Big-Room Planning

Layers of Management ThoughtLayer 10: Practices and RitualsPracticeAlso known as Big Room, Obeya

A practice of lean management with no single author: Toyota's obeya, credited to Takeshi Uchiyamada as chief engineer of the Prius in the 1990s, and the Big Room of lean construction bring a project's people together to plan and decide, and Dean Leffingwell's release planning, which became the Scaled Agile Framework's PI Planning (2011), is its best-known software form.

Brings everyone whose work must fit together into one room, or one live session, to plan the next stretch of work at once, settle dependencies face to face, and commit to shared objectives.

Seven items from a nine-team draft plan, sorted by where the decision belongs

Two days of planning sort the draft plan into what a team can settle alone, what teams settle with each other in the room, and what only the executives can decide. Select an item, then the column it belongs in, and show the sort to compare. Illustrative.

Items (select one, then a box)
  • Not placedPlacedInside one teamBetween teamsExecutives
  • Not placedPlacedInside one teamBetween teamsExecutives
  • Not placedPlacedInside one teamBetween teamsExecutives
  • Not placedPlacedInside one teamBetween teamsExecutives
  • Not placedPlacedInside one teamBetween teamsExecutives
  • Not placedPlacedInside one teamBetween teamsExecutives
  • Not placedPlacedInside one teamBetween teamsExecutives

Draft plan

Items
Inside one team
Between teams
Executives
One teamTeams in the roomExecutives

Who can settle it

Needs login token change. The payments team cannot start its mobile checkout until the accounts team issues a new kind of login token.Not placed yet.Needs login token change. The payments team cannot start its mobile checkout until the accounts team issues a new kind of login token.Inside one team: No other team's work is involved. The team plans it, commits to it, and the planning board needs no entry.Needs login token change. The payments team cannot start its mobile checkout until the accounts team issues a new kind of login token.Between teams: Another team must deliver first or share something. Settle it face to face while both teams are in the room, and put the date on the planning board.One team's start depends on another team's delivery. Agreed in the room, it becomes a dated line on the planning board, so nobody learns of it in week six.Needs login token change. The payments team cannot start its mobile checkout until the accounts team issues a new kind of login token.Executives: The plan asks for more than the teams can deliver, or a priority has to change. Only the people accountable for outcomes can trade scope for time.Refactor billing module. Cleanup the billing team can finish alone.Not placed yet.Refactor billing module. Cleanup the billing team can finish alone.Inside one team: No other team's work is involved. The team plans it, commits to it, and the planning board needs no entry.No other team depends on it, so the team commits to it and moves on.Refactor billing module. Cleanup the billing team can finish alone.Between teams: Another team must deliver first or share something. Settle it face to face while both teams are in the room, and put the date on the planning board.Refactor billing module. Cleanup the billing team can finish alone.Executives: The plan asks for more than the teams can deliver, or a priority has to change. Only the people accountable for outcomes can trade scope for time.Shared database upgrade. Every team reads from the same customer database, and the upgrade needs a maintenance window.Not placed yet.Shared database upgrade. Every team reads from the same customer database, and the upgrade needs a maintenance window.Inside one team: No other team's work is involved. The team plans it, commits to it, and the planning board needs no entry.Shared database upgrade. Every team reads from the same customer database, and the upgrade needs a maintenance window.Between teams: Another team must deliver first or share something. Settle it face to face while both teams are in the room, and put the date on the planning board.It touches every team's plan. The teams agree on one window while they are together, so no team schedules work against it.Shared database upgrade. Every team reads from the same customer database, and the upgrade needs a maintenance window.Executives: The plan asks for more than the teams can deliver, or a priority has to change. Only the people accountable for outcomes can trade scope for time.Plan holds 140% of capacity. After estimating, the teams' commitments add up to far more than one interval can hold.Not placed yet.Plan holds 140% of capacity. After estimating, the teams' commitments add up to far more than one interval can hold.Inside one team: No other team's work is involved. The team plans it, commits to it, and the planning board needs no entry.Plan holds 140% of capacity. After estimating, the teams' commitments add up to far more than one interval can hold.Between teams: Another team must deliver first or share something. Settle it face to face while both teams are in the room, and put the date on the planning board.Plan holds 140% of capacity. After estimating, the teams' commitments add up to far more than one interval can hold.Executives: The plan asks for more than the teams can deliver, or a priority has to change. Only the people accountable for outcomes can trade scope for time.Teams cannot shrink the demand themselves. The executives decide which features move out, and the teams leave with a plan they can believe.Fix typo in a report. A one-line change to a customer statement.Not placed yet.Fix typo in a report. A one-line change to a customer statement.Inside one team: No other team's work is involved. The team plans it, commits to it, and the planning board needs no entry.It involves one team and no dependency.Fix typo in a report. A one-line change to a customer statement.Between teams: Another team must deliver first or share something. Settle it face to face while both teams are in the room, and put the date on the planning board.Fix typo in a report. A one-line change to a customer statement.Executives: The plan asks for more than the teams can deliver, or a priority has to change. Only the people accountable for outcomes can trade scope for time.Partner launch moved up. A partner now expects its integration a month earlier than planned.Not placed yet.Partner launch moved up. A partner now expects its integration a month earlier than planned.Inside one team: No other team's work is involved. The team plans it, commits to it, and the planning board needs no entry.Partner launch moved up. A partner now expects its integration a month earlier than planned.Between teams: Another team must deliver first or share something. Settle it face to face while both teams are in the room, and put the date on the planning board.Partner launch moved up. A partner now expects its integration a month earlier than planned.Executives: The plan asks for more than the teams can deliver, or a priority has to change. Only the people accountable for outcomes can trade scope for time.Changing a priority changes what every team plans. Only the executives can set it, and the room needs the answer before teams finalize.Two teams need one tester. Both the claims team and the billing team have planned the same specialist for week four.Not placed yet.Two teams need one tester. Both the claims team and the billing team have planned the same specialist for week four.Inside one team: No other team's work is involved. The team plans it, commits to it, and the planning board needs no entry.Two teams need one tester. Both the claims team and the billing team have planned the same specialist for week four.Between teams: Another team must deliver first or share something. Settle it face to face while both teams are in the room, and put the date on the planning board.A shared resource is settled between the teams. In the room the two leads can swap weeks in minutes.Two teams need one tester. Both the claims team and the billing team have planned the same specialist for week four.Executives: The plan asks for more than the teams can deliver, or a priority has to change. Only the people accountable for outcomes can trade scope for time.

Your sort matched 0 of 7.Your sort matched 1 of 7.Your sort matched 2 of 7.Your sort matched 3 of 7.Your sort matched 4 of 7.Your sort matched 5 of 7.Your sort matched 6 of 7.Your sort matched 7 of 7.

Inside one team
No other team's work is involved. The team plans it, commits to it, and the planning board needs no entry.
Between teams
Another team must deliver first or share something. Settle it face to face while both teams are in the room, and put the date on the planning board.
Executives
The plan asks for more than the teams can deliver, or a priority has to change. Only the people accountable for outcomes can trade scope for time.

The sort

  • Needs login token change: Between teams. One team's start depends on another team's delivery. Agreed in the room, it becomes a dated line on the planning board, so nobody learns of it in week six.
  • Refactor billing module: Inside one team. No other team depends on it, so the team commits to it and moves on.
  • Shared database upgrade: Between teams. It touches every team's plan. The teams agree on one window while they are together, so no team schedules work against it.
  • Plan holds 140% of capacity: Executives. Teams cannot shrink the demand themselves. The executives decide which features move out, and the teams leave with a plan they can believe.
  • Fix typo in a report: Inside one team. It involves one team and no dependency.
  • Partner launch moved up: Executives. Changing a priority changes what every team plans. Only the executives can set it, and the room needs the answer before teams finalize.
  • Two teams need one tester: Between teams. A shared resource is settled between the teams. In the room the two leads can swap weeks in minutes.

An example

A logistics software company had nine teams building one dispatch platform, and its quarterly planning ran for six weeks. Each team drafted a plan alone, sent its dependencies to other teams as requests, and waited. By the time the plans were reconciled, the first month of the quarter was gone, and the first release always slipped because a team discovered in week six that another team had never agreed to its request.

The company moved to a single two-day event. All nine teams, their product managers, and two executives gathered in one hall with a wall for a planning board. On the first morning, leadership explained the priorities. Teams spent the rest of the first day drafting plans and finding dependencies, and the second day resolving them, with the executives available to trim scope. Teams left with committed objectives and a board showing who depended on whom and by when. The first release landed on time, and planning no longer consumed six weeks.

The core idea

Big-room planning gathers every party whose work must fit together (the teams, their leaders, and the people who can trade scope) to plan the coming stretch of work in one sitting. Its roots are Toyota's obeya, Japanese for big room, used to run product development, and the Big Room of lean construction, where a project's owner, designers, and trades plan and decide together. How often it meets, for how long, and who attends are set by the work.

The Scaled Agile Framework's PI Planning, which has its own entry, is one prescribed form of the practice: a two-day event for one release train every 8 to 12 weeks, with a set agenda, named roles, team objectives, a planning board, and a closing confidence vote. The generic practice fixes none of those details. It keeps the insight: coordination is cheapest when everyone is together, so a dependency that would take two weeks of messages is settled in a ten-minute conversation, and an overloaded plan is cut while the people who can cut it are listening.

The thinking behind it

Lean management's big room, from Toyota's obeya and lean construction, carried into software as joint planning events No single author owns big-room planning. The Lean Enterprise Institute credits Toyota's obeya to Takeshi Uchiyamada, chief engineer of the Prius, a program Toyota officially launched in 1994: project leaders worked in the room, with timing and progress posted on its walls. Lean construction took up the Big Room, which the Lean Construction Institute defines as a way of working: a project's key people gather to plan, decide, and solve problems, and co-locating people or holding a meeting does not by itself make a Big Room. In software, Dean Leffingwell's release planning for the agile release train, set out in Agile Software Requirements (2011), became the Scaled Agile Framework's PI Planning, the practice's best-known software form.

Where it sits in the layers

Big-room planning sits in Layer 10, Practices and Rituals, because it is a recurring event: the day or two when everyone whose work must fit together plans in one place. It takes for granted what Lean Thinking and the agile philosophies hold in Layer 6, that the people who do the work should plan it and that every handoff slows the flow. It is where Layer 8 methods meet their people: the Scaled Agile Framework prescribes its own version, PI Planning, which sits beside this entry in Layer 10, and teams under Integrated Project Delivery often plan in the construction Big Room. The common mistake is asking the room to set strategy. It can turn chosen priorities into a plan, and a group that arrives without them spends the event arguing about direction.

How organizations put it to work

A program or delivery lead usually owns the event (in SAFe, the release train engineer), with product or project leaders supplying priorities and the executives who can trade scope attending. It changes structure little, because it uses the teams that already exist, but it changes decisions: dependencies are settled in the room, and the plan is a commitment the whole group makes together. It changes the routine, since the group pauses its normal work for the event at each planning interval, and prepares for weeks beforehand. The measures are what share of the committed objectives each team delivers, the number of dependencies found late, and how long planning takes.

Sustaining it takes preparation: clear priorities, a draft vision, a room set up for it, and leaders who come and stay. In the first year, expect the first events to be rough, with plans that overcommit and dependencies discovered a day late, and expect the second and third to be calmer. A business that plans this way depends less on a few coordinators who carry the dependency map in their heads, and sees its commitments on one board.

Where it goes wrong

One failure is the event with no decisions. Leaders give presentations, teams fill in templates, and nobody with authority is present to trade scope, so the plan is a wish list. The sign is a plan that still exceeds capacity when the event ends.

Another is cost and fatigue. Pulling dozens or hundreds of people into a room for a day or two is expensive, and a group that plans too often or with too little purpose will learn to resent it. The sign is shrinking attendance and half-hearted participation.

A third is a plan treated as a promise. Commitments made in the room can harden into a schedule that teams defend after the market has moved. The sign is surprise at a change that everyone could see coming. In fast-changing fields, a plan that runs a quarter ahead may also be too long.

Related and rival frameworks

  • PI Planning. SAFe's prescribed version: two days for one release train every 8 to 12 weeks, with set roles, a set agenda, and a confidence vote. The better entry when the group runs SAFe.
  • SAFe (Scaled Agile Framework). The framework that made the practice familiar in software. Read it for the train, roles, and portfolio its version assumes.
  • Integrated Project Delivery. The construction approach whose teams, bound by one shared contract, often plan and decide in a Big Room. The better frame for a building project.
  • Large-Scale Scrum (LeSS). Plans many teams together in two short meetings. Choose it for fewer people and a lighter event.

Go to the source

Back to the catalog