Balanced Scorecard

Layers of Management ThoughtLayer 7: Assessment and Maturity ModelsModelAlso known as BSC

Developed by Robert S. Kaplan and David P. Norton from a 1990 multi-company study of performance measurement (The Balanced Scorecard: Measures That Drive Performance, 1992), and extended by them into a system for managing strategy (The Balanced Scorecard: Translating Strategy into Action, 1996).

Measures a business on four linked fronts (financial results, customers, internal processes, and learning and growth) so that the drivers of future results get the same attention as the financial outcomes they produce.

A training cut shows up in three perspectives before it reaches profit

One measure from each perspective of a building-services company's scorecard, linked from training to profit. Set the training hours and watch eight quarters run: a cut lifts profit at first, while certification and first-time fixes fall, lost contracts climb, and profit follows them down. Illustrative.

At 4 hours a quarter, profit rises from $500K to $548K for three quarters while certification falls from 80 to 66 percent and first-time fixes slip almost seven points. By quarter 8, 11 of 50 contracts are lost a quarter and profit is down to $398K. Select a box to read it.Training hours. The decision: hours of training per technician each quarter. Twelve hours keeps the workforce's certification where it is.Financial: profit. Financial perspective. Training is a cost this quarter, so a cut lifts profit at once. The renewals it loses arrive later and cost more.Learning: skills. Learning and growth perspective. Training keeps technicians certified on new equipment. Without it, certification slips every quarter.Process: first-time fixes. Internal process perspective. Certified technicians fix more faults on the first visit, about a quarter after their skills change.Customer: contracts lost. Customer perspective. Building owners walk away when faults keep coming back. They judge a year of visits, so this measure moves last.
4

Certified technicians, percent

0: 80%1: 74%2: 70%3: 66%4: 64%5: 62%6: 60%7: 59%8: 58%0%25%50%75%100%0123456780: 80%1: 74%2: 70%3: 66%4: 64%5: 62%6: 60%7: 59%8: 58%0%25%50%75%100%012345678

Contracts lost a quarter, of 50 up for renewal

0: 51: 52: 53: 54: 65: 76: 97: 108: 110510150123456780: 51: 52: 53: 54: 65: 76: 97: 108: 11051015012345678

Operating profit a quarter

0: $500K1: $548K2: $548K3: $548K4: $534K5: $508K6: $474K7: $436K8: $398K$0K$200K$400K$600K0123456780: $500K1: $548K2: $548K3: $548K4: $534K5: $508K6: $474K7: $436K8: $398K$0K$200K$400K$600K012345678

Quarter 8 of 8

Certified technicians, percent
58%
Contracts lost a quarter, of 50 up for renewal
11
Operating profit a quarter
$398K

Training hours
The decision: hours of training per technician each quarter. Twelve hours keeps the workforce's certification where it is.
Financial: profit
Financial perspective. Training is a cost this quarter, so a cut lifts profit at once. The renewals it loses arrive later and cost more.
Learning: skills
Learning and growth perspective. Training keeps technicians certified on new equipment. Without it, certification slips every quarter.
Process: first-time fixes
Internal process perspective. Certified technicians fix more faults on the first visit, about a quarter after their skills change.
Customer: contracts lost
Customer perspective. Building owners walk away when faults keep coming back. They judge a year of visits, so this measure moves last.

An example

A company that maintains heating and cooling systems in office buildings ran its monthly review from one page of financials. Profit beat plan for three straight quarters after a freeze on technician training, so the freeze stayed. A new chief operating officer asked for a scorecard first. The strategy was to win and keep multi-year maintenance contracts by fixing faults on the first visit, so the team picked a few measures in each perspective: certified technicians, first-time fix rate, contracts lost at renewal, and operating profit.

The first scorecard showed certification down from 80 to 66 percent, first-time fixes down almost seven points, and lost contracts beginning to tick up on accounts with the newest equipment. The extra profit had been borrowed from next year's renewals. Training came back, the fix rate became a monthly target for every branch, and the managers' bonus moved from profit alone to a weighted mix of all four perspectives.

The core idea

Financial measures report the results of decisions made months or years earlier. A business steered by them alone can improve its numbers while weakening whatever produces them. The Balanced Scorecard keeps the financial perspective and adds three that lead it. The customer perspective asks how the targeted customers see the business: whether it wins them, keeps them, and earns a growing share of their spending. The internal process perspective asks which processes must excel to deliver what those customers were promised. The learning and growth perspective asks what people, systems, and culture those processes need.

Each perspective holds a few objectives, and each objective gets a measure, a target, and a funded initiative. The objectives are meant to connect in a chain of cause and effect: skills improve processes, processes win and keep customers, and customers produce the financial results. That chain is the insight. A scorecard of unconnected measures is only a dashboard. One whose measures state what drives what can be tested, quarter by quarter, against the strategy it came from.

The thinking behind it

Robert S. Kaplan Robert S. Kaplan, an accounting professor at Harvard Business School, had argued with H. Thomas Johnson in Relevance Lost (1987) that American companies had become fixed on short-term financial measures. He joined a 1990 multi-company study of performance measurement, where a presentation on Analog Devices' corporate scorecard showed every quality measure improving while the company's sales and margins failed to follow. The lesson he and Norton drew was that operational gains had to be linked to customer and financial outcomes. The result was The Balanced Scorecard: Measures That Drive Performance (1992), which treats operational measures as leading indicators and financial measures as lagging ones.

David P. Norton David P. Norton, a consultant who, like Kaplan, trained as an electrical engineer, carried the scorecard into the companies that adopted it after 1992. Working with them, he and Kaplan found that measures copied from admired firms, or sorted out of existing reports into four boxes, missed what drove each company's success. A scorecard had to start from the strategy's objectives and only then choose measures. That finding shaped The Balanced Scorecard: Translating Strategy into Action (1996) and the strategy maps that followed, which turned a set of measures into a way of carrying out a strategy.

Where it sits in the layers

The Balanced Scorecard sits in Layer 7, the assessment and maturity models, because its job is to tell an organization where it stands against its own strategy, one perspective at a time. It takes the strategy as given. The choice of customers and value proposition is made upstream, by strategy work that draws on theories of the firm such as the Resource-Based View, and its customer and process measures carry the inheritance of the quality movement in Layer 6. Below it, methodologies such as Hoshin Kanri cascade its objectives into plans, and a Monthly Business Review in Layer 10 is where its numbers get read and acted on. The common mistake is asking the scorecard to choose the strategy. Four perspectives filled with generic measures describe a business without saying where it should go.

How organizations put it to work

The scorecard belongs to the chief executive and the leadership team, with a small strategy office keeping the measures, the data, and the review calendar. Adoption starts with the strategy, written as a handful of objectives per perspective and drawn as a chain from learning to financial results. Only then does each objective get one or two measures, a target, and a funded initiative. A few measures per perspective is enough, since a list of forty is a report nobody steers by.

The scorecard then has to enter the routines that already run the business. The monthly operating review is run from it, the budget funds its initiatives, and business units build their own scorecards that roll up to the corporate one. Many companies tie part of variable pay to it, which gives it weight and raises the stakes on choosing the measures well.

The first year is mostly about data. Several measures will have no clean source, the first targets will be guesses, and at least one cause-and-effect link will turn out to be wrong. The first real payoff usually comes when a leading measure moves a quarter or two before the financial result and the team acts on it in time. A strategy translated into measures that every unit reads the same way also outlasts any one executive.

Where it goes wrong

The first failure is a scorecard built by sorting existing measures into four boxes. It looks balanced and connects to nothing. Spot it by asking which strategic objective each measure serves. If nobody can say, the measure is decoration.

The second is a chain that is never tested. Teams assume that training lifts the fix rate and the fix rate lifts renewals, and never check. Spot it when a leading measure improves for several quarters and the outcome it is supposed to drive does not move.

The third is pay pressure. Once bonuses ride on the measures, people manage the measures, and the scorecard starts reporting what the organization wants to be true. Spot it when results land just over every target. Critics add that the cause-and-effect links are usually assumed and seldom verified, and that suppliers and the community appear only if a company chooses to add them.

Related and rival frameworks

  • Strategy Maps. The diagram Kaplan and Norton later drew of the cause-and-effect chain between objectives. Build the map first when the leadership team does not yet agree on the strategy.
  • OKRs. Quarterly objectives with measurable key results, set from the top and from the teams. Better for focusing a fast-moving group on a few changes, weaker as a standing view of the whole business.
  • EFQM Excellence Model. Scores the whole organization against a model of excellence. Use it to assess capability broadly, and the scorecard to track one strategy.

Go to the source

Back to the catalog