Developed from 1957 by the US Navy's Special Projects Office and the consulting firm Booz, Allen and Hamilton for the Polaris missile program, in a team led by Wil Fazar, and set out in D. G. Malcolm, J. H. Roseboom, C. E. Clark, and W. Fazar's 1959 paper in Operations Research.
A planning technique that models each activity's duration as three estimates, optimistic, most likely, and pessimistic, then finds the chain of activities that governs the finish and the probability of meeting a given date.
A three-task release plan, with the last task's estimate as three numbers instead of one
Design and build are fixed at 10 and 14 days most likely. Set the optimistic, most likely, and pessimistic times for the testing task. The chain's expected length is longer than the sum of the most likely times, and the date with about an 84 percent chance of being met is longer again. Illustrative.
An example
A software company's release plan listed a single duration for each task, and the sum of the most likely times said thirty days. The release team had missed every plan of that kind. The program manager asked each lead for three numbers per task: the least it could take, the most likely time, and a pessimistic time if things went poorly.
The testing lead said four, six, and sixteen, because testing always turned up something. Averaged with the usual weights, the testing estimate came to seven days against the six most likely, and across the three tasks in the chain the expected length was thirty-four days. The spread was wide enough that a date with a good chance of being met was nearly thirty-eight. The manager gave the business thirty-eight days and said that thirty was possible but unlikely. The release shipped on day thirty-six, and the business had arranged its launch around the later date.
The core idea
PERT asks for three estimates of each activity: an optimistic time, a most likely time, and a pessimistic time. The original models took the optimistic and pessimistic figures as limits that would be bettered or exceeded about one time in a hundred. The expected duration is a weighted average, the optimistic time plus four times the most likely time plus the pessimistic time, divided by six. Delay being more common than speed, the expected time usually exceeds the most likely.
The activities are drawn as a network, and the path of longest expected duration governs the finish. The spread of each activity is approximated as the pessimistic time minus the optimistic, divided by six. To combine activities along the path, the variances add, and the square root of the total gives the spread of the whole path. From that, a manager can state a date with a given chance of being met, such as about 84 percent. The insight is that a schedule is a range of outcomes, and a single date hides how wide the range is.
The thinking behind it
Wil Fazar PERT was developed from 1957 for the US Navy's Special Projects Office, which ran the Polaris fleet ballistic missile program, by a team of Navy staff and Booz, Allen and Hamilton led by Wil Fazar. Work began on January 27, 1957 as the Program Evaluation Research Task, renamed the Program Evaluation Review Technique by July. Its first description called for knowing the exact order of the activities and estimating each one's duration with care, ideally as a probability. The method is set out in a 1959 paper by D. G. Malcolm, J. H. Roseboom, C. E. Clark, and W. Fazar in Operations Research. By one historian's account the team also coined the term critical path.
Where it sits in the layers
PERT is placed in Layer 8, Methodologies and Operating Systems, in the family of scheduling methods, though in use it is a technique within a larger project method. It takes for granted the layers above: that work can be broken into activities with dependencies, and that uncertainty can be estimated and managed, ideas from the improvement philosophies in Layer 6. It supports the plans that Earned Value Management measures against, and it feeds tools such as the Gantt chart and the critical path method. The common mistake is asking it to manage the work as it unfolds. It estimates a schedule's range before the project starts, and says little about how to respond when reality departs from it.
How organizations put it to work
A project scheduler or planning office usually owns it, working with the leads who supply the estimates. It changes the planning conversation more than the structure: leads are asked for a range of outcomes, and the program manager reports a date with a stated confidence. It changes decisions, since commitments to customers or the board are set at a confidence level the organization chooses, and routines, with the network updated at reviews as estimates change.
The measures are the spread of the estimates, how often actual durations fall within them, and the gap between the most likely total and the expected total. Sustaining it takes estimators who give honest ranges, which depends on leaders who do not treat a pessimistic figure as a lack of commitment.
In the first year, expect wide ranges, a schedule that looks longer than the one the company used before, and the first real discussion of which activities carry the uncertainty. The business gains commitments that are met more often and depends less on a project manager's optimism.
Where it goes wrong
Failure often starts with garbage in. Estimating the ends of a range is hard, and without data, optimistic and pessimistic figures are guesses. The sign is estimates that sit in a narrow band and still miss.
It also comes from the arithmetic. The standard approximation tends to give a more optimistic average than a triangular distribution, and the method underestimates the length of a project when paths merge, because activities off the longest path are ignored even though any of them can delay the finish. Its own authors promised a follow-up that proved intractable beyond two merging paths. The sign is a project that finishes later than the stated 84 percent date more often than one time in six.
And there is its age. It was built for 1950s computing and for research and development, and Monte Carlo simulation handles the same questions with fewer assumptions.
Related and rival frameworks
- Critical Path Method. Schedules activities with a single duration each and finds the longest path. The better pick when durations are well known, as in repeated work.
- Monte Carlo Simulation. Runs the network many times with sampled durations and reads the finish as a distribution. Better when paths merge or the estimates are uncertain; see Monte Carlo simulation.
- Gantt Chart. A picture of the schedule over time. Use it to show the plan once the durations have been chosen.
Go to the source
- Application of a Technique for Research and Development Program Evaluation, Operations Research 7(5), 646 to 669, 1959