MoSCoW Prioritization

Layers of Management ThoughtLayer 9: Tools and TechniquesToolAlso known as MoSCoW, MoSCoW method, Must, Should, Could, Won't

Developed by Dai Clegg in 1994 for rapid application development, in the book he wrote with Richard Barker, Case Method Fast-Track: A RAD Approach, and later made a standard technique of the DSDM method.

Sorts requirements into must have, should have, could have, and won't have this time, so a team fixes in advance what a timebox guarantees and what gives way first when time runs short.

Six requirements for a 40-day booking launch: what is a must?

The six requirements add up to 42 days of work and the team has about 40. The first sort, shown here, makes calendar sync a must. Set each one to Must, Should, Could, or Won't, and watch the share of effort tied up in musts; a typical guide is no more than 60 percent. Illustrative.

Must
Should
Must
Must
Could
Won't
Share of planned effort in musts
68%
Share of planned effort in coulds (the contingency)
18%
Can the plan absorb a slip?
No: too many musts leave no room for a slipYes: the musts fit within the guide

Share of planned effortA typical split

0%25%50%75%100%68%13%18%MustShouldCould0%25%50%75%100%68%13%18%MustShouldCould

An example

A clinic group's app team had about forty working days to launch online booking and six requirements that added up to forty-two. Every stakeholder insisted that their requirement was essential. The facilitator asked of each whether the launch would be pointless, unsafe, or illegal without it. Booking and appointment confirmation passed, and so did the card deposit that cut no-shows. Text reminders and calendar sync were important and had workarounds, so they became should haves.

The customer reviews page was a nice extra and a could have. Dark mode went on the list as a won't have this time, written down so nobody had to wonder. The musts came to 20 days of the 38 planned, about half. When a payment integration slipped by six days, the team dropped the reviews page, kept the date, and shipped every must and both shoulds. Nobody had to argue about what to cut, because the order had been agreed.

The core idea

MoSCoW sorts requirements into four classes. Must haves are the ones without which delivery would be pointless, unsafe, or unlawful, and the project guarantees them. Should haves matter, and leaving one out hurts, but the solution still works, perhaps with a workaround. Could haves are welcome extras, and they go first when time runs short. Won't haves are recorded as out of this timebox, so nobody wonders whether they are coming. The lowercase o's only make the word pronounceable.

The method works through effort guidelines. The DSDM framework suggests that must haves take no more than about 60 percent of the effort on a typical project, with could haves around 20 percent to serve as contingency. The idea is that time and cost stay fixed and scope flexes, and the plan itself holds the slack. A team that agrees the order in advance can absorb a slipped task by dropping the lowest items, without a negotiation under pressure.

The thinking behind it

Dai Clegg Dai Clegg developed MoSCoW in 1994 for rapid application development, and the scheme appears in Case Method Fast-Track: A RAD Approach, which he wrote with Richard Barker and which Addison-Wesley published that year. The problem it answered was the endless dispute over scope in fast, fixed-time projects, where every stakeholder calls their request essential. Clegg's answer was to name the categories and let the plan decide. The Dynamic Systems Development Method later made it a standard technique, and its framework page defines the four categories and applies them at the level of a project, an increment, and a timebox.

Where it sits in the layers

MoSCoW sits in Layer 9, Tools and Techniques, as a way to sort requirements that a team can apply to any backlog or scope list. It carries out the stance of the Agile Manifesto in Layer 6 that plans give way to change, since it fixes time and flexes scope. It is a core technique of DSDM in Layer 8, and it is applied in Layer 10 at Backlog Refinement, where the team readies the next items. The common mistake is asking it to rank items within a class or to measure value. MoSCoW classifies how necessary an item is and does not say which should-have is worth more than another. Those questions call for the scoring methods or customer research that sit beside it.

How organizations put it to work

The product owner or business sponsor owns the priorities, and the delivery team helps by sizing. At the start of each timebox, the team assigns a priority to every requirement, and DSDM keeps priorities at three levels: for the project, for the increment, and for the timebox. A short rule, such as the launch-day question the team above asked, keeps the musts honest.

What changes is how scope is managed. Time and cost are fixed, and scope flexes in the lower classes. The plan checks the effort in each class against the guideline, with must haves at no more than about 60 percent and could haves near 20 percent, so that contingency exists by design. The measures are the share of must haves delivered, how much of the could-have pool was used, and how often the must list changed during the timebox.

Sustaining it takes a sponsor who defends the definition of must. In the first year a leader should expect inflation, with stakeholders arguing that everything is a must, and a better rhythm once the first slipped task is absorbed without a crisis.

Where it goes wrong

The first failure is must inflation. When stakeholders learn that only musts are guaranteed, everything becomes one. The sign is must haves above the 60 percent guideline, which leaves no slack for the first slip.

The second is classes with no sizing. A list sorted into four classes without effort estimates cannot show whether the musts fit the time. The sign is a plan whose must haves alone exceed capacity.

The third is a stale sort. Priorities from the start of a project are rarely right three timeboxes later, and the sign is a won't have that has become urgent because nobody revisited it.

The fourth is reading won't as never. The category means not in this timebox, and stakeholders who hear a rejection stop engaging. The sign is a won't-have list that stakeholders stop reading. The scheme also gives only four ranks, so it cannot compare two items in the same class.

Related and rival frameworks

  • DSDM and AgilePM. The method that makes MoSCoW a standard practice, with timeboxes and a fixed time and cost. Better to read for the wider framework around it.
  • Kano Model. Classifies features by how customers react to them. Better when the question is what delights users, and MoSCoW answers what the project must guarantee.
  • RICE Scoring. Ranks items by reach, impact, confidence, and effort. Better when a team needs a full order within a class and has data to score with.