Work Breakdown Structure

Layers of Management ThoughtLayer 9: Tools and TechniquesToolAlso known as WBS

Developed within United States defense and space program management in the early 1960s, set out in a joint Department of Defense and NASA PERT/COST guide of 1962, and later required across defense programs by MIL-STD-881.

Breaks the total scope of a project into a hierarchy of deliverables and work packages, so that every piece of work has a place, an owner, and a basis for estimating, and no work sits outside the structure.

Eight pieces of a warehouse move, sorted by their level in the structure

A work breakdown structure names deliverables and work packages and leaves the verbs to the schedule. Select a piece, then the level it belongs at: each level says what it holds. Show the sort to compare yours. Illustrative.

Items (select one, then a box)
  • Not placedPlacedThe wholeDeliverableWork packageSchedule
  • Not placedPlacedThe wholeDeliverableWork packageSchedule
  • Not placedPlacedThe wholeDeliverableWork packageSchedule
  • Not placedPlacedThe wholeDeliverableWork packageSchedule
  • Not placedPlacedThe wholeDeliverableWork packageSchedule
  • Not placedPlacedThe wholeDeliverableWork packageSchedule
  • Not placedPlacedThe wholeDeliverableWork packageSchedule
  • Not placedPlacedThe wholeDeliverableWork packageSchedule

Pieces

The move
The whole
Deliverable
Work package
Schedule
The wholeDeliverableWork packageLeft to the schedule

Level in the structure

Returns center relocation. The sponsor's one-line description of the project.Not placed yet.Returns center relocation. The sponsor's one-line description of the project.The whole: The project itself, at the top. Everything below it must add up to it, with nothing missing and nothing extra.One box that stands for all the work. Every level below must sum to it.Returns center relocation. The sponsor's one-line description of the project.Deliverable: A thing that will exist when the work is done, named as a noun. Each one divides again until the pieces can be owned.Returns center relocation. The sponsor's one-line description of the project.Work package: The lowest box the structure names: small enough to estimate, give to one owner, and track.Returns center relocation. The sponsor's one-line description of the project.Schedule: A verb step inside a work package. The schedule lists these and puts them in order. The structure stops above them.Racking installed. A result the project hands over.Not placed yet.Racking installed. A result the project hands over.The whole: The project itself, at the top. Everything below it must add up to it, with nothing missing and nothing extra.Racking installed. A result the project hands over.Deliverable: A thing that will exist when the work is done, named as a noun. Each one divides again until the pieces can be owned.A noun that will exist when done. It divides into work packages by zone or by contractor.Racking installed. A result the project hands over.Work package: The lowest box the structure names: small enough to estimate, give to one owner, and track.Racking installed. A result the project hands over.Schedule: A verb step inside a work package. The schedule lists these and puts them in order. The structure stops above them.Safety approved. The city inspection and the fire-suppression sign-off.Not placed yet.Safety approved. The city inspection and the fire-suppression sign-off.The whole: The project itself, at the top. Everything below it must add up to it, with nothing missing and nothing extra.Safety approved. The city inspection and the fire-suppression sign-off.Deliverable: A thing that will exist when the work is done, named as a noun. Each one divides again until the pieces can be owned.A deliverable even though it is not a physical object. The first plan had nothing for it, which is how the gap went unseen.Safety approved. The city inspection and the fire-suppression sign-off.Work package: The lowest box the structure names: small enough to estimate, give to one owner, and track.Safety approved. The city inspection and the fire-suppression sign-off.Schedule: A verb step inside a work package. The schedule lists these and puts them in order. The structure stops above them.Staff trained on scanners. Every picker certified on the new scanners.Not placed yet.Staff trained on scanners. Every picker certified on the new scanners.The whole: The project itself, at the top. Everything below it must add up to it, with nothing missing and nothing extra.Staff trained on scanners. Every picker certified on the new scanners.Deliverable: A thing that will exist when the work is done, named as a noun. Each one divides again until the pieces can be owned.A result with several owners underneath, so it divides into work packages by shift.Staff trained on scanners. Every picker certified on the new scanners.Work package: The lowest box the structure names: small enough to estimate, give to one owner, and track.Staff trained on scanners. Every picker certified on the new scanners.Schedule: A verb step inside a work package. The schedule lists these and puts them in order. The structure stops above them.Rack anchoring, east wall. One lead, four days, one crew.Not placed yet.Rack anchoring, east wall. One lead, four days, one crew.The whole: The project itself, at the top. Everything below it must add up to it, with nothing missing and nothing extra.Rack anchoring, east wall. One lead, four days, one crew.Deliverable: A thing that will exist when the work is done, named as a noun. Each one divides again until the pieces can be owned.Rack anchoring, east wall. One lead, four days, one crew.Work package: The lowest box the structure names: small enough to estimate, give to one owner, and track.Small enough to estimate and give to one owner, and large enough to report on weekly.Rack anchoring, east wall. One lead, four days, one crew.Schedule: A verb step inside a work package. The schedule lists these and puts them in order. The structure stops above them.Cabling contract, zone 2. One vendor, one price, one finish date.Not placed yet.Cabling contract, zone 2. One vendor, one price, one finish date.The whole: The project itself, at the top. Everything below it must add up to it, with nothing missing and nothing extra.Cabling contract, zone 2. One vendor, one price, one finish date.Deliverable: A thing that will exist when the work is done, named as a noun. Each one divides again until the pieces can be owned.Cabling contract, zone 2. One vendor, one price, one finish date.Work package: The lowest box the structure names: small enough to estimate, give to one owner, and track.One owner and one estimate, so cost and slippage can be tracked against it.Cabling contract, zone 2. One vendor, one price, one finish date.Schedule: A verb step inside a work package. The schedule lists these and puts them in order. The structure stops above them.Book the forklift for Monday. A step the rack crew takes.Not placed yet.Book the forklift for Monday. A step the rack crew takes.The whole: The project itself, at the top. Everything below it must add up to it, with nothing missing and nothing extra.Book the forklift for Monday. A step the rack crew takes.Deliverable: A thing that will exist when the work is done, named as a noun. Each one divides again until the pieces can be owned.Book the forklift for Monday. A step the rack crew takes.Work package: The lowest box the structure names: small enough to estimate, give to one owner, and track.Book the forklift for Monday. A step the rack crew takes.Schedule: A verb step inside a work package. The schedule lists these and puts them in order. The structure stops above them.A verb step inside a work package. It belongs on the schedule, and listing it here would bury the structure in detail.Call the electrician. A step inside the cabling work package.Not placed yet.Call the electrician. A step inside the cabling work package.The whole: The project itself, at the top. Everything below it must add up to it, with nothing missing and nothing extra.Call the electrician. A step inside the cabling work package.Deliverable: A thing that will exist when the work is done, named as a noun. Each one divides again until the pieces can be owned.Call the electrician. A step inside the cabling work package.Work package: The lowest box the structure names: small enough to estimate, give to one owner, and track.Call the electrician. A step inside the cabling work package.Schedule: A verb step inside a work package. The schedule lists these and puts them in order. The structure stops above them.An activity, not a result. The structure names what the electrician delivers, and the schedule names the call.

Your sort matched 0 of 8.Your sort matched 1 of 8.Your sort matched 2 of 8.Your sort matched 3 of 8.Your sort matched 4 of 8.Your sort matched 5 of 8.Your sort matched 6 of 8.Your sort matched 7 of 8.Your sort matched 8 of 8.

The whole
The project itself, at the top. Everything below it must add up to it, with nothing missing and nothing extra.
Deliverable
A thing that will exist when the work is done, named as a noun. Each one divides again until the pieces can be owned.
Work package
The lowest box the structure names: small enough to estimate, give to one owner, and track.
Schedule
A verb step inside a work package. The schedule lists these and puts them in order. The structure stops above them.

The sort

  • Returns center relocation: The whole. One box that stands for all the work. Every level below must sum to it.
  • Racking installed: Deliverable. A noun that will exist when done. It divides into work packages by zone or by contractor.
  • Safety approved: Deliverable. A deliverable even though it is not a physical object. The first plan had nothing for it, which is how the gap went unseen.
  • Staff trained on scanners: Deliverable. A result with several owners underneath, so it divides into work packages by shift.
  • Rack anchoring, east wall: Work package. Small enough to estimate and give to one owner, and large enough to report on weekly.
  • Cabling contract, zone 2: Work package. One owner and one estimate, so cost and slippage can be tracked against it.
  • Book the forklift for Monday: Schedule. A verb step inside a work package. It belongs on the schedule, and listing it here would bury the structure in detail.
  • Call the electrician: Schedule. An activity, not a result. The structure names what the electrician delivers, and the schedule names the call.

An example

A regional distributor planned to move its returns center over six months. The first plan was a list of 140 tasks that the operations director kept in a spreadsheet. Two weeks before the move, the safety officer asked who owned the fire-suppression sign-off. Nobody did. The list held "call the electrician" and "book the forklift", but nothing for the inspection the city required before racking could be loaded.

The project manager rebuilt the plan from the top. The move came first, then six deliverables: racking installed, power and cabling, scanners configured, staff trained, safety approved, and inventory transferred. Under each sat work packages with one owner and an estimate in days. Laid out this way, safety approval had no work packages at all, and scanner configuration carried three weeks of effort that the old list had priced at three days. The move slipped by two weeks, but nothing had to be redone, and finance finally had a budget by deliverable instead of a pile of invoices.

The core idea

A work breakdown structure divides a project by what it must produce. When the work happens and who does it come later. The top box is the whole project, the next level its major deliverables, and each deliverable divides again until the lowest boxes, called work packages, are small enough to estimate, assign to one owner, and track. NASA's systems engineering handbook defines it by product: a hierarchy of everything the project must deliver, from hardware and software to services and data, laid out so that cost, schedule, and risk can be added up and reported box by box.

The insight is that the structure works as a completeness test. The parts of any box must add up to that box, with nothing missing and nothing extra, so a gap in the structure is a gap in the plan. Boxes name things that will exist, in nouns. The verbs, the order of work, and the dates belong to the schedule that hangs from the structure afterward.

The thinking behind it

United States defense and space program management practice of the early 1960s, built on the Navy's PERT No single author is credited. Histories of the method trace it to PERT, built for the Navy's Polaris missile program, whose 1959 account broke the work into systems, subsystems, and components. By the early 1960s the idea had moved into cost control, and a joint Department of Defense and NASA guide to PERT/COST of June 1962 described how to build one. The Defense Department issued MIL-STD-881 on November 1, 1968, requiring a structure across defense programs. The problem it answered was cost control on programs too large for anyone to hold in their head: money and schedule had to roll up from small pieces to a whole.

Where it sits in the layers

The Work Breakdown Structure sits in Layer 9, Tools and Techniques, because it is a portable instrument that many methodologies borrow and none owns. It takes for granted, from the layers above, that a body of work divides into parts whose sum is the whole and that most of the effort can be known before it starts. That assumption suits stable, mechanistic organizations better than fluid ones. Above it, Layer 8 methods lean on it: earned value management measures progress box by box, and the PMBOK process groups assume one. Below it, the structure is put into practice in the weekly status meeting, where each box reports. The common mistake is asking it to answer a Layer 8 question. A structure says what the work is. It does not say how the team should run, in what order, or how to respond when the first plan proves wrong.

How organizations put it to work

A project manager owns the structure, with the sponsor approving the top two levels and a project office keeping a template library. It changes four things. Decisions: budgets and approvals attach to deliverables, so a request for more money names the box it enlarges. Structure: every work package has exactly one accountable owner. Routines: a change request is tested against the structure, which shows whether it adds a box, grows one, or sits outside the project. Measures: status and cost are reported by box, so a variance has an address.

Sustaining it takes a short dictionary entry for each work package (scope, owner, estimate, and what counts as done) and a rule that the structure is updated before the schedule is. Without that rule it becomes a document from week one that nobody reads.

In the first year a leader should expect the first plans to take longer to build and to surface work nobody had priced. Estimates for similar projects start to agree with each other once the template library has two or three finished projects behind it, which also lets a second manager plan a project without the first one in the room.

Where it goes wrong

The first failure is dividing by activity or department. A structure whose boxes begin with verbs, or are named for teams, cannot be checked for completeness, and it redraws the org chart. The sign is boxes titled "Engineering" and "Testing".

The second is the wrong depth. Too shallow, and a work package runs for months with no way to see it slipping. Too deep, and hundreds of small boxes need weekly updates that nobody makes, so the structure goes stale. The sign is status reports that cannot be tied to any box.

The third is treating the structure as fixed when the work is uncertain. In software and research, much of the scope is discovered along the way, and a detailed breakdown made on day one is guesswork written down. Critics prefer rolling-wave planning, in which near-term work is broken down fully and later work stays coarse. The sign is weekly change requests.

Related and rival frameworks

  • RACI Matrix. Assigns people to the boxes the structure creates, showing who does, approves, and is consulted on each. The better pick when the scope is clear and the open question is ownership.
  • Gantt Chart. Puts the work packages on a calendar. It answers when, where the structure answers what, so the two are used in sequence.
  • PMBOK Guide. The body of practice in which the structure sits as one planning step among many. Read it when the question is how to run the project, not how to divide it.