Burndown and Burnup Charts

Layers of Management ThoughtLayer 9: Tools and TechniquesToolAlso known as Burndown chart, Burnup chart, Sprint burndown, Release burndown

Described by Ken Schwaber in 2000, while he was working at Fidelity Investments, as a simple tool for Scrum teams, and documented by him on his website; the Agile Alliance's glossary calls it original to the Scrum community.

A chart of work remaining against time, updated daily with an ideal line to the end date, that shows whether a sprint or release is on course to finish and how fast the remaining work is shrinking.

A ten-day sprint of 40 points: what the burndown shows when scope changes

The team finishes the same number of points each day. Set that pace and the points of work added on day 5, and compare the line with the ideal one. The burndown can end above zero even when the team worked at full speed. Illustrative.

4 a day
8 points
Work remaining on day 10
8 points
What the line suggests
Ahead of plan: everything is done earlyOn plan: the sprint finishesBehind plan: some work remains
Scope added midsprint (hidden inside the line)
8 points
Share of everything in scope that is finished
83%

Remaining (burndown)Ideal line

0204060Day 0123456789Day 100204060Day0123456789Day10

An example

A team of nine started a ten-day sprint with 40 points of work and posted a burndown chart on the wall. On day five a stakeholder asked for an extra integration worth 8 points, and the team agreed. The line jumped up by 8 and then kept sloping down at the same pace. On day ten it stood 8 points above zero, and a manager reading it from across the room concluded that the team had fallen behind.

The Scrum master added a second view, a burnup chart with two lines: work finished and total scope. It showed a steady pace of 4 points a day, 40 points finished in all, and a step in total scope on day five. The conversation changed from why the team was slow to what the extra integration had displaced. After that, any addition to a sprint was traded against something taken out, in plain view.

The core idea

A burndown chart shows the work left to do, day by day, against a calendar that runs out to the end date. An ideal line runs from the starting amount down to zero at the end date, and the team's actual line is updated each day. The slope shows pace. A line above the ideal one means the team is behind, a flat line means nothing is finishing, and a jump upward means work was added or re-estimated. A sprint burndown covers one iteration and a product burndown covers a release or a whole project.

The burnup chart is the variant that turns the picture upside down. It plots work completed rising over time, with a separate line for total scope. The difference matters because a burndown shows only what remains, so a change in scope is hidden inside the same line as a change in pace. A burnup keeps the two apart. The idea behind both is visibility: a team and its stakeholders see status at a glance, without a report.

The thinking behind it

Ken Schwaber Ken Schwaber devised the burndown chart around 2000, by the Agile Alliance's account, while he was at Fidelity Investments and wanted an easy kit of tools for Scrum teams; he later wrote it up on his own website. He had published his SCRUM Development Process paper in 1997. The chart answered a practical problem: how a team and its sponsors can see progress against a time box without waiting for a status meeting. The Alliance's glossary considers it original to the Scrum community and stresses that it belongs on a wall, large enough to start a conversation.

Where it sits in the layers

The burndown chart sits in Layer 9, Tools and Techniques, as a chart that a team draws for itself. It carries out the transparency that the Agile Manifesto in Layer 6 prizes, putting progress where everyone can see it. It grew up inside Scrum in Layer 8, and below, it is read each day in Layer 10 and set up at Sprint Planning, where the amount of work in the sprint is chosen. The common mistake is asking it to show value. Even the Agile Alliance's glossary notes that a burndown shows a trend in the work remaining and never which items are finished, let alone whether they were the right ones.

How organizations put it to work

The Scrum master or delivery lead owns the chart, and the team updates it at the daily meeting from its own remaining-work estimates. The Agile Alliance's advice is to make it large and place it in the project room, so that it works as an information radiator and starts discussion.

Two charts are common. A sprint burndown tracks the work in the current iteration. A product burndown tracks the whole release and shows how the release date is moving. Many teams add a burnup beside them, with a scope line, so that added work does not read as slow progress. The measures are work remaining, velocity, and the gap between the actual and ideal lines.

Sustaining it takes daily updates and a team that accepts that the chart will show bad news. In the first year a leader should expect early gaming, such as re-estimating work to hug the ideal line, a few misreadings by people who see only the downward slope, and a growing habit of discussing scope at the wall.

Where it goes wrong

The first failure is hidden scope. When work is added, a burndown looks like slow progress. The sign is a chart that ends above zero and a team that finished everything it started with.

The second is treating the ideal line as a target. Teams then re-estimate remaining work to stay near it, and the chart shows what everyone wants to see. The sign is a line that follows the diagonal too neatly.

The third is a hockey stick. If work counts only when an item is fully finished, the line stays flat and then drops at once. The sign is a cliff in the last two days.

The fourth is confusing a trend with a result. A good line means the team is working through its list at pace, and says nothing about whether it is the right list. The sign is a sprint that lands on the line and a review where stakeholders reject the work.

Related and rival frameworks

  • Cumulative Flow Diagram. Shows where work waits across stages, with scope and progress kept apart. Better when the question is where the flow stalls; the burndown asks whether the end date holds.
  • Gantt Chart. Lays out tasks and dates on a calendar. Better for a plan with dependencies and fixed dates, such as a build project, where a single remaining-work line is too crude.
  • Cycle Time, Lead Time, and Throughput. Measures how long each item takes. Better for forecasting delivery from the team's own history, without a daily chart.

Go to the source

  • Burndown Chart, Agile Alliance glossary entry, which dates Schwaber's first description to 2000, 2000