Quarterly Business Review

Layers of Management ThoughtLayer 10: Practices and RitualsPracticeAlso known as QBR, Executive business review, Business review

An operating and account management practice with no single author, documented most fully in customer success writing, such as Gainsight's guides to the internal review a team gives its leaders (2022) and to the review held with a key customer (2014 and 2016).

A review held each quarter in which a business unit, or a supplier with a key customer, sets the quarter's results against what was planned, explains the gaps, and agrees on the next quarter's priorities and the help it needs.

Eight gaps against plan from one quarter's reviews, sorted by cause and how long they last

Each tag is a gap a unit reported against its plan. Select one, then the box for whether its cause is inside the company's control and whether it will outlast the quarter: the box says what the review decides. One is placed as an example. Show the sort to compare yours. Illustrative.

Items (select one, then a box)
  • Not placedPlacedRide it outFix it nowRe-forecastFund the fix
  • Not placedPlacedRide it outFix it nowRe-forecastFund the fix
  • Not placedPlacedRide it outFix it nowRe-forecastFund the fix
  • Not placedPlacedRide it outFix it nowRe-forecastFund the fix
  • Not placedPlacedRide it outFix it nowRe-forecastFund the fix
  • Not placedPlacedRide it outFix it nowRe-forecastFund the fix
  • Not placedPlacedRide it outFix it nowRe-forecastFund the fix
  • Not placedPlacedRide it outFix it nowRe-forecastFund the fix

How long it lasts

Beyond itThis quarter
Re-forecast
Fund the fix
Ride it out
Fix it now
Outside our controlInside our control

Cause

Freight between warehouses. Southwest: gross margin three points under plan, mostly freight between two half-empty warehouses twenty miles apart.Not placed yet.Freight between warehouses. Southwest: gross margin three points under plan, mostly freight between two half-empty warehouses twenty miles apart.Ride it out: A one-off from outside. Note it, keep the plan, and check that it is gone next quarter.Freight between warehouses. Southwest: gross margin three points under plan, mostly freight between two half-empty warehouses twenty miles apart.Fix it now: A slip the unit caused and can correct within weeks. Name the action, the owner, and the date.Freight between warehouses. Southwest: gross margin three points under plan, mostly freight between two half-empty warehouses twenty miles apart.Re-forecast: A lasting change the company cannot control. Reset the year's numbers and the plan behind them.Freight between warehouses. Southwest: gross margin three points under plan, mostly freight between two half-empty warehouses twenty miles apart.Fund the fix: A lasting problem the company can solve with money, people, or a change in structure. Decide the ask in the room.The cause is the company's own layout, and it will last until changed. The unit asks to consolidate, and the review decides it.Storm closed the plant. Gulf: four days of lost production after a hurricane.Not placed yet.Storm closed the plant. Gulf: four days of lost production after a hurricane.Ride it out: A one-off from outside. Note it, keep the plan, and check that it is gone next quarter.Outside anyone's control and over. Keep the plan, and check next quarter that output recovered.Storm closed the plant. Gulf: four days of lost production after a hurricane.Fix it now: A slip the unit caused and can correct within weeks. Name the action, the owner, and the date.Storm closed the plant. Gulf: four days of lost production after a hurricane.Re-forecast: A lasting change the company cannot control. Reset the year's numbers and the plan behind them.Storm closed the plant. Gulf: four days of lost production after a hurricane.Fund the fix: A lasting problem the company can solve with money, people, or a change in structure. Decide the ask in the room.Big order delayed. Midwest: a large customer pushed its order into next quarter.Not placed yet.Big order delayed. Midwest: a large customer pushed its order into next quarter.Ride it out: A one-off from outside. Note it, keep the plan, and check that it is gone next quarter.A matter of timing: the revenue moves a quarter, and the year's plan holds.Big order delayed. Midwest: a large customer pushed its order into next quarter.Fix it now: A slip the unit caused and can correct within weeks. Name the action, the owner, and the date.Big order delayed. Midwest: a large customer pushed its order into next quarter.Re-forecast: A lasting change the company cannot control. Reset the year's numbers and the plan behind them.Big order delayed. Midwest: a large customer pushed its order into next quarter.Fund the fix: A lasting problem the company can solve with money, people, or a change in structure. Decide the ask in the room.Rival's lasting price cut. Northeast: a competitor cut prices 8 percent and says it will hold them.Not placed yet.Rival's lasting price cut. Northeast: a competitor cut prices 8 percent and says it will hold them.Ride it out: A one-off from outside. Note it, keep the plan, and check that it is gone next quarter.Rival's lasting price cut. Northeast: a competitor cut prices 8 percent and says it will hold them.Fix it now: A slip the unit caused and can correct within weeks. Name the action, the owner, and the date.Rival's lasting price cut. Northeast: a competitor cut prices 8 percent and says it will hold them.Re-forecast: A lasting change the company cannot control. Reset the year's numbers and the plan behind them.Outside the company's control and here to stay. The year's numbers and the unit's plan must be reset.Rival's lasting price cut. Northeast: a competitor cut prices 8 percent and says it will hold them.Fund the fix: A lasting problem the company can solve with money, people, or a change in structure. Decide the ask in the room.Lumber tariff raised costs. All units: a new tariff on imported lumber lifted material costs.Not placed yet.Lumber tariff raised costs. All units: a new tariff on imported lumber lifted material costs.Ride it out: A one-off from outside. Note it, keep the plan, and check that it is gone next quarter.Lumber tariff raised costs. All units: a new tariff on imported lumber lifted material costs.Fix it now: A slip the unit caused and can correct within weeks. Name the action, the owner, and the date.Lumber tariff raised costs. All units: a new tariff on imported lumber lifted material costs.Re-forecast: A lasting change the company cannot control. Reset the year's numbers and the plan behind them.A lasting change nobody in the room controls. Re-forecast, then decide on prices separately.Lumber tariff raised costs. All units: a new tariff on imported lumber lifted material costs.Fund the fix: A lasting problem the company can solve with money, people, or a change in structure. Decide the ask in the room.Quote backlog. Mountain: quotes took nine days instead of three after an estimator left.Not placed yet.Quote backlog. Mountain: quotes took nine days instead of three after an estimator left.Ride it out: A one-off from outside. Note it, keep the plan, and check that it is gone next quarter.Quote backlog. Mountain: quotes took nine days instead of three after an estimator left.Fix it now: A slip the unit caused and can correct within weeks. Name the action, the owner, and the date.The unit's own slip, fixable in weeks with a temporary estimator. Name the owner and the date.Quote backlog. Mountain: quotes took nine days instead of three after an estimator left.Re-forecast: A lasting change the company cannot control. Reset the year's numbers and the plan behind them.Quote backlog. Mountain: quotes took nine days instead of three after an estimator left.Fund the fix: A lasting problem the company can solve with money, people, or a change in structure. Decide the ask in the room.Late invoices, new system. Southwest: invoices went out late for a month after the billing system changed.Not placed yet.Late invoices, new system. Southwest: invoices went out late for a month after the billing system changed.Ride it out: A one-off from outside. Note it, keep the plan, and check that it is gone next quarter.Late invoices, new system. Southwest: invoices went out late for a month after the billing system changed.Fix it now: A slip the unit caused and can correct within weeks. Name the action, the owner, and the date.Caused inside and short-lived. Retrain the billing team and confirm by month's end.Late invoices, new system. Southwest: invoices went out late for a month after the billing system changed.Re-forecast: A lasting change the company cannot control. Reset the year's numbers and the plan behind them.Late invoices, new system. Southwest: invoices went out late for a month after the billing system changed.Fund the fix: A lasting problem the company can solve with money, people, or a change in structure. Decide the ask in the room.Too few installers. Northeast: jobs wait three weeks for installation crews, and customers cancel.Not placed yet.Too few installers. Northeast: jobs wait three weeks for installation crews, and customers cancel.Ride it out: A one-off from outside. Note it, keep the plan, and check that it is gone next quarter.Too few installers. Northeast: jobs wait three weeks for installation crews, and customers cancel.Fix it now: A slip the unit caused and can correct within weeks. Name the action, the owner, and the date.Too few installers. Northeast: jobs wait three weeks for installation crews, and customers cancel.Re-forecast: A lasting change the company cannot control. Reset the year's numbers and the plan behind them.Too few installers. Northeast: jobs wait three weeks for installation crews, and customers cancel.Fund the fix: A lasting problem the company can solve with money, people, or a change in structure. Decide the ask in the room.A lasting constraint the company can fix with hiring and training. Decide the funding in the review.

Your sort matched 0 of 8.Your sort matched 1 of 8.Your sort matched 2 of 8.Your sort matched 3 of 8.Your sort matched 4 of 8.Your sort matched 5 of 8.Your sort matched 6 of 8.Your sort matched 7 of 8.Your sort matched 8 of 8.

Ride it out
A one-off from outside. Note it, keep the plan, and check that it is gone next quarter.
Fix it now
A slip the unit caused and can correct within weeks. Name the action, the owner, and the date.
Re-forecast
A lasting change the company cannot control. Reset the year's numbers and the plan behind them.
Fund the fix
A lasting problem the company can solve with money, people, or a change in structure. Decide the ask in the room.

The sort

  • Freight between warehouses: Fund the fix. The cause is the company's own layout, and it will last until changed. The unit asks to consolidate, and the review decides it.
  • Storm closed the plant: Ride it out. Outside anyone's control and over. Keep the plan, and check next quarter that output recovered.
  • Big order delayed: Ride it out. A matter of timing: the revenue moves a quarter, and the year's plan holds.
  • Rival's lasting price cut: Re-forecast. Outside the company's control and here to stay. The year's numbers and the unit's plan must be reset.
  • Lumber tariff raised costs: Re-forecast. A lasting change nobody in the room controls. Re-forecast, then decide on prices separately.
  • Quote backlog: Fix it now. The unit's own slip, fixable in weeks with a temporary estimator. Name the owner and the date.
  • Late invoices, new system: Fix it now. Caused inside and short-lived. Retrain the billing team and confirm by month's end.
  • Too few installers: Fund the fix. A lasting constraint the company can fix with hiring and training. Decide the funding in the review.

An example

A building-products company with five regional business units held a quarterly review for each one with the chief executive and the finance chief. The reviews ran two hours each on sixty slides of mostly good news, and the gaps against plan surfaced on the last slides, if at all.

The finance chief rebuilt the format around one page per unit: results against plan and forecast, the three largest gaps with their causes, what the unit learned, next quarter's priorities, and its asks. Pages went out two days ahead, and the hour was spent on gaps and asks.

The southwest unit's page showed revenue on plan and gross margin three points under, which the slides would have buried. Most of the gap came from freight between two half-empty warehouses the unit ran twenty miles apart. Since the cause was inside the company's control and would last, the general manager asked to consolidate the warehouses, and the decision was made in the room with one condition: no missed deliveries during the move. Margin recovered two points the next quarter.

The core idea

A quarterly business review comes in two forms with one logic. Internally, a unit or function presents to its leaders: results against plan and forecast, the largest gaps and their causes, lessons, next quarter's priorities, and its asks. With a key customer, a supplier reviews the results the customer has gained, the goals agreed last time, problems and support history, and the goals for the next ninety days.

Both sit between the weekly rhythm, which manages activity, and the annual plan, which sets direction. A quarter is long enough for results to show and short enough to change course within the year. The insight is that the review is worth its gaps. A review that lingers on what went well teaches nothing, while one that sorts each gap by its cause and its duration decides what to fix, what to fund, and what to re-forecast. With customers the same discipline shows whether the customer is getting what it paid for, which is an early reading of whether it will stay.

The thinking behind it

Operating and account management practice Quarterly reviews have no author, and their fullest written guides come from customer success, the discipline of keeping subscription customers. Gainsight's 2022 guide to internal reviews asks each team to set its forecast against its results, talk about losses as openly as wins, and close on a slide of the help it wants. For the review held with a customer, Gainsight's 2014 guide ranks it among an account manager's most important duties: it shows the customer's executives what they have gained, sets goals for the next ninety days that the following review checks, and should leave nothing to settle at renewal. A 2016 Gainsight post schedules these reviews up to four times a year, depending on the customer's service level.

Where it sits in the layers

The quarterly business review is a Layer 10 practice, the quarterly beat of an operating rhythm. It assumes the measurement systems of Layer 7, such as the Balanced Scorecard, which decide what the review reads, and the goal systems of Layer 8, such as OKRs, whose quarterly cycle it often closes. In the same layer it is the slow beat over the faster weekly business review and the monthly business review, which catch problems sooner and in more detail. The common wrong-layer mistake is using the QBR as the place to discover problems. A gap the quarterly review is the first to see was missed by the faster weekly and monthly reviews, and the fix is in those rhythms. The other mistake is making strategy in it: a quarter's results can test a strategy, and choosing a new one belongs to the annual plan.

How organizations put it to work

Internally, the finance chief or a strategy and operations lead usually owns the format and calendar, and each unit head owns their review. A workable design uses one page per unit, the same template for every unit, sent two days ahead. The meeting goes to the three largest gaps and the asks, and decisions, owners, and forecast changes are written down before the next unit begins. With customers, the account owner runs the review with the customer's executive sponsor, using the customer's own goals as the agenda.

The practice changes decisions and measures. Funding and staffing shifts can be made quarterly, in the room, instead of waiting for next year's budget. Forecast accuracy by unit becomes visible, and so does which units explain their gaps and which only report them. With customers, results against the customer's goals become a leading indicator of renewal, which makes revenue more certain and lets problems surface while there is time to fix them.

In the first year, expect units to defend their slides, pages that hide the gaps in footnotes, and reviews that run long. Expect it to take three or four quarters before units bring their bad news first.

Where it goes wrong

The first failure is the slide parade. Each unit presents everything it did, the good news first and the gaps last, and the time runs out before the asks. Spot it in decks over twenty slides and reviews that end with no decision recorded.

The second is the surprise. A gap appears for the first time at the quarterly review, too late to act on within the quarter. Spot it when the weekly and monthly reviews showed nothing wrong, and fix the reviews below.

The third is the one-sided customer review. The supplier presents its features, its roadmap, and a renewal date, and the customer's goals never come up. Spot it when the customer's executives stop attending and send someone junior, which often comes before a lost renewal. A quarterly cadence also tempts managers toward fixes that make one quarter look good and cost more later, such as orders pulled forward or maintenance put off.

Related and rival frameworks

  • Monthly Business Review. The same review at a monthly beat, closer to operations and quicker to catch a gap. Most companies need both, with the monthly feeding the quarterly.
  • Weekly Business Review. A weekly read of the same operating metrics, built to catch anomalies as they start. Better for fast-moving operations where a quarter is too long to wait.
  • OKR Check-Ins. Weekly reading of key results by confidence. Where a company runs on OKRs, the QBR is often the grading session that closes their quarter.