Catchball

Layers of Management ThoughtLayer 10: Practices and RitualsPracticeAlso known as Catch ball, Vertical and horizontal catchball

A practice of hoshin kanri, the policy deployment that grew out of Japanese quality management in the 1950s and 1960s, with no single author; Yoji Akao's Hoshin Kanri: Policy Deployment for Successful TQM (English edition, 1991) brought the method to English readers.

Passes a proposed objective between levels of an organization, each level answering with what it can deliver and what it needs, until the target, the means, and the resources agree and every level commits.

One objective thrown down and back until it holds

The leadership team proposes cutting order-to-delivery time from twelve weeks to six. At each turn that offers a choice, pick a move: the other side's reply shows, the verdict says why, and the meter tracks how much of the commitment the plant can actually keep. Illustrative.

Leadership team

Plant team

Leadership team

Plant team

Select a stage to read it, or play the exchange.Propose. The leadership team sets the year's breakthrough objective and asks each plant what it can contribute.First answer. The plant team checks the target against its capacity before it answers.Pick a move to see the reply.The objective is filed as agreed.Silent acceptance: the gap surfaces in month nine as a miss.The leadership team asks what it would take to reach 6.An answer with data and a counteroffer starts a real negotiation.Reply. The answer goes back up, and the leaders decide what to change.Pick a move to see the reply.The plant manager agrees in the meeting and plans for 9.A target imposed over the data becomes a number no one owns.With the booth and faster suppliers, the plant offers 7 weeks this year and 6 the next.Changing the means as well as the target closes most of the gap.Pass it on. The plant team takes the 7-week target to its paint, assembly, and purchasing leads, each of whom answers for its share.Pick a move to see the reply.Departments learn their targets from the plan.Skipping the next round hands down a number nobody below has tested.Paint commits to the booth by spring, purchasing to supplier lead times by summer.Each level's commitment now rests on the level below.Agree. The leadership team writes the 7-week commitment, the booth, and the quarterly milestones into the annual plan.

Moves that worked: 0 of 3Moves that worked: 1 of 3Moves that worked: 2 of 3Moves that worked: 3 of 3

Commitment the plant can keep0of 6

  1. Propose (Leadership team). The leadership team sets the year's breakthrough objective and asks each plant what it can contribute.
  2. First answer (Plant team). The plant team checks the target against its capacity before it answers.
    • Accept the 6-week target without comment The objective is filed as agreed. Silent acceptance: the gap surfaces in month nine as a miss.
    • Show that the paint shop caps the plant at 9 weeks, and offer 8 with a weekend shift The leadership team asks what it would take to reach 6. An answer with data and a counteroffer starts a real negotiation.
  3. Reply (Leadership team). The answer goes back up, and the leaders decide what to change.
    • Insist on 6 weeks, since every plant must stretch The plant manager agrees in the meeting and plans for 9. A target imposed over the data becomes a number no one owns.
    • Fund a second paint booth, push suppliers for shorter lead times, and ask again With the booth and faster suppliers, the plant offers 7 weeks this year and 6 the next. Changing the means as well as the target closes most of the gap.
  4. Pass it on (Plant team). The plant team takes the 7-week target to its paint, assembly, and purchasing leads, each of whom answers for its share.
    • Report 7 weeks upward as agreed and tell the departments later Departments learn their targets from the plan. Skipping the next round hands down a number nobody below has tested.
    • Commit 7 weeks only after each lead has answered, with a milestone per quarter Paint commits to the booth by spring, purchasing to supplier lead times by summer. Each level's commitment now rests on the level below.
  5. Agree (Leadership team). The leadership team writes the 7-week commitment, the booth, and the quarterly milestones into the annual plan.

An example

A maker of farm equipment set a breakthrough objective for the year: cut the time from order to delivery from twelve weeks to six. The vice president of operations took it to the assembly plant as a proposal and asked what the plant could commit to.

The plant team came back a week later with data. The paint shop capped output, and with the current booth the best the plant could do was nine weeks, or eight with a weekend shift. The vice president took the answer to the leadership team, which funded a second paint booth and asked purchasing to cut supplier lead times. With those means the plant committed to seven weeks this year and six the next. Before agreeing, the plant manager ran the same exchange with her paint, assembly, and purchasing leads, so each commitment rested on the level below it. By the fourth quarter the plant was delivering in seven weeks, the first stretch target in years met as planned.

The core idea

Catchball is the exchange through which an objective moves between levels of an organization until the target, the means, and the resources agree. A leader proposes an objective and passes it down. The receiving team studies it and answers with what it can achieve, what it would need, and what it proposes instead. The answer goes back up, the leader adjusts the target, the means, or the resources, and the ball goes around again. When the levels agree, each commits to its part and plays the same game with the level below. A horizontal version runs between functions whose work depends on each other.

The insight is that a target is only as real as the plan beneath it. A number handed down without an answer becomes a promise no one believes, and the gap shows up late in the year as a miss. Catchball moves that discovery to the start of the year, when it is still cheap to change the target or fund the means.

The thinking behind it

Japanese hoshin kanri practice from the 1960s Catchball comes from hoshin kanri, the method of policy deployment that grew out of Japanese quality management in the 1950s and 1960s, with Bridgestone Tire among its early users and no single inventor. Yoji Akao's Hoshin Kanri: Policy Deployment for Successful TQM brought the method to English readers in 1991. The Lean Enterprise Institute's glossary describes it as a dialogue between senior managers and the teams doing the work about the time and resources a target needs, named for the way ideas are "tossed back and forth like a ball," and notes that it is also called nemawashi.

Where it sits in the layers

Catchball is a Layer 10 practice, the conversation through which the Layer 8 method of Hoshin Kanri actually runs. It carries the Layer 6 philosophy of Total Quality Management, whose plan-do-check-act cycle hoshin applies to a whole organization's goals, and it shares the instinct of Nemawashi, its neighbor in Layer 10, the habit of building agreement before a decision is announced. In the yearly calendar it follows the annual planning offsite, turning the top team's choices into commitments level by level. The classic mistake is to ask catchball to choose the strategy. It tests and commits to objectives the top team has already set, and when those objectives are unclear the exchange turns into bargaining over numbers.

How organizations put it to work

In companies that use hoshin kanri, the chief executive's office or a small strategy deployment team runs the catchball calendar, and every manager who receives an objective owns the answer for their level. Adoption means a fixed window after the annual plan, often four to eight weeks, in which each level receives proposed objectives with the reasons behind them, answers in writing with what it can deliver, the means it would use, and the resources it lacks, and meets the level above to settle the gaps. A standard one-page form keeps the answers comparable, and horizontal sessions settle what one function needs from another.

It changes decisions and measures. Targets are set with the people who will deliver them, resources move to where the answers show they are needed, and monthly reviews track the commitments each level made.

In the first year, expect timid or padded first answers, since people are not used to being asked, and a longer planning season than before. Leaders have to accept a few lowered targets to show the exchange is real. The return is a plan the organization believes in, fewer surprises in the fourth quarter, and managers who learn to plan their own part.

Where it goes wrong

The first failure is catchball in name only. The target comes down, the answer is expected to be yes, and any pushback is treated as resistance. Spot it when no target changes during the exchange and no resources move.

The second is the padded answer. Teams that fear being held to a stretch learn to offer less than they can deliver. Spot it when every level's commitment is met easily and early, year after year.

The third is endless negotiation. Without a deadline and a leader willing to decide, the ball goes back and forth until the year has started. Spot it when the planning season runs into the first quarter and objectives are still being revised in the second.

Related and rival frameworks

  • Hoshin Kanri. The Layer 8 method that catchball serves, with its annual objectives, its matrix of targets and means, and its monthly reviews.
  • Nemawashi. Builds agreement informally, one conversation at a time, before a decision. Catchball does similar work in a structured round tied to the planning cycle.
  • Management by Objectives. Sets objectives jointly between a manager and a subordinate. Catchball extends that negotiation across whole levels and functions, with resources on the table.

Go to the source

  • Hoshin Kanri: Policy Deployment for Successful TQM, Productivity Press (English edition, translated by Glenn H. Mazur), 1991

Back to the catalog