Definition of Done

Layers of Management ThoughtLayer 9: Tools and TechniquesToolAlso known as DoD, Definition of Ready, Done and ready criteria

A practice of the Scrum community, written into The Scrum Guide by Ken Schwaber and Jeff Sutherland; the Guide's revision history already treats Ready and Done as paired states in 2013.

A shared, written list of the checks a piece of work must pass before it counts as finished, so that done means the same thing to everyone and only work meeting it joins the product increment.

Three moments when the definition of done is put under pressure

A team has a five-check definition of done, and the company has a standard above it. At each of the team's turns, choose what to do, and watch the meter for unfinished work that slips into the increment. Illustrative.

The team

The business

The team

The business

Select a stage to read it, or play the sequence.Day 10: one story left. The CSV export story is reviewed and its tests pass, but a major defect is still open. The definition says no open defect above minor. The review is tomorrow and the sprint goal names this story.Pick a move to see the reply.The review goes well. After release a customer finds the defect first, and the team spends the next sprint's opening week on it.A story that fails the team's own check joins the increment.The review shows four stories, not five. The product owner sees the true state and moves the defect to the top of the list.Right: only work that meets the definition counts.Everyone nods. The label hides how much remains, and the next plan counts the story as nearly free.Partial credit has no place in the standard.Stakeholders wait. The sprint goal named five stories and a launch date has moved up by a week. The business would like every one of them shown tomorrow.Day 1: a shortcut offered. A teammate proposes dropping the help-text check from the definition, only for this sprint, to make room for the earlier launch.Pick a move to see the reply.The team takes one story out of the sprint and keeps its standard. The launch holds a week later than the business wanted.Right: scope flexes and the definition does not.Two stories ship without help text, and support tickets climb. The check does not return next sprint because the team has shown it can be dropped.A standard that bends once will bend again.Each story becomes a negotiation. Soon the team argues over which checks apply to which story.A definition that varies by story is no longer a definition.The company's standard. The company's standard says every team's work must pass an automated security scan. The team's own definition does not mention it, and the scan adds ten minutes to the build.Day 8: the lighter standard. The scan sometimes fails on old code that the team did not write. A teammate proposes replacing the company's standard with the team's lighter definition.Pick a move to see the reply.The team keeps its five checks and adds the scan. The failures on old code are logged and fixed over time.Right: an organizational standard is the minimum, and teams add to it.A vulnerability passes through unseen and is found by an outside party months later. The team's work no longer matches that of the teams around it.A team may raise the company's bar and must not lower it.

Standard kept: 0 of 3Standard kept: 1 of 3Standard kept: 2 of 3Standard kept: 3 of 3

Unfinished work hidden in the increment (points)0of 12

  1. Day 10: one story left (The team). The CSV export story is reviewed and its tests pass, but a major defect is still open. The definition says no open defect above minor. The review is tomorrow and the sprint goal names this story.
    • Show it as done at the review The review goes well. After release a customer finds the defect first, and the team spends the next sprint's opening week on it. A story that fails the team's own check joins the increment.
    • Return it to the backlog and show only what meets the definition The review shows four stories, not five. The product owner sees the true state and moves the defect to the top of the list. Right: only work that meets the definition counts.
    • Show it as 90 percent done Everyone nods. The label hides how much remains, and the next plan counts the story as nearly free. Partial credit has no place in the standard.
  2. Stakeholders wait (The business). The sprint goal named five stories and a launch date has moved up by a week. The business would like every one of them shown tomorrow.
  3. Day 1: a shortcut offered (The team). A teammate proposes dropping the help-text check from the definition, only for this sprint, to make room for the earlier launch.
    • Keep all five checks and cut scope instead The team takes one story out of the sprint and keeps its standard. The launch holds a week later than the business wanted. Right: scope flexes and the definition does not.
    • Drop the check just for this sprint Two stories ship without help text, and support tickets climb. The check does not return next sprint because the team has shown it can be dropped. A standard that bends once will bend again.
    • Make the check optional for each story Each story becomes a negotiation. Soon the team argues over which checks apply to which story. A definition that varies by story is no longer a definition.
  4. The company's standard (The business). The company's standard says every team's work must pass an automated security scan. The team's own definition does not mention it, and the scan adds ten minutes to the build.
  5. Day 8: the lighter standard (The team). The scan sometimes fails on old code that the team did not write. A teammate proposes replacing the company's standard with the team's lighter definition.
    • Add the scan to the team's definition as a minimum The team keeps its five checks and adds the scan. The failures on old code are logged and fixed over time. Right: an organizational standard is the minimum, and teams add to it.
    • Use the team's own definition in place of the standard A vulnerability passes through unseen and is found by an outside party months later. The team's work no longer matches that of the teams around it. A team may raise the company's bar and must not lower it.

An example

A software team ended each sprint with a review where stakeholders watched demonstrations, and the stories shown as finished kept coming back with defects after release. The team looked at why. One developer counted a story as done when the code worked on her machine. Another waited for review. A third counted it only when tests ran in the pipeline. So the team wrote down five checks: a second developer has reviewed the code, automated tests pass in the pipeline, no open defect above minor remains, the help text is updated, and the product owner has accepted the story.

The next sprint, one story passed review and tests but carried an open major defect. The team returned it to the backlog and showed four of the five stories. The stakeholders saw an honest state and moved the defect to the top of the list. Over the following months, defects after release fell, and so did the argument at each review about what was finished.

The core idea

A definition of done is the written standard a piece of work must meet before anyone calls it finished. It is a list of checks that every item must pass, such as code reviewed, tests passing, documentation updated, and no open defects above an agreed level. The Scrum Guide describes it as the state of the product increment when it meets the quality measures the product requires, and says an item that does not meet it cannot be released or shown at the sprint review. It goes back to the backlog.

The companion idea, a definition of ready, covers the other end: the conditions a backlog item should meet before a team takes it on. The current Scrum Guide does not name it, and teams that use it write their own.

The insight is that done is a binary, shared standard. Without one, each person decides privately, partly finished work hides inside the totals, and a team that thinks it is faster than it is learns the truth from its customers.

The thinking behind it

Ken Schwaber Ken Schwaber wrote The Scrum Guide with Jeff Sutherland, first in 2010, to set out the rules of Scrum. The guide's revision history shows how the idea of done took its place in it. By the 2013 version, refined backlog items were called Ready, and the revision notes say that "Ready and Done are two states that reinforce transparency." The problem it addresses is a team and its stakeholders talking past each other about progress, each counting different things as complete.

Jeff Sutherland Jeff Sutherland shares the guide's authorship with Schwaber, and the 2020 version sets the definition's place most firmly. It treats the definition of done as one of three commitments, tied to the increment: work counts as part of an increment only if it meets the definition. Where an organization has a standard, every team must follow it as a minimum, and teams working on one product must agree on one definition. If there is no standard, the Scrum team writes one suited to its product.

Where it sits in the layers

The definition of done sits in Layer 9, Tools and Techniques, as a portable standard that any team can write down. It puts the Agile Manifesto principle of working software in Layer 6 into a testable form. It is a commitment inside Scrum in Layer 8, and it is applied each sprint in Layer 10 at the Sprint Review, where only work that meets it is shown as part of the increment. The common mistake is asking it to describe a particular item. It sets the same quality bar for every item, and what a specific story must do belongs to that story's own acceptance criteria and to the conversation that shapes it.

How organizations put it to work

The team owns the definition, in the Scrum Guide's terms, unless the organization already has a standard, which the team then extends. The first draft is written in an hour or two by the people who do the work, from a list of the things that have gone wrong before. It lives where the team can see it, often on the board, and as much of it as possible is enforced automatically by the build pipeline, so that a failing test stops an item at the door.

The behavior it changes is at the review. Only items meeting the definition are shown, with no partial credit, and unfinished work returns to the backlog. The measures are the share of items that meet the definition at the review, defects found after release, and rework in the following sprint. The team raises the bar in its retrospectives as its tooling improves.

In the first year a leader should expect velocity to dip as unfinished work stops being counted, a few uncomfortable reviews, and then steadier delivery and fewer surprises after release.

Where it goes wrong

The first failure is a checklist ticked without evidence. People mark items done to satisfy the list, and defects keep escaping. The sign is a definition that is always met and a backlog of customer complaints.

The second is a definition so long that nothing ever finishes. Teams then work around it. The sign is a board full of items at ninety percent and unspoken exceptions that become habit.

The third is renegotiating it each sprint. If a deadline or a persuasive stakeholder can drop a check, the standard means nothing. The sign is phrases such as done except for testing.

The fourth is the readiness gate. A strict definition of ready can turn backlog refinement into a handoff, with the team refusing items and product owners writing to pass the checklist. The current Scrum Guide does not use the term. A team that adopts it should treat it as a prompt for conversation.

Related and rival frameworks

  • INVEST Criteria. Tests whether a story is fit to start, on the entry side. Better when the trouble lies in vague or oversized stories; the definition of done deals with unfinished ones.
  • Scrum. The framework in which the definition of done is a formal commitment. Better to read for the whole set of roles, events, and artifacts around it.
  • Working Agreements. Sets the team's norms for how it works together. Better for conduct, such as how fast to answer a review request, and the definition of done covers the work itself.