Developed by the UK Office of Government Commerce (OGC), with version 1.0 dated 2006 on its owner's page, version 2.0 in 2008, and version 3 in 2015, and now owned by AXELOS, the Cabinet Office, and PeopleCert.
Rates how well an organization manages its portfolio of change, its programs, and its projects on five maturity levels across seven perspectives, so that weak spots such as benefits or resourcing show up even where the process looks sound.
A water utility rated on P3M3's seven perspectives, from awareness to optimizing
Each perspective is rated from 1 to 5 against the evidence the utility has. The figure averages the ratings to name an overall level, a simplification of how assessors work. The profile matters more: the weakest perspective sets where to start. Change a rating and read the level and the order. Illustrative.
Management control: every program reports in one format each month
ScoreBenefits management: benefits are in the case and rarely tracked
ScoreFinancial management: costs tracked per project only, never per program
ScoreRisk management: a shared risk register is reviewed monthly
ScoreStakeholder engagement: consulted at the start of each project
ScoreOrganizational governance: the board meets but records no decisions
ScoreResource management: people go to whoever asks first
ScoreOverall level, average of seven2.1
VerdictScore every row to see the verdict.Level 1, awarenessPractice is ad hoc. Pick the one or two perspectives hurting most and make them routine.Level 2, repeatableSome practice repeats from project to project. Define the shared standards, starting with the weakest perspective.Level 3, definedPractice is defined across the organization. Begin to measure how well it works.Level 4, managedPractice is measured and managed against targets. Use the data to decide where to improve.Level 5, optimizingThe organization improves its management of change continuously. Keep testing that it still serves the work.
Perspectives, strongest first
- 3.0Management control: every program reports in one format each month
- 3.0Risk management: a shared risk register is reviewed monthly
- 2.0Benefits management: benefits are in the case and rarely tracked
- 2.0Financial management: costs tracked per project only, never per program
- 2.0Stakeholder engagement: consulted at the start of each project
- 2.0Organizational governance: the board meets but records no decisions
- 1.0Resource management: people go to whoever asks first
An example
A regional water utility ran a capital program of one hundred and forty projects. Every project report was green until the money ran out, and the board asked why. The finance director arranged a P3M3 assessment of how the utility managed its portfolio, its programs, and its projects, scored across seven perspectives: management control, benefits management, financial management, risk management, stakeholder engagement, organizational governance, and resource management.
The overall picture was uneven. Management control and risk were at the third level, with one reporting format and a shared register. Benefits, finance, stakeholder engagement, and governance sat at the second: costs were tracked per project and never per program, and the portfolio board met but did not record its decisions. Resource management was at the first level. People went to whoever asked first, and three engineers appeared in the plans of eleven projects at once. The board chose resource management as the first target. That alone explained most of the missed dates, and it was invisible while every project looked fine by itself.
The core idea
The model has three sub-models, for portfolio, program, and project management, and each is assessed across the same seven perspectives: management control, benefits management, financial management, risk management, stakeholder engagement, organizational governance, and resource management. Each perspective is rated on five maturity levels: awareness of process, repeatable process, defined process, managed process, and optimizing process.
A result is therefore a profile instead of a single grade. An organization can sit at the third level for risk and at the first for resources, and the gap points to where to work. The model draws on the staged logic of the Capability Maturity Model and applies it to the management of change at three scales. The insight is that good project practice does not make a well-run portfolio. A company can run each project properly and still fail on the choice of projects, the sharing of people, and the tracking of benefits, which sit above any one project.
The thinking behind it
The UK Office of Government Commerce (OGC), whose model AXELOS later took over No single author stands behind the model. It originated with the Office of Government Commerce, the UK government body that also stood behind the project and program guides used across British public service. The owner's page dates version 1.0 to 2006, version 2.0 to 2008, and version 3 to 2015, and names AXELOS, the Cabinet Office, and PeopleCert as its owners. Other sources give 2005 as the first release, and the discrepancy is not settled here. The five-level design borrows the pattern of earlier maturity models, in particular the Capability Maturity Model, which evolved into CMMI.
Where it sits in the layers
The model sits in Layer 7, Assessment and Maturity Models, because it rates organizational practice against staged levels and perspectives. From Layer 6 it takes the quality movement's idea, in Total Quality Management, that a managed practice improves stage by stage. Below it, it rates how well methods such as PRINCE2 and MSP in Layer 8 are used, and routines in Layer 10 such as the Monthly Business Review are where portfolio health is read. The common mistake is asking it to choose the method. It rates how well an organization manages across the seven perspectives, and it does not tell a team whether to run a project in phases or in sprints, or how to estimate.
How organizations put it to work
A portfolio office or a head of transformation usually owns it, with an executive sponsor, and formal assessments are usually led by trained assessors, often from outside. Adoption starts with a scope, such as which of the three sub-models to assess, then evidence gathering and ratings by perspective. It changes structure by giving the portfolio, program, and project layers owners for each perspective, and it changes decisions by making benefits and resource availability a condition for starting work. Measures follow: benefits realized against plan, program-level cost, and the share of people committed to more than one project.
Sustaining it takes reassessment on a cycle and a sponsor who reads the weak perspectives and does not settle for the average. In the first year, a leader should expect the portfolio and resource perspectives to rate lower than project management, first improvements that are simple, such as a resource plan across projects, and friction from project managers who lose the right to start work when they please. The return is fewer projects that start without people or a benefit, more predictable delivery, and decisions that depend less on who argues loudest.
Where it goes wrong
The first failure is a rating used as an end in itself. A public body is asked for a target level and prepares evidence for the assessors. The sign is a level that rises while projects keep missing dates for the same reasons.
The second is cost and access. Formal assessments usually bring in outside assessors, and a small organization can find the expense out of proportion to the improvement it buys. The sign is an assessment bought once and never repeated.
The third is the generality of the levels. Seven perspectives at five levels each describe practice in broad terms, and two assessors can read the same evidence differently. The sign is a rating that changes with the assessor. The model also has its roots in public-sector practice and may need translation for companies that organize their change work differently.
Related and rival frameworks
- Organizational Project Management Maturity Model (OPM3). PMI's maturity model for the same three domains. Pick it when the organization works from the PMBOK Guide, and P3M3 when it works from the UK guides.
- PRINCE2. A method for running a single project in controlled stages. It describes the work that P3M3 rates, and it is the better pick when the need is a method more than a rating.
- CMMI. The software-born maturity model that P3M3's staged design resembles. Use it when the subject is how a development organization builds and maintains its products.
Go to the source
- P3M3 (AXELOS ProPath), AXELOS, 2015
- Portfolio, Programme and Project Management Maturity Model (P3M3), Knowledge Train, 2026