No single author: the arithmetic linking the three is John Little's 1961 law, and the measures became standard in software and knowledge work through David Anderson's Kanban (2010) and The Kanban Guide.
Three flow measures, the time work takes from start to finish, the time from request to delivery, and the number of items finished per period, that show how fast and how predictably a team delivers.
Thirty finished tickets: how many days can the team safely promise?
Each bar is how many of 30 support tickets took that many days, start to finish. Set the delivery promise and see what share of tickets would have met it. Find the promise that holds for at least 85 of every 100. Illustrative.
Tickets finished within the promiseAll tickets
An example
A customer-support team resolved a ticket in 4.4 working days on average and told customers five. About a quarter of tickets arrived late, and neither the team nor its manager could say why the average looked fine while customers complained. The team lead pulled start and finish dates for the last 30 tickets and plotted how many finished in one day, two days, three, and so on.
The picture was lopsided. Most tickets finished in two to five days, and a few dragged to eight, nine, or ten. Only 73 percent finished within five days. Twenty-seven of every hundred broke the promise, and the average had hidden that. The team promised seven days, the point by which 90 percent were done, and began a daily look at the oldest unfinished tickets. With a cap on tickets in progress, the long tail shortened within two months.
The core idea
Cycle time is the elapsed time from when work on an item starts until it finishes. Lead time is the elapsed time from when the item is requested until it is delivered, so it includes the wait before work begins. Throughput is the number of items finished per unit of time. The Kanban Guide defines cycle time, throughput, and work in progress, the number of items started but not finished, and it adds work item age, how long an item has been in progress so far. Usage varies, so a team should write down which start and finish events it means.
The measures are linked. In a stable process, average work in progress equals average throughput times average cycle time, which is Little's Law, so a team cannot change one without changing another. The practical point is that cycle time for individual items spreads out, usually with a long tail, so the average misleads. The useful statement for a customer is a range: most items finish within some number of days.
The thinking behind it
John D. C. Little John D. C. Little proved in 1961, in Operations Research, the queuing formula L = λW: the average number of items in a stable system equals the average arrival rate times the average time each spends in it. In the language of flow, that is work in process equals throughput times cycle time. He returned to the result in 2011 on its fiftieth anniversary. The formula is the arithmetic under every flow measure, and it holds for any stable process whatever the work.
David J. Anderson David Anderson set out the Kanban method for technology businesses in Kanban: Successful Evolutionary Change for Your Technology Business (2010), which manages work by limiting what is in progress and watching how it flows. The measures of cycle time, lead time, and throughput are the means of watching. The Kanban Guide, updated in May 2025, gives the formal definitions of cycle time, throughput, work in progress, and work item age that teams now use. The problem the measures answer is how a team knows whether it is getting faster and whether its promises are safe.
Where it sits in the layers
Cycle time, lead time, and throughput sit in Layer 9, Tools and Techniques, as measures a team can compute from start and finish dates. They rest on the logic of Stocks and Flows in Layer 1, where the time an item spends in a stock follows from its inflow and outflow. They serve the Layer 6 aim of Lean Thinking to shorten the time from order to delivery, and they are the measures of the Kanban Method in Layer 8. Below, they are read in the daily stand-ups and service reviews of Layer 10. The common mistake is asking them to say how good the work is. They describe speed and predictability, and a team can have excellent flow measures while building the wrong thing.
How organizations put it to work
Ownership sits with the delivery lead, with the team agreeing on the definitions. The first task is deciding which event starts the clock and which ends it, and recording both dates for every item in the work tracker. From that data a chart plots each finished item by finish date and cycle time, with lines marking the share of items finished within a given time, and a second chart shows throughput per week.
The routines are small. A daily look at the oldest items in progress catches work that is stalling. Forecasts of delivery dates come from the team's own throughput history and are given as ranges. The structural change is a limit on work in progress, because cutting it shortens cycle time. The measures are the percentile of cycle time at which the team promises, throughput per period, work in progress, and the age of the oldest item.
Sustaining it takes stable definitions and honest dates. In the first year a leader should expect messy data at first, a shock at how long the slowest items take, and a move from estimating each item to forecasting from history.
Where it goes wrong
The first failure is promising from the average. Because cycle times spread with a long tail, the average sits well below the point by which most items finish. The sign is a promise broken one time in four, as in the example.
The second is gaming. Teams split items to look faster, start the clock late, or finish items on paper. The sign is a falling cycle time with no change in what customers receive.
The third is pooling unlike work. A distribution that mixes small fixes with large projects describes neither. The sign is a very wide spread that no limit on work in progress narrows.
The fourth is judging people by it. When cycle time becomes an individual target, people avoid hard items. The sign is a queue of difficult tickets that nobody picks up.
Related and rival frameworks
- Little's Law. The arithmetic that links the three measures. Better when the question is what must change to bring cycle time down.
- Cumulative Flow Diagram. Draws work in each stage over time. Better when the question is where in the workflow time is lost.
- Kanban Method. The management method that uses these measures with limits on work in progress. Better when a team wants to change how it works as well as measure it.
Go to the source
- The Kanban Guide, May 2025 version, contributors including Daniel Vacanti, 2025
- A Proof for the Queuing Formula: L = λW, Operations Research 9(3), 383 to 387, 1961