PI Planning

Layers of Management ThoughtLayer 10: Practices and RitualsPracticeAlso known as PI planning event, Planning interval planning, Program increment planning, Release planning for an agile release train

Developed by Dean Leffingwell from the two-day release planning of the agile release train in Agile Software Requirements (2011), and made the central event of the Scaled Agile Framework, where PI meant program increment until version 6.0 renamed it planning interval.

A recurring two-day event in which every team on a large product group plans the next eight to twelve weeks together, settles dependencies face to face, fits the work to capacity, and commits to objectives it then votes on.

Six features against four teams' capacity, and the deferral that lets the plan fit

The draft plan from the bank's first planning day: six features loaded onto four teams, each bar a team's planned work against its capacity (the line). Defer features until every bar sits at or under its line, keeping as much business value as you can. Illustrative.

In the plan
In the plan
In the plan
In the plan
In the plan
In the plan
Teams over capacity
2 of 4
What the confidence vote will say
Every team fits: the plan is ready for the voteOver capacity: expect a low vote and a rework
Platform team's load
140%
Business value kept in the plan
35 of 35

Points plannedCapacity

0204044382842MobileWebPaymentsPlatform0204044382842MobileWebPaymentsPlatform

An example

A regional bank's digital release train, sixty people in six teams, met for its planning event in a rented hall. On the first morning the business owners set out the context, a regulatory deadline for an open banking interface and a push to win customers on mobile, and product management walked through six features in order of value. By the afternoon's review of draft plans, the trouble was on the planning board: the platform team carried 42 points of work against a capacity of 30, because four of the six features needed something from it, and the mobile team was over too.

The business owners first asked the teams to find a way. The confidence vote the next afternoon averaged 2.4 out of 5, so the plan went back for rework, and the spending-insights feature, low in value and heavy on the platform team, was deferred. The second vote averaged 3.9. At the end of the interval, the train had delivered 88 percent of the business value it planned, against 55 percent the interval before.

The core idea

PI planning opens each planning interval of the Scaled Agile Framework, a fixed timebox of eight to twelve weeks. Every team on an agile release train, the standing group of teams that delivers one solution, plans together with its business owners and product managers, led by the release train engineer. The first day turns business context and the top features into draft plans, team by team, and leaders resolve the conflicts those drafts reveal. The second day reworks the plans, records the risks with owners, and ends with a vote on how confident the teams are that they can deliver.

The outputs are each team's objectives for the interval, a planning board showing when features land and which teams depend on which, and the risks. The premise is that coordination across teams is cheapest when everyone is in the room. A dependency that would take weeks of messages is settled in minutes, and an overcommitted plan meets its limits before the interval starts, while scope can still be cut without breaking promises.

The thinking behind it

Dean Leffingwell Dean Leffingwell built the event into his model of agile requirements at scale. Agile Software Requirements, published at the end of 2010, organized teams into an agile release train and gave release planning a chapter of its own, a narrative of a two-day planning session for the whole train, with ways to measure how predictably a train delivers what it planned. The Scaled Agile Framework, which grew from that work, made the session its central event as PI planning. PI meant program increment until version 6.0 retired the word program and renamed it planning interval. The problem it answered was many agile teams that each planned well alone and collided with one another.

Where it sits in the layers

PI planning is a practice of Layer 10, the recurring event where a scaled operating model meets its people. It is an event of the Scaled Agile Framework in Layer 8, and SAFe's own form of Big Room Planning, the general practice beside it in this layer. It assumes what the Agile Manifesto and Lean Thinking hold in Layer 6, that work is planned in short, fixed intervals by the people who do it, and it orders features with Weighted Shortest Job First, a Layer 9 scoring rule. The common mistake is asking the event to set strategy. Two days with a whole train can turn chosen priorities into a plan, but they cannot choose the priorities, and a train that arrives without them spends the event arguing about direction. Those choices belong to portfolio decisions made before the event.

How organizations put it to work

The event is owned by the release train engineer, who runs it, with business owners and product management accountable for its inputs: a short, ordered list of features and the context behind them. Preparation takes weeks. Features are sized and ordered, each team's capacity is known after holidays and support duties, architecture questions are settled, and a room or a virtual space is set up for the whole train. Business owners attend both days and review every team's objectives.

The event changes the organization's rhythm. Every eight to twelve weeks, priorities are fixed for an interval, dependencies sit on one board, and leaders cut scope in the room, while cutting is still cheap. During the interval, teams track progress against their objectives, and at its end each team's achievement is scored. SAFe averages those scores into a predictability measure for the train.

Sustaining it is expensive, two days of the whole train's time every quarter, and it needs leaders willing to defer work when the plan does not fit. In the first year, expect overfull plans, low votes, and a predictability measure that starts low and climbs as the train learns its real capacity.

Where it goes wrong

The first failure is the overfull plan. Leaders refuse to defer anything, teams accept work beyond capacity to end the argument, and the interval ends with half its objectives missed. Spot it when draft plans exceed capacity and the final plans somehow fit with no feature deferred.

The second is the ceremonial vote. Teams vote high because a low vote prolongs the meeting or displeases a sponsor. Spot it when confidence votes stay above four while predictability stays low.

The third is planning theater. The event runs to schedule while the real priorities are set elsewhere and change in the second week. Spot it when features join the train mid-interval and nothing leaves. For smaller or loosely coupled groups, the event's cost can also outweigh its benefit, and a shared backlog with lighter coordination does the job.

Related and rival frameworks

  • Big-Room Planning. The general practice of planning many teams together in one room, which SAFe formalized as this event. The better frame outside SAFe.
  • SAFe (Scaled Agile Framework). The operating model the event belongs to. Pick it when the question is the whole structure of trains, roles, and portfolio.
  • Large-Scale Scrum (LeSS). Scales Scrum with one product backlog and lighter shared events. A leaner choice when every team works on one product and fewer roles are wanted.