From Armand V. Feigenbaum's Total Quality Control (1956) and Kaoru Ishikawa's company-wide quality control in Japan, with practices shaped by W. Edwards Deming, Joseph M. Juran, and Philip Crosby; the name total quality management came into use in the mid-1980s.
Makes quality the job of everyone in the organization, managed as a system from supplier to customer, on the reasoning that defects prevented at the source cost far less than defects inspected out or repaired.
Eight costs at one water heater maker, sorted into the four costs of quality
Select a cost, then the box it belongs in: whether it pays for doing the work right or for fixing failures, and how early or late the defect is stopped or found. Show the sort to compare yours. Illustrative.
- Not placedPlacedPreventionAppraisalInternal failureExternal failure
- Not placedPlacedPreventionAppraisalInternal failureExternal failure
- Not placedPlacedPreventionAppraisalInternal failureExternal failure
- Not placedPlacedPreventionAppraisalInternal failureExternal failure
- Not placedPlacedPreventionAppraisalInternal failureExternal failure
- Not placedPlacedPreventionAppraisalInternal failureExternal failure
- Not placedPlacedPreventionAppraisalInternal failureExternal failure
- Not placedPlacedPreventionAppraisalInternal failureExternal failure
What the money buys
Where the defect is stopped or found
Your sort matched 0 of 8.Your sort matched 1 of 8.Your sort matched 2 of 8.Your sort matched 3 of 8.Your sort matched 4 of 8.Your sort matched 5 of 8.Your sort matched 6 of 8.Your sort matched 7 of 8.Your sort matched 8 of 8.
- Prevention
- Money spent so defects never happen: design reviews, training, capable processes. The cheapest quality there is, and the category TQM grows.
- Appraisal
- Money spent checking whether work conforms: inspection, testing, audits. Needed while processes are unreliable; it finds defects and prevents none.
- Internal failure
- Defects caught before the customer sees them: scrap, rework, downtime. Costly, and a sign the process needs prevention.
- External failure
- Defects the customer finds: warranty, returns, service calls. The most expensive kind, because it costs customers as well as money.
The sort
- Training welders: Prevention. Teaching the revised procedure stops bad welds from being made at all.
- Burner design review: Prevention. Catching a leak-prone design on paper costs far less than catching it in the field.
- Final leak test: Appraisal. Testing every finished unit finds leaks but does nothing to stop the next one.
- Incoming valve checks: Appraisal. Inspection of supplier parts: needed while the supplier is unreliable, and a cost of not trusting the process.
- Scrapped tanks: Internal failure. A failure caught inside the plant: materials and labor thrown away.
- Re-welding failed seams: Internal failure. Rework before shipment: the defect was made and then paid for twice.
- Warranty replacements: External failure. The customer found the defect, and the company pays for a new unit plus the damage to its name.
- Service calls for leaks: External failure. Each truck roll to a customer's basement is a failure cost the plant never sees.
An example
A maker of residential water heaters spent heavily on quality and still had a warranty problem: one unit in thirty leaked within its first year. The quality department's budget went almost entirely to inspection, two extra leak tests and a team that re-checked welds, and inspection kept finding more to scrap. A new chief operating officer asked finance to total every cost of quality across every department.
The answer was nearly nine percent of sales, most of it scrap, rework, warranty replacements, and service calls, and less than a tenth of it went to preventing defects. Under a company-wide program, designers, welders, buyers, and service technicians each took responsibility for quality in their own work. Welders were trained on a revised procedure, the burner design went through a formal review with field service, and teams fixed the most frequent leak causes at the source. Within two years warranty claims fell by half, and one of the two extra leak tests was retired.
The core idea
Total quality management treats quality as the responsibility of everyone in the organization, managed as a system from design through service and judged by the customer. Its principles are few. Focus on the customer, internal as well as external. Improve processes continuously, with data and simple statistical tools. Involve every employee, often through teams. Build quality in at every stage, from supplier to service, since inspection at the end can find defects and never prevent them.
The insight that sets it apart is economic. Feigenbaum showed that the costs of quality could be counted in four groups: prevention, appraisal, internal failure, and external failure. In most companies the failure costs dwarf prevention, so spending more on prevention lowers the total. Quality and cost, usually traded against each other, move together once defects are prevented at the source. That is why the approach puts quality in every function's hands: most defects are designed in or bought in long before an inspector sees them.
The thinking behind it
Armand V. Feigenbaum Armand V. Feigenbaum argued in Total Quality Control (1956), in the Harvard Business Review, that quality could not be left to inspectors or a quality department, because every function, from marketing and design through purchasing, production, and service, shapes it. He proposed managing quality as a company-wide system and counting its costs, so that money spent on prevention could be weighed against the much larger cost of failure. He later co-founded General Systems Co., a systems engineering firm, and kept refining the idea for decades.
Kaoru Ishikawa Kaoru Ishikawa promoted what Japanese industry called company-wide quality control, in which everyone from executives to frontline workers studies and improves quality, and he wrote Guide to Quality Control (1968) so that frontline teams could use simple statistical tools themselves. A 1998 history of the term names him and Feigenbaum as perhaps its greatest contributors, and notes that Deming, Juran, and Crosby, who shaped its practices, did not use the name total quality management themselves.
Where it sits in the layers
It sits in Layer 6, the improvement philosophies, because it prescribes what better means for a whole organization: fewer defects, lower cost, and more satisfied customers, pursued by everyone at once. From the layers above it takes the habit of Pragmatism of judging ideas by their results in practice, which its improvement cycles turn into a routine. It supports assessments and tools below. The Baldrige Excellence Framework grew out of the quality movement and scores an organization against its principles, and the PDSA Cycle is the small loop by which teams improve one process at a time. The common mistake is to treat it as a department. When quality belongs to a quality function, the rest of the company stops owning it, which is the opposite of what the philosophy asks.
How organizations put it to work
TQM has to be owned by the chief executive, because its premise is that every function shares responsibility for quality, and only the top can make that true. Its first concrete step is usually the one in the scene: a cost-of-quality study across the whole company, which turns quality from a technical topic into a financial one. Programs then build a few routines. Each process writes down its customers' requirements, including those of internal customers. Every area gets improvement teams trained in simple tools. Purchasing helps suppliers improve their own processes, and management reviews quality measures on a regular schedule.
Structure changes less than habits. The quality department shrinks toward coaching and auditing as line managers take over quality in their own areas, and measures move toward defects, the cost of poor quality, and customer satisfaction. Expect the first year to show quick savings from obvious failures and slower progress after that, as the easy problems run out and the work turns to design and suppliers. Sustaining it takes years of consistent leadership attention. Programs run as campaigns tend to fade once attention moves on, and programs built into the management system keep cutting costs and keep customers longer.
Where it goes wrong
The first failure is the program without the leaders. Training, slogans, and quality teams arrive, while executives keep their attention on output and cost. Spot it when management reviews never discuss defect data.
The second is quality as a department. The new quality office gains staff and the line managers lose ownership, the opposite of the philosophy. Spot it when every quality problem is routed to the quality function.
The third is improvement without focus. Hundreds of teams fix small irritations while the costliest failures, often in design or with suppliers, go untouched. Spot it when the number of projects grows and the cost of poor quality does not fall. Critics note that the term has been defined in so many ways, by academics and practitioners alike, that it means little without a specific program behind it.
Related and rival frameworks
- Six Sigma. A later, more statistical descendant, run as expert-led projects with measured savings. The better pick when variation in specific processes is the problem.
- Deming's 14 Points and System of Profound Knowledge. Deming's management philosophy behind much of TQM, aimed at leaders and the system they run. Better for changing how management itself behaves.
- Crosby's Zero Defects. Crosby's case that quality is conformance to requirements and that doing it right the first time is cheapest. A simpler message for rallying a company.
Go to the source
- Total Quality Control, Harvard Business Review, 1956
- Guide to Quality Control, JUSE; English edition from the Asian Productivity Organization, 1968
- Total Quality Management: Origins and Evolution of the Term, The TQM Magazine 10(5), by Martínez-Lorente, Dewhurst, and Dale, 1998