Sprint Planning

Layers of Management ThoughtLayer 10: Practices and RitualsPracticeAlso known as Sprint planning meeting, Iteration planning

An event of Scrum, which Ken Schwaber and Jeff Sutherland first presented in 1995, and whose Scrum Guide recast the event's selection as a forecast in 2011, made it one event with a Sprint Goal in 2013, and added the question of why the sprint is valuable in 2020.

Opens each sprint by settling why it matters, what the team can finish, and how, so the team commits to one goal and treats the chosen items as a forecast it can adjust.

A sprint forecast cut against the ordered backlog, and what it leaves for the Sprint Goal

The bars are the backlog's running total in the product owner's order; the line is the team's forecast, its recent average output times the share of days it will have. Items whose bar sits under the line fit. Change the availability and watch what fits, and whether the goal's three items are safe. Illustrative.

30
80%
Forecast for this sprint
24 points
Items that fit, in order
4 of 6
The Sprint Goal
At risk: the goal's own items exceed the forecastCovered, with little room for surprisesCovered, with room for one surprise

Running total of points, in backlog orderForecast

01020304081316182631Goal items end hereSwap requestOfficeapprovalSwap noticeCalendar bugVisit-hoursexportNew loginpage01020304081316182631Goal items end hereSwap requestOffice approvalSwap noticeCalendar bugVisit-hours exportNew login page

An example

A six-developer team building a scheduling app for home-care agencies opened a two-week sprint with planning on Monday morning. The product owner proposed the sprint's purpose, letting caregivers swap a visit without phoning the office, and the team turned it into a one-sentence Sprint Goal. Then it forecast. It had finished 26, 34, and 30 points in its last three sprints, an average of 30, but one developer would be away for a week and Thursday was a holiday, leaving about 80 percent of its usual days. The forecast came to 24 points.

Taking items in the product owner's order, the three swap items and a small calendar bug fit, 18 points in all. The visit-hours export did not, and stayed at the top of the backlog. The developers broke each chosen item into tasks of a day or less. Midway through the sprint the swap request ran long, and because the plan had six points of room, the goal was met without overtime.

The core idea

Sprint planning opens every sprint in Scrum. The whole Scrum Team takes part, and the event settles three things in turn. First comes why the sprint is worth running: the product owner suggests what the product could gain this time, and the whole team turns that into a one-sentence Sprint Goal. Next comes what can be done: the developers choose items from the top of the ordered backlog, judging how much they can finish from their recent output, the days they will actually have, and their definition of done. Last comes how the work will get done: the developers break each chosen item into work, often tasks of a day or less, and that plan is theirs alone.

The goal, the chosen items, and the plan together make up the sprint backlog. The selection is a forecast, and the goal is the commitment. That split is the practice's central idea: scope can flex as the sprint teaches the team something, while the purpose holds, so stakeholders get a dependable result without anyone pretending the estimate was exact.

The thinking behind it

Ken Schwaber Ken Schwaber first presented Scrum with Jeff Sutherland at the OOPSLA conference in 1995, and the two have defined it in The Scrum Guide since 2010. Two early revisions shaped planning. In 2011 the guide dropped the developers' promise to finish everything planned and called their selection a forecast, open to revision as the sprint went on. In 2013 the guide folded planning into a single event about what to build and how, and made the Sprint Goal part of it, so that the sprint's separate pieces of work pulled in one direction.

Jeff Sutherland Jeff Sutherland, co-author of each version, kept the event at the center of the 2020 guide and gave it a third topic, why the sprint is valuable, placed before what and how. The answer is the Sprint Goal, which the 2020 guide made the formal commitment of the sprint backlog. The same edition sets the event's limit at eight hours for a month-long sprint and less for shorter ones, and leaves the method of planning the work to the developers alone.

Where it sits in the layers

Sprint planning is a practice of Layer 10, the event where Scrum in Layer 8 turns a backlog into the next few weeks of work. It assumes what the Agile Manifesto holds in Layer 6, that plans should be short and open to revision, and it depends on Backlog Refinement beside it in Layer 10, which hands it items small and clear enough to choose. Its forecasts lean on Layer 9 instruments such as the Burndown Chart and a team's record of finished work. The common mistake is asking sprint planning to decide what the product is for. A planning session can choose the next step toward a goal, but asked to settle direction as well, it overruns and the Sprint Goal shrinks into a task list. Direction belongs to the product goal and the roadmap above it.

How organizations put it to work

Sprint planning is owned by the Scrum Team. The product owner brings the ordered backlog and a proposed purpose, the developers choose the work and plan it, and the Scrum Master keeps the event within its timebox. It works when refinement has done its job beforehand, when capacity is counted honestly (leave, holidays, support duties), and when the team bases its selection on recent output.

For the wider organization, the change is in what gets promised. Stakeholders are promised a goal every sprint, and the scope behind it is understood as a forecast that can move. Managers stop assigning tasks to individuals, since the developers decide how the work gets done. Useful measures are how often sprint goals are met, how much of the selected work is finished, and how steady the team's output is from one sprint to the next.

In the first year, expect overfilled sprints, goals that read like task lists, and pressure from stakeholders to treat the forecast as a contract. The return is a delivery rhythm the rest of the business can plan around, with fewer surprises at the end of each sprint.

Where it goes wrong

The first failure is planning to full capacity. The team fills the sprint to its best-ever output, leaves no room for the unexpected, and misses the goal whenever anything slips. Spot it when sprints routinely end with unfinished items carried over.

The second is the goal as a list. The Sprint Goal restates the chosen items, so nothing tells the team what to protect when work runs long. Spot it when the goal is a string of features joined by and, or when no one can say which item would be dropped first.

The third is planning by assignment. A manager or the product owner picks the work and hands out tasks, and the developers stop owning the forecast. Spot it when estimates arrive with the backlog, before the developers have seen the items. Points also lose their meaning once they are compared across teams or rewarded: teams inflate them, and the forecast loses its anchor.

Related and rival frameworks

  • Backlog Refinement. Prepares the items planning chooses from. Without it, planning turns into a long session of clarifying and splitting.
  • Sprint Review. Closes the sprint by inspecting what was built with stakeholders, and its findings reorder the backlog that the next planning draws on.
  • PI Planning. Plans many teams' work together for eight to twelve weeks. The better pick when teams depend on each other too much to plan alone.