Sprint Retrospective

Layers of Management ThoughtLayer 10: Practices and RitualsPracticeAlso known as Retrospective, Retro, Iteration retrospective

From the project retrospectives of Norman L. Kerth (Project Retrospectives: A Handbook for Team Reviews, 2001), adapted to every short iteration by Esther Derby and Diana Larsen (Agile Retrospectives: Making Good Teams Great, 2006), and made the closing event of every Sprint in Scrum.

Closes each short work cycle with a structured, blame-free review in which a team looks at how it worked, finds causes, and commits to one or two improvements for the next cycle.

A retrospective after a missed sprint goal, and the three moves that decide whether anything improves

The five phases run down the page. At each of the facilitator's turns, pick the move: one keeps the team learning, the other turns the hour into blame or a wish list. What happens shows with a verdict, and the dashed arrow is the next retrospective checking this one's action. Illustrative.

Facilitator

Team

  • Next time, check this action (Close to Set the stage)

Facilitator

Team

  • Next time, check this action (Close to Set the stage)

Select a stage to read it, or play the sequence.The sprint. A claims-software team missed its sprint goal. Two stories sat waiting for testing, and a production incident took two days.Set the stage. Pick how the facilitator opens the hour.Pick a move to see the reply.The testers go quiet, and the developers defend their estimates.Blame first, so people protect themselves and the facts stay hidden.Words like tired and scrambled come out, and everyone has spoken once.Safety first, so people describe what happened.Gather data. The team builds a timeline: the incident on day four, and two stories waiting for a test environment from day six onward.Generate insights. Pick the question the facilitator puts to the timeline.Pick a move to see the reply.Testing promises to hurry, and the same wait happens the next sprint.A verdict on people, and the cause stays hidden.There is one shared environment, rebuilt by hand after every incident, which takes two days.A cause the team can act on.Decide what to do. Pick what the team commits to.Pick a move to see the reply.Two weeks later none is finished, and the list is dropped without a word.A wish list nobody can finish.The script is working by day five of the next sprint.One owned change, small enough to finish.Close. The team thanks two people who stayed late on the incident and rates the retrospective itself, asking for a shorter data step next time.

Moves that lead to an improvement: 0 of 3Moves that lead to an improvement: 1 of 3Moves that lead to an improvement: 2 of 3Moves that lead to an improvement: 3 of 3

  1. The sprint (Team). A claims-software team missed its sprint goal. Two stories sat waiting for testing, and a production incident took two days.
  2. Set the stage (Facilitator). Pick how the facilitator opens the hour.
    • Open with the missed goal and ask who was responsible. The testers go quiet, and the developers defend their estimates. Blame first, so people protect themselves and the facts stay hidden.
    • Read the prime directive aloud and ask each person for one word about the sprint. Words like tired and scrambled come out, and everyone has spoken once. Safety first, so people describe what happened.
  3. Gather data (Team). The team builds a timeline: the incident on day four, and two stories waiting for a test environment from day six onward.
  4. Generate insights (Facilitator). Pick the question the facilitator puts to the timeline.
    • Agree that testing has to move faster next time. Testing promises to hurry, and the same wait happens the next sprint. A verdict on people, and the cause stays hidden.
    • Ask why the stories waited: what made the test environment so scarce? There is one shared environment, rebuilt by hand after every incident, which takes two days. A cause the team can act on.
  5. Decide what to do (Facilitator). Pick what the team commits to.
    • List ten improvements and spread them across the team. Two weeks later none is finished, and the list is dropped without a word. A wish list nobody can finish.
    • Pick one: script the test-environment rebuild, owned and in the next sprint's backlog. The script is working by day five of the next sprint. One owned change, small enough to finish.
  6. Close (Team). The team thanks two people who stayed late on the incident and rates the retrospective itself, asking for a shorter data step next time.

An example

A team building claims software for an insurer missed its sprint goal: two stories sat waiting for testing, and a production incident took two days. The team's retrospectives had become a list of complaints that changed nothing, and this one started the same way, with a developer asking why testing was always slow.

The Scrum Master reset the hour. She read the retrospective prime directive aloud, asked each person for one word about the sprint, and had the team build a timeline on the wall before anyone offered a view. The timeline showed the stories waiting on a test environment from day six. Asking why, the team found one shared environment, rebuilt by hand after every incident, a two-day job. It chose a single action: script the rebuild, with an owner, in the next sprint's backlog. The script worked by day five. Over the next quarter, environment waits disappeared from the timeline, and the team met three goals in a row.

The core idea

A retrospective is a team's regular, structured look at how it worked during the cycle just ended, held so that the next cycle goes better. In Scrum it closes every Sprint, timeboxed to three hours for a one-month Sprint and less for shorter ones. Its subject is the way of working: people, interactions, processes, tools, and the standards the team holds itself to.

A common structure runs in five phases. Set the stage, so that people are ready to speak openly. Gather data, so that the team shares one picture of what actually happened. Generate insights, looking for patterns and causes. Decide what to do, choosing one or two actions small enough to finish. Close, appreciating and reviewing the retrospective itself. A prime directive, that everyone did the best job they could given what they knew and had at the time, sets the tone against blame.

The insight is the cadence. A team that improves one thing every two weeks changes faster than one that waits for a post-mortem at the end of a project.

The thinking behind it

Norman L. Kerth Norman L. Kerth, a software consultant, wrote Project Retrospectives: A Handbook for Team Reviews (2001) to replace the blame-ridden post-mortem with a facilitated review in which a team could learn from its own history. Its best-known contribution is the prime directive, read at the start of the review: "Regardless of what we discover, we understand and truly believe that everyone did the best job he or she could, given what was known at the time, his or her skills and abilities, the resources available, and the situation at hand." The aim was to remove the fear of retribution that keeps people from saying what happened.

Esther Derby Esther Derby and Diana Larsen brought the retrospective into the short cycles of agile teams with Agile Retrospectives: Making Good Teams Great (2006), published with a foreword by Ken Schwaber. They argued that a team should keep learning from its first weeks onward, and gave it a five-phase structure to do so: set the stage, gather data, generate insights, decide what to do, and close. For each phase they collected activities a facilitator could use, so that a retrospective every two weeks stayed fresh and productive.

Where it sits in the layers

The sprint retrospective is a practice of Layer 10, where the improvement built into a methodology happens on the calendar. It is an event of Scrum in Layer 8, and it puts to work two explanatory models from Layer 5: Psychological Safety, which explains why people speak up only when they do not fear blame, and Single- and Double-Loop Learning, which separates fixing a problem from questioning the assumptions that produced it. Its rhythm echoes the plan, do, check, act cycle of the quality movement. The common mistake is asking a team's retrospective to fix what the team cannot control. Problems that sit in budgets, structure, or another department belong in an escalation with a named owner above the team, and a retrospective that keeps listing them breeds cynicism.

How organizations put it to work

Each team owns its own retrospective, usually facilitated by a Scrum Master or a rotating team member, and the organization's role is to protect the time and act on what teams escalate. Adopting it well means a few norms: a regular slot at the end of every cycle, the prime directive or something like it to set the tone, data before opinions, and no more than one or two actions, each with an owner and a place in the next cycle's plan.

The practice changes routines at two levels. Within the team, last time's actions are reviewed at the start of the next retrospective, so improvements get finished instead of forgotten. Across teams, some organizations collect the issues that retrospectives cannot solve and route them to managers who can, which turns frontline learning into structural change.

In the first year a leader should expect a few awkward sessions, teams that slide into complaint, and pressure to skip retrospectives when deadlines loom. The return is steady, compounding improvement in how work gets done, owned by the people who do it, without waiting for an outside program.

Where it goes wrong

The first failure is the complaint session. The team lists what went wrong, feels better, and changes nothing. Spot it when no action from the last retrospective was finished, or when there were no actions at all.

The second is blame. When managers attend as judges, or findings reach performance reviews, people stop describing what really happened. Spot it when the data phase is thin and everyone agrees quickly.

The third is the stale format. The same three questions every two weeks produce the same answers, and attendance becomes a ritual. Spot it when the team can predict the retrospective's output before it starts. The prime directive itself has critics: practitioners debating it in 2008 questioned whether anyone can truly believe everyone did their best, and noted that reading it aloud does little without a discussion of what it means.

Related and rival frameworks

  • Blameless Postmortem. Reviews a single incident in depth, without blame, to find its causes. Use it for one failure, and the retrospective for the team's routine way of working.
  • After-Action Review. The military's short review of what was planned, what happened, why, and what to change. Fits any team after any event, without the agile cycle.
  • Hansei. Japanese practice of candid self-reflection on shortfalls, built into Toyota's management. A broader habit of which the retrospective is one scheduled form.