Cone of Uncertainty

Layers of Management ThoughtLayer 9: Tools and TechniquesToolAlso known as Funnel curve, Funnel of uncertainty

The funnel shape goes back to H. C. Bauman's 1958 paper on the accuracy of capital cost estimates; Barry Boehm drew it for software, as the funnel curve, in Software Engineering Economics (1981), and Steve McConnell brought it to wide notice as the cone of uncertainty and is reported to have later called it a best case.

Pictures how the range of reasonable estimates for a project's cost or duration is widest at the start and narrows only as decisions are made and unknowns are resolved, so early single-number estimates are far less certain than they look.

A 12-month estimate: how wide is the honest range at each stage?

A project is estimated at 12 months and the range starts a factor of four either way. Choose the stage the project has reached, and whether the team actively worked to remove its unknowns or just let time pass. Find the stage at which a date is safe to promise. Illustrative.

Requirements
Actively resolved
Fastest reasonable finish
4.2 months
Slowest reasonable finish
33.9 months
Can a date be promised?
No: the range is too wide for a dateNearly: promise a window, not a dateYes: the range is narrow enough for a date

Fastest reasonable finish (months)Slowest reasonable finish (months)The point estimate

02040346812ConceptRequirementsDesignBuildTest02040346812ConceptRequirementsDesignBuildTest

An example

A logistics company approved a new routing platform and the sponsors asked for a delivery date the same day. The program manager gave one estimate, twelve months, and it went into the plan and into promises to customers as a date. A senior engineer drew the funnel on a whiteboard. At the idea stage, the real duration could land anywhere between a quarter of the estimate and four times it, which meant anywhere from three months to four years.

Sponsors did not like the picture and could not argue with it. They agreed to treat the twelve months as a midpoint, to commit to customers only after the design work, and to spend the early months on the questions that kept the funnel wide: how the platform would connect to carrier systems and how routing rules would be handled. By the end of design the range had narrowed to six to twenty-four months, and the company gave customers a launch window and set the date after the build began.

The core idea

The cone of uncertainty is a picture of estimation error over a project's life. At the start, with only an idea and a rough scope, the true cost or duration may land anywhere in a wide band around the point estimate: Boehm's early drawing put it within a factor of four on either side. As requirements settle, design is chosen, and pieces are built, the band narrows toward the end, where the outcome is known. A funnel lying on its side is the whole picture.

The point is what the cone says about the use of estimates. An early number is the midpoint of a wide range, and a date promised at that stage is a bet. The range narrows only through decisions and learning, so it makes sense to spend early effort on the biggest unknowns and to commit later. McConnell is reported to have called the cone a best case, reached only on a well-run project, and late scope decisions can widen it again.

The thinking behind it

Barry W. Boehm The idea began outside software, in chemical engineering. H. C. Bauman's 1958 paper in Industrial and Engineering Chemistry examined the accuracy of capital cost estimates. Barry Boehm drew the same funnel for software and called it the funnel curve in Software Engineering Economics (1981), on page 311. A footnote there says the ranges were determined subjectively, to represent 80 percent confidence limits within a factor of four on either side. The problem it addressed was how to explain to managers why early software estimates miss so widely.

Steve McConnell Steve McConnell brought the diagram to wide notice in the 1990s under the name it carries now; Little's 2006 article credits him with popularizing the term in 1996. He returned to estimation at length in Software Estimation: Demystifying the Black Art (2006). When Todd Little's 2006 article in IEEE Software published project data whose range of error hardly narrowed, McConnell is reported to have answered that the cone describes a best case, and that a poorly run project lives under a cloud of uncertainty.

Where it sits in the layers

The cone of uncertainty sits in Layer 9, Tools and Techniques, as a piece of estimation literacy that any manager can carry. It takes for granted the view from PMBOK in Layer 8 that plans are estimated in stages and refined, and it fits the preference of the Agile Manifesto in Layer 6 for responding to change and learning in short cycles over committing to a long plan up front. In Layer 10 it shapes Sprint Planning, where a team commits only to the near term. The common mistake is asking it to give a number. The cone says how wide the range is and does not say where inside it the answer lies, and it does not tell a manager how to reduce the range. That takes decisions and prototypes.

How organizations put it to work

Ownership sits with the program or project office, with finance as a partner. The first change is a policy on how estimates are reported: a single number is never given without its range and the stage of the project it belongs to. Budgets and dates are then tied to stages. Early funding covers discovery, and a full commitment waits until the major unknowns are resolved.

The routines follow the stages. Each gate review restates the estimate, with the range and what was learned since the last gate. The team picks early work by how much uncertainty it removes. The measures are estimate accuracy by stage, the width of the range at each gate, and the share of projects that meet a date promised at a given stage.

Sustaining it takes sponsors who accept ranges and a record of past estimates against outcomes. In the first year a leader should expect pushback from people who want one number, a few uncomfortable gate reviews when the range does not narrow, and more credible commitments to customers.

Where it goes wrong

The first failure is believing the narrowing is automatic. Time passing does not shrink the range, and decisions do. The sign is a project in its sixth month whose range is as wide as it was in the first.

The second is treating the numbers as data. Boehm's factors were subjective, and Todd Little's 2006 data from one company showed error skewed toward lateness and a range that barely narrowed. The sign is a portfolio where actual outcomes sit in the upper half of every range.

The third is using it as a reason never to commit. A wide range is a reason to choose what to learn first. The sign is a team still quoting the concept-stage range in its build phase.

The fourth is forgetting that scope changes reopen the funnel. A late addition widens the range again, and the sign is an estimate that stays fixed while the scope grows.

Related and rival frameworks

  • Monte Carlo Simulation. Turns uncertain inputs into a distribution of outcomes. Better when a team has ranges for its tasks and needs a calculated range for the whole.
  • Risk Register and Risk Matrix. Logs the specific risks behind the width of the range, with owners. Better for acting on the unknowns the cone says to attack first.
  • Walking Skeleton. Builds a thin end-to-end version early to answer the architectural unknowns. Better as a way to make the cone narrow sooner.