Developed by the American Institute of Architects (AIA National and the AIA California Council) in Integrated Project Delivery: A Guide (2007), drawing on earlier project alliance contracts from the North Sea oil industry.
A way of delivering large building projects in which the owner, designer, and builder sign one agreement, join the project early, and share risk and reward, so each firm's success depends on the project's success.
Who earns what when a $50 million hospital wing comes in over or under its target cost
Under a cost-plus fee, the designer and builders earn the same $4 million margin whatever the project costs. Under the alliance model the guide describes, margin is paid only if the project meets its target, with a bonus for beating it. Choose the pay model and the actual cost as a share of the $50 million target. Illustrative.
Team margin, $ million
At this cost80%: Well under target. Under the alliance model the team earns its normal margin plus a share of the saving.90%: Under target. The team earns its normal margin and a smaller bonus, so every saving is shared.100%: On target. The team earns its normal margin and no bonus, and the owner pays no more than agreed.110%: Over target. Under the alliance model the team's margin is gone and it is paid its costs only.120%: Well over target. Costs are still paid, the margin stays at zero, and the owner carries the larger overrun.130%: Far over target. The same: the team never risks its direct costs, so the owner bears the catastrophic overrun.
An example
A hospital system was planning a surgical wing, and its last two projects had ended in disputes. The architect blamed the contractor for missing details, the contractor blamed the architect for late drawings, and each party's pay was safe whatever happened to the project as a whole. Change orders were the main source of profit, and the owner paid for each one.
For the new wing, the owner signed one agreement with the architect, the general contractor, and the mechanical subcontractor before the design began. The firms set a target cost together. Their direct costs were guaranteed, but their normal margin was paid only if the project met its target, with a bonus if it came in under. The mechanical subcontractor joined the design meetings in month one and caught a ceiling conflict that would have cost a month of rework. When the wing opened, it finished under the target, the three firms split the saving, and the owner had no claims to settle.
The core idea
Integrated Project Delivery puts the owner, the lead designer, and the lead builder into one team from early design to handover, and ties each firm's reward to the project's result. It can sit inside different kinds of contract, and the team often reaches past those three to engineers and key trades. What sets an integrated project apart is the depth of that collaboration and how early it begins.
The guide gives nine principles: mutual respect and trust, mutual benefit and reward, collaborative innovation and decision making, early involvement of key participants, early goal definition, intensified planning, open communication, appropriate technology, and organization and leadership. The structural device is the multi-party agreement: one contract, signed by all the main participants, that fixes what each must do and what each answers for. Pay is tied to project success, so no firm can win while the project loses. The insight is that much construction waste comes from hand-offs between firms with separate interests, and the remedy is to write a shared outcome into the contract.
The thinking behind it
Collaborative contracting in construction, set out by the American Institute of Architects The AIA's 2007 guide, written by practitioners from architecture, construction, and law, pulled the practice together and named it, presenting it as a way to get better results for the owner with less waste at every stage from design to construction. Its multi-party agreements draw on earlier forms, among them the project alliances of North Sea oil exploration. There the owner guaranteed the other parties' direct costs, while their profit, overhead, and bonus depended on the project's outcome, and the parties made major decisions by facilitated consensus.
Where it sits in the layers
Integrated Project Delivery lives in Layer 8, Methodologies and Operating Systems, as a prescribed way to organize and contract one kind of work. It takes for granted the problem agency theory describes in Layer 3, that parties with separate incentives pull apart, and the improvement logic of Lean Thinking in Layer 6. It pairs with the Last Planner System for day-to-day planning on site, and draws on the planning and review routines of Layers 9 and 10. The common mistake is asking it to supply discipline that a contract cannot. Shared incentives help, but a team without planning skill and open communication will fail inside a well-written agreement.
How organizations put it to work
The owner usually owns the approach, because the owner chooses the delivery model and signs the agreement. Adoption changes structure, since the firms form a temporary organization with a joint management group, and it changes contracting, with direct costs reimbursed and profit placed at risk against shared goals. It changes decisions: key firms join before design is complete, and big choices are made by the team, ideally unanimously. It changes routines, as the team plans more intensely early on and meets in a shared space.
The measures are agreed project goals, such as cost to target and duration to schedule, and the compensation formulas that tie to them. The guide notes that quantifying outcomes, deciding when and how they are measured, and writing the reward formulas are the hardest parts.
Sustaining it takes trust, open books, and an owner who lets the team decide. In the first year of a first project, expect a long setup and costly negotiation, a good deal of early friction between firms used to opposing each other, and the biggest gains in the design phase. A business that builds this way carries less risk of disputes and cost overruns and depends less on one heroic project manager.
Where it goes wrong
The most common failure is an agreement without a changed relationship. The firms sign the document and behave as before, with each protecting its own scope, and the shared pool becomes another line to argue about. The sign is change orders and claims that look like those on a traditional project.
Close behind is the cost of setup. The guide itself says the planning, negotiation, and team building can be costly, and that the overhead is easy to absorb on a large project and heavier on a small one. The sign is a modest project spending a large share of its budget on the agreement.
Last is poorly framed goals. If the success measures are vague or the formulas reward the wrong things, the team will optimize for the formula. The sign is a team that hits its cost target while quality or schedule slips.
Related and rival frameworks
- Last Planner System. A weekly planning method that suits the same shared-commitment team. The better pick when the problem is weekly coordination.
- Lean Thinking. The philosophy of reducing waste and improving flow behind IPD. Read it when the question is how to improve the work itself.
- PMBOK Guide. A general body of knowledge for managing projects of any kind. Choose it when no shared-risk contract is possible.
Go to the source
- Integrated Project Delivery: A Guide, AIA National and AIA California Council (version 1), 2007