been spent The team is reassigned within the month and the learnings go into the next project. Right: the money spent is gone either way, and only the future return counts.
    • Go: $3.1 million is already in it The launch proceeds and sells at a loss for two years. Sunk cost: past spending is not a reason to spend more.
    • Hold: wait and see what the rival does The team sits idle for a quarter and the rival gains share. A hold needs a condition and a date. This one has neither.

An example

A maker of commercial dishwashers had forty product ideas in progress and engineers stretched across all of them. Projects were seldom stopped. Each one had a sponsor, and each sponsor could point to the money already spent.

The chief operating officer introduced gates. After a short scoping study, a project went before three senior leaders with a one-page scorecard covering strategic fit, market size, technical risk, and expected return. It was cleared to the next stage, held, sent back for rework, or killed on the spot, and only a project that passed received funding for the next stage.

In the first year, eleven of the forty ideas were killed or sent back at the first two gates, after weeks of work, where in earlier years such projects had run on for months until testing. With those engineers freed, the six projects already in development launched a quarter sooner.

The core idea

Stage-Gate divides the path from idea to launch into a series of stages, such as scoping, building the business case, development, testing, and launch. In each stage a team does a defined set of activities, and gathers the information needed to decide whether the project deserves more money. At the end of each stage sits a gate, a meeting of senior managers who hold the budget.

A gate has four possible outcomes. Go commits the next stage's resources. Kill stops the project. Hold pauses it. Recycle returns it to the same stage for more work. The decision is made against criteria set in advance, often scored on a gate scorecard, so the same questions apply to every project.

The insight is that each stage costs more than the last, so the cheapest place to stop a bad project is at the earliest gate. A gate turns spending into a series of small bets that managers can withdraw from.

The thinking behind it

Robert G. Cooper Robert Cooper, a professor emeritus at McMaster University, began by watching project teams at large firms develop bold new products and by comparing hundreds of products that succeeded or failed, research he reported in Winning at New Products in 1986. He has described Stage-Gate as those observed practices put together, with the success drivers his studies found built in. His 1990 Business Horizons article, Stage-Gate Systems: A New Tool for Managing New Products, set the system out for managers. Later work with Scott Edgett and Elko Kleinschmidt studied how best-practice companies run their gates, including a scorecard to rate and rank projects.

Where it sits in the layers

Stage-Gate sits in Layer 8, Methodologies and Operating Systems: it prescribes the stages a new product passes through, the gates between them, who sits on each gate, and what evidence each gate needs. It grew out of research on why new products succeed and fail, findings of the kind Layer 5's explanatory models hold, and it takes for granted a Layer 3 view of the firm as a bundle of resources to be allocated among competing uses, the problem behind the Resource Allocation Process. Beside it in Layer 8, Lean Startup and the Design Sprint share its habit of stopping early on evidence, and in Layer 10 its gate meetings are where the process actually happens. The common mistake is asking it to generate ideas. It filters and funds them, so a company with a weak flow of ideas gets a careful way of choosing among weak candidates.

How organizations put it to work

A senior group of gatekeepers owns the gates, usually the heads of marketing, engineering, operations, and finance with the chief executive or a divisional head chairing, and a process owner runs the system day to day. The structural change is a single pipeline with common stages and criteria, which replaces the separate rules each function kept.

It changes how money is released. Funding follows gate decisions, tranche by tranche, and gatekeepers commit the people a project needs when they say go, so a project cleared at a gate is actually staffed. Meetings change too: a gate reviews evidence against a scorecard and does not hear a sales pitch.

Measures are the kill rate at early gates, time from idea to launch, and the share of launches that meet their forecast. Sustaining it depends on gatekeepers willing to kill their favorites. In the first year, expect fewer active projects, some resentment from sponsors, and a period when paperwork grows faster than decisions improve. The gain is a leaner portfolio and less dependence on any one champion's persuasiveness.

Where it goes wrong

The first failure is the gate that never kills. When every project passes, the system is a ritual, and the sign is a kill rate near zero while the portfolio keeps growing.

The second is bureaucracy. Heavy documents at every gate slow small projects and push the best engineers to work around the system. Cooper's later variants, such as Stage-Gate Lite and XPress, exist for smaller and lower-risk projects, which acknowledges the point. The sign is teams that hide projects outside the process.

The third is a criticism of fit. A fixed sequence of plan, build, and test suits products whose requirements can be known up front, and fits poorly where needs emerge only through use, as in software. Cooper's newer versions build in practices from agile software development. The sign is a gate that asks for a business case the team can only invent.

Related and rival frameworks

  • Lean Startup. Replaces a planned sequence with short cycles of building and testing against customers. The better pick when the main uncertainty is whether anyone wants the product.
  • Discovery-Driven Planning. Starts from the return the venture must show and then lists the assumptions to test in order of cost. Use it when forecasts would be pure invention.
  • Design Sprint. Compresses the early stages into a few days with a prototype tested on customers. A fast way to give an early gate real evidence.