Developed inside the UK civil service, whose Central Computer and Telecommunications Agency adapted Simpact Systems' PROMPT II as PRINCE in 1989 and released PRINCE2 for any kind of project in 1996, and owned since 2021 by PeopleCert, which published the seventh edition in 2023.
Runs a project as a controlled sequence of stages under a business case that must stay valid, with a project board that sets tolerances and steps in only when a forecast breaks them.
Manage by exception: inside the board's tolerances the project manager decides, outside them the board does
The project board of an engineering firm's finance-system project set tolerances for the build stage: how far over budget and how late the stage may run before the board must hear about it. The shaded corner is room left in both. Set the tolerances and the project manager's forecast, and see who has to decide. Illustrative.
Where the forecast fallsWithin tolerance: the project manager handles it and reports at the next checkpoint.Exception: the forecast breaks a tolerance, so the project manager sends an exception report and the board decides.
An example
An engineering firm with eleven offices was replacing its finance and timesheet systems, and its last two system projects had overrun by a year each. The new one ran under PRINCE2. A project board of three, the chief financial officer as executive, the operations director as senior user, and the vendor's delivery head as senior supplier, approved one stage at a time and set tolerances for each: ten percent on cost and two weeks on time.
Halfway through the build stage, the project manager forecast a three-week delay from data migration, with cost still inside tolerance. Under the old habits that would have meant weekly crisis meetings. Instead she sent an exception report with three options. The board met once, split migration into its own stage, and rechecked the business case, which led it to cancel a reporting module whose benefits no longer justified its cost. The system went live two months later than the original plan and under budget. The chief financial officer spent a tenth of the hours on it that the last project had taken.
The core idea
PRINCE2 holds that a project is a temporary organization set up to deliver products that justify their cost, and that it should be controlled on that basis. Seven principles anchor it: continued business justification, learning from experience, defined roles and responsibilities, management by stages, management by exception, a focus on products, and tailoring to the project. Seven practices cover the business case, organizing, plans, quality, risk, issues, and progress, and seven processes run from starting up and initiating a project, through directing it and controlling each stage, to closing it.
The insight is the separation of levels. A project board representing the business, the users, and the suppliers owns the decision to invest and approves the project one stage at a time. Within each stage it sets tolerances for time, cost, and other measures, and leaves the project manager to run the work inside them. Only a forecast breach comes back up as an exception. Senior people spend their attention where a decision is actually needed.
The thinking behind it
UK government project management PRINCE2 grew out of the UK civil service. Simpact Systems had built PROMPT, a method for computer projects, and the government's Central Computer and Telecommunications Agency adapted its PROMPT II module for public IT projects, naming its version PRINCE in April 1989. In 1996 the agency released PRINCE2, made generic for any kind of project and shaped with input from about 150 European organizations. The method stayed in the government's best-practice portfolio, which in 2013 moved to AXELOS, a venture of the Cabinet Office and Capita, and in 2021 to PeopleCert. Its seventh edition, in 2023, added explicit attention to people.
Where it sits in the layers
PRINCE2 sits in Layer 8, the methodologies and operating systems, because it names the roles, processes, documents, and decision points of a project down to who approves what. It takes for granted a delegation problem from Layer 3, the one Agency Theory describes, in which an owner must hand work to an agent without watching every move. Tolerances and exception reports are its answer. Its practices rely on tools from Layer 9 such as the Risk Register, and an organization's skill at running it can be assessed with a maturity model from Layer 7 such as P3M3. The common mistake is asking PRINCE2 to choose projects. It governs one project against its business case, and the choice among competing projects belongs to portfolio management.
How organizations put it to work
Adoption is usually led by a project or program management office, with sponsorship from the executive who funds the most projects. The structural change comes first: every significant project gets a project board with a named executive who is accountable for the business case, a senior user, and a senior supplier, and a project manager who reports to that board.
Decisions then move to fixed points. Boards authorize initiation, each stage, and closure, and they set tolerances at each authorization. Between those points the project manager reports by highlight reports and escalates only by exception. The business case is updated at every stage boundary, so a project that no longer pays for itself can be stopped by design.
In the first year a leader should expect a burst of documentation as teams learn the templates, and the need to tailor them to the size of each project. Executives need coaching to stay away from detail inside tolerance and to show up for decisions outside it. The return is projects that stop when they should, and senior time spent on the few decisions that need it.
Where it goes wrong
The first failure is document-driven delivery. Teams produce every management product the manual names, whatever the project's size, and the paperwork becomes the work. Spot it when a small project carries the same documents as a large one, or when tailoring has never been discussed.
The second is the absent board. Executives sign the stage plans and then fail to show up for exceptions, or they micromanage inside tolerance, which defeats the point. Spot it by asking when the board last made a decision that changed the project.
The third is the frozen business case. It is written to win funding and never revisited. Spot it when nobody can say whether the benefits still justify the remaining cost. Critics, especially from agile teams, have long argued that its stage-gated control fits fixed-scope projects better than discovery work, a criticism the later editions answer by allowing agile delivery inside its stages.
Related and rival frameworks
- PMBOK Guide. A broad body of project management knowledge and practices from the Project Management Institute. Describes what project managers should know, where PRINCE2 prescribes how a project is governed.
- Scrum. Runs product work in short cycles with a team that plans its own work. Many organizations use Scrum inside PRINCE2's stages, with the board governing and Scrum delivering.
- Managing Successful Programmes (MSP). The program-level sibling from the same government portfolio. Use it when several projects together deliver one change.
Go to the source
- The History of PRINCE2, ILX Group, updated 2022, 2017
- New deal will market government professional qualifications, UK Cabinet Office, 2013
- PRINCE2 7: a new chapter in a well-told story, PeopleCert, 2023