Gantt Chart

Layers of Management ThoughtLayer 9: Tools and TechniquesToolAlso known as Gantt bar chart, Progress chart

Developed by Henry Gantt, whose 1903 paper A Graphical Daily Balance in Manufacture, 1910 book Work, Wages, and Profits, and 1919 Organizing for Work describe his charts, and set out as a working tool in Wallace Clark's The Gantt Chart (1922); the Polish engineer Karol Adamiecki devised a comparable schedule chart, the harmonogram, described by Edward Marsh in 1975.

Shows tasks as bars along a time axis and sets the work planned beside the work done in the same space, so a manager sees what is ahead of plan, what is behind, and which task to chase.

Work planned and work done, in the same space, for five workstreams of a system launch

Each bar is how much of a workstream is done, and the dashed line marks how much the plan said would be done by now. Set the progress of each workstream and find which one threatens the launch: testers finish 10 points a week and five weeks remain. Illustrative.

100%
75%
30%
30%
20%
Workstreams behind plan
2 of 5
Largest gap to plan
20 points
Does testing finish before launch?
No: at 10 points a week, testing runs past the launchYes: testing finishes in time

Done so farPlanned by now

0%25%50%75%100%100%75%30%30%20%DesignBuildTestTrain staffLaunch comms0%25%50%75%100%100%75%30%30%20%DesignBuildTestTrainstaffLaunchcomms

An example

A program manager running a system launch reported every workstream as green for six weeks. The steering group asked for something more exact, and she redrew the plan as a chart of five bars, one for each workstream. In the same space as each bar she marked the share of the work scheduled to be done by that date and, beside it, the share actually done.

Design was finished, and build ran a few points behind. Testing was planned to be half complete and stood at thirty percent. Training and launch communications sat on plan. The picture showed what the green labels had not: testing was behind on the task the launch depended on, and at the pace of the testers it would run past the launch date by two weeks. The steering group moved two testers from build, and the following week's chart showed the gap closing.

The core idea

Wallace Clark's 1922 book states the principle behind Henry Gantt's charts: "a division of space represents both an amount of time and an amount of work to be done in that time." A horizontal line through that space then shows how much was actually done against how much was scheduled, and Clark held that this is what sets the Gantt chart apart from every other chart: plan and performance share one space.

The chart most people draw today is a later form of the same idea. Tasks are listed down the left side, time runs across the top, and each bar's length shows its duration. Shading marks progress, a vertical line marks today, and project software adds arrows for dependencies. The value lies in what the chart forces. It requires a plan, makes the plan visible to everyone, and compares what is done with what was planned, so a shortfall is seen early and has a name on it. Clark also counted its compactness: one sheet carries what would take 37 sheets of ordinary curve charts.

The thinking behind it

Henry Gantt Henry Gantt (1861 to 1919) was an American engineer and consultant who wrote about graphical control of production from at least 1903, when he presented a paper called A Graphical Daily Balance in Manufacture to the American Society of Mechanical Engineers. His 1910 book Work, Wages, and Profits shows colored charts of workers' task and bonus records, and his 1919 Organizing for Work describes a system of progress charts. In 1917 General William Crozier, the Chief of Ordnance, retained him as a consultant on production at the Frankford Arsenal and in the Ordnance Department. Wallace Clark's The Gantt Chart (1922) set out the principle of the chart and the way to draw it.

Where it sits in the layers

The Gantt chart sits in Layer 9, Tools and Techniques, as a picture of a plan that any method can borrow. It is a standard part of the planning practice in PMBOK in Layer 8, where it displays a schedule built from a work breakdown. It shows the sequence that Critical Path Method scheduling computes, and it supports the plan-against-actual comparison of Earned Value Management. Below, it is read in the weekly status meetings of Layer 10. The common mistake is asking it to do the scheduling. A bar chart displays durations and dates someone has already decided. It does not find the longest path, test whether resources are available, or say which delay endangers the finish.

How organizations put it to work

Ownership sits with the project manager or the project office. The chart is built from a work breakdown: each task has an owner, a duration, and its dependencies, and the first version is saved as a baseline. Progress is updated on a set rhythm, usually weekly, and the status meeting looks at the actual bars against the baseline.

What changes in the organization is the habit of reporting against a plan in a shared picture. Task owners are named on the chart, slips appear with a date and a person, and discussions about resources and priorities start from the same page. The measures are schedule variance, share of tasks complete against plan, and the slip on the tasks that sit on the longest path.

Sustaining it takes honest updates and a discipline of keeping the chart as detailed as the decisions it supports. In the first year a leader should expect a chart that grows too detailed to read, status reports that go green until a sudden red, and more useful conversations once progress is judged on finished output, whatever share of the time has passed.

Where it goes wrong

The first failure is false precision. Dates on a bar suggest certainty the estimate does not have. The sign is a schedule with every task in whole days and no allowance for the range of outcomes.

The second is progress by guesswork. Percent complete is easy to overstate, and a task sits at ninety percent for weeks. The sign is bars that fill steadily and then stall near the end.

The third is clutter. Charts with every dependency drawn become unreadable, and a network diagram shows the relationships among tasks more clearly. The sign is a chart that nobody reads and one person maintains.

The fourth is treating the baseline as the truth. A plan changed silently every week gives a chart that always looks on time. The sign is a project that has never been behind according to its own chart, though it has missed its date twice.

Related and rival frameworks

  • Critical Path Method. Computes which sequence of tasks sets the finish date. Better when dependencies and delay risk drive the project, and the bar chart only draws the result.
  • Work Breakdown Structure. Divides the whole scope into tasks and deliverables. Better to build first, since a Gantt chart is only as complete as the breakdown beneath it.
  • Burndown and Burnup Charts. Tracks work remaining against time for iterative work. Better when scope is flexible and a fixed list of dated tasks does not fit.