Cumulative Flow Diagram

Layers of Management ThoughtLayer 9: Tools and TechniquesToolAlso known as CFD, Cumulative input-output diagram, Newell curve

An older queueing chart, sometimes called a cumulative input-output diagram, that David Anderson brought into software management in Agile Management for Software Engineering (2003) and made a standard measure of the Kanban method in Kanban (2010); no single originator of the chart itself is established.

A stacked area chart of how many work items sit in each stage of a process over time, whose bands show where work piles up and how long it waits, so a team sees its bottleneck at a glance.

The review stage of a software team over eight weeks: items entering and items leaving

Each week items arrive in review and the reviewers finish some. The black line is the total that has entered review and the bars are the total that has left, so the gap between them is the band of items waiting. Set the reviewers' capacity and find where the band stops widening. Illustrative.

12 a week
9 a week
Items waiting in review at week 8
24 items
Wait for an item arriving in week 8
2.7 weeks
The band is
Narrowing: the reviewers are catching upFlat: work leaves as fast as it arrivesWidening: review is the bottleneck

Total finished in reviewTotal entered review

050100918273645546372Wk 1Wk 2Wk 3Wk 4Wk 5Wk 6Wk 7Wk 8050100918273645546372Wk 1Wk 2Wk 3Wk 4Wk 5Wk 6Wk 7Wk 8

An example

A product team of twelve delivered less each month than its managers expected, and the managers blamed development speed. The delivery lead drew a cumulative flow diagram from the work tracker, one band for each stage: backlog, design, build, review, and done. Over eight weeks the bands for design and build kept a steady thickness, but the review band grew from three items to twenty-four. Items were arriving in review at twelve a week and leaving at nine, because two senior engineers did all the reviews.

Seen on one chart, the slow delivery had nothing to do with developer speed. The team set a limit on items in review, trained two more reviewers, and began pairing on reviews of risky changes. The review band narrowed within three weeks, and the average wait for review fell from nearly three weeks to under one.

The core idea

A cumulative flow diagram plots time along the bottom and the cumulative count of work items up the side. Each band is a stage of the workflow, stacked in order, so the top line is the total that has entered the process and the bottom line is the total finished. At any date, the thickness of a band is the number of items in that stage. Across the band, the horizontal distance is roughly how long an item waits there, when work leaves in the order it arrived. The slope of the bottom line is throughput.

The shapes carry the diagnosis. Parallel lines mean steady flow. A band that thickens over time means work is arriving faster than it leaves, and the stage is a bottleneck. A flat bottom line means nothing is finishing. The insight that makes it more than a progress chart is that it shows work in process, throughput, and time in process on one picture, and it shows trouble weeks before a missed date does.

The thinking behind it

David J. Anderson The chart itself is older than software. Traffic engineers have plotted cumulative counts over time since Karl Moskowitz's work of 1954, and Gordon Newell later made such curves a working tool of queueing theory, which is why some call them Newell curves. David Anderson brought it into software management in Agile Management for Software Engineering (2003), a book that applies the theory of constraints to software work and includes a section on monitoring cumulative flow. His later book Kanban: Successful Evolutionary Change for Your Technology Business (2010) sets out the Kanban method, which teams commonly track with the diagram. The problem it answered was how a manager sees where software work stalls.

Where it sits in the layers

The cumulative flow diagram sits in Layer 9, Tools and Techniques, as a chart that any team with a workflow can draw. It draws on the logic of the Theory of Constraints in Layer 6, which the subtitle of Anderson's 2003 book names, and the stage that holds the thickest band is the candidate constraint. It is the standard picture of flow in the Kanban Method in Layer 8. In Layer 10 teams study it at a Sprint Retrospective when they ask where work waited. The common mistake is asking it to explain why. The chart shows where work piles up, and finding the reason takes a conversation with the people at that stage.

How organizations put it to work

Ownership sits with the delivery lead or team lead, supported by whoever administers the work tracker. The prerequisite is a workflow with explicit stages and a team that moves items through them as they happen. Most trackers then draw the chart automatically from daily counts.

The routine is a weekly look at the chart in a team meeting, asking three questions: which band is thickening, which line has gone flat, and what changed. Actions follow from the answers. The team limits work in the stage that is flooding, shifts people toward the stage that is starving, or investigates the cause of a stall. The measures are work in process by stage, throughput per week, and approximate time in process.

Sustaining it takes agreed definitions of the stages and a habit of keeping the tracker current. In the first year a leader should expect confusing charts at first because states are used inconsistently, a surprise at which stage turns out to be the bottleneck, and a few arguments about whether the chart is a tool for the team or a report for management.

Where it goes wrong

The first failure is bad data. If people move items on the board in batches before a meeting or skip a stage, the bands jump and the chart misleads. The sign is staircase patterns that follow the meeting calendar.

The second is reading the width of a band as exact time. The estimate holds when work leaves in the order it arrives, and it breaks when urgent items jump the queue or when items are dropped. The sign is a computed wait that does not match what people report.

The third is treating all items as equal. A one-day item and a three-week item count the same in the chart, so mixed sizes distort the bands. The sign is a thick band that disappears after one large item finishes.

The fourth is a chart shown and never acted on. The sign is a chart in a monthly deck and no change to the limits or the staffing it points to.

Related and rival frameworks

  • Little's Law. States the exact relationship between work in process, throughput, and time in process. Better when the question is a calculation, and this chart is the picture that shows it.
  • Kanban Method. The method that limits work in process and manages flow, with this chart as its standard measure. Better when a team wants to change how work is pulled as well as watch it.
  • Burndown and Burnup Charts. Shows work remaining against time. Better for a fixed-length sprint or release with a defined scope, where the question is whether the end date holds.

Go to the source

Back to the catalog