Risk Register and Risk Matrix

Layers of Management ThoughtLayer 9: Tools and TechniquesToolAlso known as Risk log, Risk register, Probability and impact matrix, Risk matrix

No single author: a practice of project and risk management whose probability-and-impact matrix spread through standards such as Military Standard 882C and the Australian and New Zealand standard AS/NZS 4360 of 1999, as Tony Cox notes in his critical 2008 paper on risk matrices.

A structured log of identified risks, each with its likelihood, its impact, an owner, and a planned response, usually shown on a matrix, so a team knows what could go wrong and who is dealing with it.

Eight launch risks placed on a probability and impact matrix

Each note gives a rough chance and cost. Select a risk, then the cell it belongs in; the cell names the band and says what to do. Two risks in the same band can differ a lot in dollars, which is where the matrix gets crude. Show the sort to compare yours. Illustrative.

Items (select one, then a box)
  • Not placedPlacedAccept and watchAccept and watchAccept and watchPlan a responseAccept and watchPlan a responsePlan a responsePlan a responseAccept and watchPlan a responseAct nowAct nowPlan a responsePlan a responseAct nowAct now
  • Not placedPlacedAccept and watchAccept and watchAccept and watchPlan a responseAccept and watchPlan a responsePlan a responsePlan a responseAccept and watchPlan a responseAct nowAct nowPlan a responsePlan a responseAct nowAct now
  • Not placedPlacedAccept and watchAccept and watchAccept and watchPlan a responseAccept and watchPlan a responsePlan a responsePlan a responseAccept and watchPlan a responseAct nowAct nowPlan a responsePlan a responseAct nowAct now
  • Not placedPlacedAccept and watchAccept and watchAccept and watchPlan a responseAccept and watchPlan a responsePlan a responsePlan a responseAccept and watchPlan a responseAct nowAct nowPlan a responsePlan a responseAct nowAct now
  • Not placedPlacedAccept and watchAccept and watchAccept and watchPlan a responseAccept and watchPlan a responsePlan a responsePlan a responseAccept and watchPlan a responseAct nowAct nowPlan a responsePlan a responseAct nowAct now
  • Not placedPlacedAccept and watchAccept and watchAccept and watchPlan a responseAccept and watchPlan a responsePlan a responsePlan a responseAccept and watchPlan a responseAct nowAct nowPlan a responsePlan a responseAct nowAct now
  • Not placedPlacedAccept and watchAccept and watchAccept and watchPlan a responseAccept and watchPlan a responsePlan a responsePlan a responseAccept and watchPlan a responseAct nowAct nowPlan a responsePlan a responseAct nowAct now
  • Not placedPlacedAccept and watchAccept and watchAccept and watchPlan a responseAccept and watchPlan a responsePlan a responsePlan a responseAccept and watchPlan a responseAct nowAct nowPlan a responsePlan a responseAct nowAct now

How costly if it happens

Severe >$1.5MMajor $0.3-1.5MModerate $50-299KMinor <$50K
Plan a response
Plan a response
Act now
Act now
Accept and watch
Plan a response
Act now
Act now
Accept and watch
Plan a response
Plan a response
Plan a response
Accept and watch
Accept and watch
Accept and watch
Plan a response
Rare <10%Unlikely 10%+Likely 40%+Almost sure 80%+

How likely

Key engineer leaves. A 60% chance, about $400K of delay and rework.Not placed yet.Key engineer leaves. A 60% chance, about $400K of delay and rework.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Key engineer leaves. A 60% chance, about $400K of delay and rework.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Key engineer leaves. A 60% chance, about $400K of delay and rework.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Key engineer leaves. A 60% chance, about $400K of delay and rework.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Key engineer leaves. A 60% chance, about $400K of delay and rework.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Key engineer leaves. A 60% chance, about $400K of delay and rework.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Key engineer leaves. A 60% chance, about $400K of delay and rework.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Key engineer leaves. A 60% chance, about $400K of delay and rework.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Key engineer leaves. A 60% chance, about $400K of delay and rework.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Key engineer leaves. A 60% chance, about $400K of delay and rework.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Key engineer leaves. A 60% chance, about $400K of delay and rework.Act now: Fund a response now, name a senior owner, and report the risk to the steering group every week.Likely and costly. Arrange a handover and a retention plan now.Key engineer leaves. A 60% chance, about $400K of delay and rework.Act now: Fund a response now, name a senior owner, and report the risk to the steering group every week.Key engineer leaves. A 60% chance, about $400K of delay and rework.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Key engineer leaves. A 60% chance, about $400K of delay and rework.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Key engineer leaves. A 60% chance, about $400K of delay and rework.Act now: Fund a response now, name a senior owner, and report the risk to the steering group every week.Key engineer leaves. A 60% chance, about $400K of delay and rework.Act now: Fund a response now, name a senior owner, and report the risk to the steering group every week.Vendor integration delays. An 80% chance, about $900K of lost time.Not placed yet.Vendor integration delays. An 80% chance, about $900K of lost time.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Vendor integration delays. An 80% chance, about $900K of lost time.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Vendor integration delays. An 80% chance, about $900K of lost time.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Vendor integration delays. An 80% chance, about $900K of lost time.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Vendor integration delays. An 80% chance, about $900K of lost time.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Vendor integration delays. An 80% chance, about $900K of lost time.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Vendor integration delays. An 80% chance, about $900K of lost time.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Vendor integration delays. An 80% chance, about $900K of lost time.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Vendor integration delays. An 80% chance, about $900K of lost time.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Vendor integration delays. An 80% chance, about $900K of lost time.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Vendor integration delays. An 80% chance, about $900K of lost time.Act now: Fund a response now, name a senior owner, and report the risk to the steering group every week.Vendor integration delays. An 80% chance, about $900K of lost time.Act now: Fund a response now, name a senior owner, and report the risk to the steering group every week.Vendor integration delays. An 80% chance, about $900K of lost time.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Vendor integration delays. An 80% chance, about $900K of lost time.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Vendor integration delays. An 80% chance, about $900K of lost time.Act now: Fund a response now, name a senior owner, and report the risk to the steering group every week.Almost certain, and large. Secure a dedicated team in the contract before it slips.Vendor integration delays. An 80% chance, about $900K of lost time.Act now: Fund a response now, name a senior owner, and report the risk to the steering group every week.Key supplier fails. A 20% chance, about $2.4M if it happens.Not placed yet.Key supplier fails. A 20% chance, about $2.4M if it happens.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Key supplier fails. A 20% chance, about $2.4M if it happens.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Key supplier fails. A 20% chance, about $2.4M if it happens.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Key supplier fails. A 20% chance, about $2.4M if it happens.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Key supplier fails. A 20% chance, about $2.4M if it happens.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Key supplier fails. A 20% chance, about $2.4M if it happens.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Key supplier fails. A 20% chance, about $2.4M if it happens.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Key supplier fails. A 20% chance, about $2.4M if it happens.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Unlikely but severe, so plan a second source. Its expected loss is about ten times that of scope creep, though both sit in the same band.Key supplier fails. A 20% chance, about $2.4M if it happens.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Key supplier fails. A 20% chance, about $2.4M if it happens.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Key supplier fails. A 20% chance, about $2.4M if it happens.Act now: Fund a response now, name a senior owner, and report the risk to the steering group every week.Key supplier fails. A 20% chance, about $2.4M if it happens.Act now: Fund a response now, name a senior owner, and report the risk to the steering group every week.Key supplier fails. A 20% chance, about $2.4M if it happens.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Key supplier fails. A 20% chance, about $2.4M if it happens.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Key supplier fails. A 20% chance, about $2.4M if it happens.Act now: Fund a response now, name a senior owner, and report the risk to the steering group every week.Key supplier fails. A 20% chance, about $2.4M if it happens.Act now: Fund a response now, name a senior owner, and report the risk to the steering group every week.Scope creep on the pilot. A 90% chance, about $60K.Not placed yet.Scope creep on the pilot. A 90% chance, about $60K.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Scope creep on the pilot. A 90% chance, about $60K.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Scope creep on the pilot. A 90% chance, about $60K.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Scope creep on the pilot. A 90% chance, about $60K.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Scope creep on the pilot. A 90% chance, about $60K.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Scope creep on the pilot. A 90% chance, about $60K.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Scope creep on the pilot. A 90% chance, about $60K.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Scope creep on the pilot. A 90% chance, about $60K.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Scope creep on the pilot. A 90% chance, about $60K.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Scope creep on the pilot. A 90% chance, about $60K.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Scope creep on the pilot. A 90% chance, about $60K.Act now: Fund a response now, name a senior owner, and report the risk to the steering group every week.Scope creep on the pilot. A 90% chance, about $60K.Act now: Fund a response now, name a senior owner, and report the risk to the steering group every week.Scope creep on the pilot. A 90% chance, about $60K.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Scope creep on the pilot. A 90% chance, about $60K.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Nearly certain and modest. Handle with a change process. Same band as the supplier risk, a tenth of the expected loss.Scope creep on the pilot. A 90% chance, about $60K.Act now: Fund a response now, name a senior owner, and report the risk to the steering group every week.Scope creep on the pilot. A 90% chance, about $60K.Act now: Fund a response now, name a senior owner, and report the risk to the steering group every week.Data breach at launch. A 5% chance, about $5M.Not placed yet.Data breach at launch. A 5% chance, about $5M.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Data breach at launch. A 5% chance, about $5M.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Data breach at launch. A 5% chance, about $5M.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Data breach at launch. A 5% chance, about $5M.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Rare and severe. A matrix that dismissed it as unlikely would miss it, so it needs a response plan.Data breach at launch. A 5% chance, about $5M.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Data breach at launch. A 5% chance, about $5M.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Data breach at launch. A 5% chance, about $5M.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Data breach at launch. A 5% chance, about $5M.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Data breach at launch. A 5% chance, about $5M.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Data breach at launch. A 5% chance, about $5M.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Data breach at launch. A 5% chance, about $5M.Act now: Fund a response now, name a senior owner, and report the risk to the steering group every week.Data breach at launch. A 5% chance, about $5M.Act now: Fund a response now, name a senior owner, and report the risk to the steering group every week.Data breach at launch. A 5% chance, about $5M.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Data breach at launch. A 5% chance, about $5M.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Data breach at launch. A 5% chance, about $5M.Act now: Fund a response now, name a senior owner, and report the risk to the steering group every week.Data breach at launch. A 5% chance, about $5M.Act now: Fund a response now, name a senior owner, and report the risk to the steering group every week.Regulator rejects design. A 30% chance, about $1.2M.Not placed yet.Regulator rejects design. A 30% chance, about $1.2M.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Regulator rejects design. A 30% chance, about $1.2M.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Regulator rejects design. A 30% chance, about $1.2M.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Regulator rejects design. A 30% chance, about $1.2M.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Regulator rejects design. A 30% chance, about $1.2M.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Regulator rejects design. A 30% chance, about $1.2M.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Regulator rejects design. A 30% chance, about $1.2M.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Plan a response, such as an early meeting with the regulator, since a rejection would be costly.Regulator rejects design. A 30% chance, about $1.2M.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Regulator rejects design. A 30% chance, about $1.2M.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Regulator rejects design. A 30% chance, about $1.2M.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Regulator rejects design. A 30% chance, about $1.2M.Act now: Fund a response now, name a senior owner, and report the risk to the steering group every week.Regulator rejects design. A 30% chance, about $1.2M.Act now: Fund a response now, name a senior owner, and report the risk to the steering group every week.Regulator rejects design. A 30% chance, about $1.2M.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Regulator rejects design. A 30% chance, about $1.2M.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Regulator rejects design. A 30% chance, about $1.2M.Act now: Fund a response now, name a senior owner, and report the risk to the steering group every week.Regulator rejects design. A 30% chance, about $1.2M.Act now: Fund a response now, name a senior owner, and report the risk to the steering group every week.Training slips a week. A 50% chance, about $15K.Not placed yet.Training slips a week. A 50% chance, about $15K.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Training slips a week. A 50% chance, about $15K.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Training slips a week. A 50% chance, about $15K.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Training slips a week. A 50% chance, about $15K.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Training slips a week. A 50% chance, about $15K.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Training slips a week. A 50% chance, about $15K.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Training slips a week. A 50% chance, about $15K.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Training slips a week. A 50% chance, about $15K.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Training slips a week. A 50% chance, about $15K.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Likely but small. Log it, watch it, and absorb the cost.Training slips a week. A 50% chance, about $15K.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Training slips a week. A 50% chance, about $15K.Act now: Fund a response now, name a senior owner, and report the risk to the steering group every week.Training slips a week. A 50% chance, about $15K.Act now: Fund a response now, name a senior owner, and report the risk to the steering group every week.Training slips a week. A 50% chance, about $15K.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Training slips a week. A 50% chance, about $15K.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Training slips a week. A 50% chance, about $15K.Act now: Fund a response now, name a senior owner, and report the risk to the steering group every week.Training slips a week. A 50% chance, about $15K.Act now: Fund a response now, name a senior owner, and report the risk to the steering group every week.Laptop delivery late. A 15% chance, about $10K.Not placed yet.Laptop delivery late. A 15% chance, about $10K.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Laptop delivery late. A 15% chance, about $10K.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Laptop delivery late. A 15% chance, about $10K.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Laptop delivery late. A 15% chance, about $10K.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Laptop delivery late. A 15% chance, about $10K.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Unlikely and minor. Accept it and keep it on the list.Laptop delivery late. A 15% chance, about $10K.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Laptop delivery late. A 15% chance, about $10K.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Laptop delivery late. A 15% chance, about $10K.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Laptop delivery late. A 15% chance, about $10K.Accept and watch: Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.Laptop delivery late. A 15% chance, about $10K.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Laptop delivery late. A 15% chance, about $10K.Act now: Fund a response now, name a senior owner, and report the risk to the steering group every week.Laptop delivery late. A 15% chance, about $10K.Act now: Fund a response now, name a senior owner, and report the risk to the steering group every week.Laptop delivery late. A 15% chance, about $10K.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Laptop delivery late. A 15% chance, about $10K.Plan a response: Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.Laptop delivery late. A 15% chance, about $10K.Act now: Fund a response now, name a senior owner, and report the risk to the steering group every week.Laptop delivery late. A 15% chance, about $10K.Act now: Fund a response now, name a senior owner, and report the risk to the steering group every week.

Your sort matched 0 of 8.Your sort matched 1 of 8.Your sort matched 2 of 8.Your sort matched 3 of 8.Your sort matched 4 of 8.Your sort matched 5 of 8.Your sort matched 6 of 8.Your sort matched 7 of 8.Your sort matched 8 of 8.

Accept and watch
Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.
Accept and watch
Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.
Accept and watch
Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.
Plan a response
Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.
Accept and watch
Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.
Plan a response
Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.
Plan a response
Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.
Plan a response
Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.
Accept and watch
Log it, name an owner to watch it, and spend nothing now. Revisit it if the numbers change.
Plan a response
Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.
Act now
Fund a response now, name a senior owner, and report the risk to the steering group every week.
Act now
Fund a response now, name a senior owner, and report the risk to the steering group every week.
Plan a response
Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.
Plan a response
Write a response with an owner and a trigger, and review it each period. Fund it if it is cheap and wait if it is not.
Act now
Fund a response now, name a senior owner, and report the risk to the steering group every week.
Act now
Fund a response now, name a senior owner, and report the risk to the steering group every week.

The sort

  • Key engineer leaves: Act now. Likely and costly. Arrange a handover and a retention plan now.
  • Vendor integration delays: Act now. Almost certain, and large. Secure a dedicated team in the contract before it slips.
  • Key supplier fails: Plan a response. Unlikely but severe, so plan a second source. Its expected loss is about ten times that of scope creep, though both sit in the same band.
  • Scope creep on the pilot: Plan a response. Nearly certain and modest. Handle with a change process. Same band as the supplier risk, a tenth of the expected loss.
  • Data breach at launch: Plan a response. Rare and severe. A matrix that dismissed it as unlikely would miss it, so it needs a response plan.
  • Regulator rejects design: Plan a response. Plan a response, such as an early meeting with the regulator, since a rejection would be costly.
  • Training slips a week: Accept and watch. Likely but small. Log it, watch it, and absorb the cost.
  • Laptop delivery late: Accept and watch. Unlikely and minor. Accept it and keep it on the list.

An example

A software company preparing a payments launch kept its worries in email and in the margins of meeting notes. The program manager started a register of 24 risks. Each had a plain description, a likelihood, a cost if it happened, a named owner, a response, and a date by which the response had to be in place. A fifteen-minute review each week kept it current, and the five risks in the top band went to the steering group.

Two things changed the plan. The risk that a key engineer would leave, rated likely and costly, had an owner who arranged a knowledge handover and a retention bonus, and when the engineer resigned in week nine the work carried on. And a long argument over two risks that sat in the same color band, a supplier failure and a scope creep, ended when the owner pointed out that the first carried about ten times the expected loss of the second. The team began writing dollar figures beside the colors.

The core idea

A risk register is a record of identified risks. Each entry typically carries a description, a likelihood, an impact, a score that multiplies the two, a named owner, a response, a trigger that says when the response starts, and a status. The risks are usually plotted on a matrix, with likelihood along one axis and impact along the other, and the cells are grouped into bands, such as accept and watch, plan a response, and act now.

The idea that makes it more than a list is ownership and response. A risk with a name beside it and a prepared answer is a managed risk, and one without is only a worry. The register also carries memory: it records what was known, what was decided, and what happened, so that a handover does not lose the thread. The matrix adds a quick way to rank. It also compresses, a point the criticism below takes up.

The thinking behind it

Project and risk management practice from the 1990s, spread by national and international standards No individual devised the risk register. It grew out of project and risk management practice, and standards pushed the probability-and-impact matrix into wide use: Tony Cox credits national and international standards, Military Standard 882C and the Australian and New Zealand AS/NZS 4360 of 1999 among them, with spreading risk matrices through organizations and their consultants. Project management guides, PMI's PMBOK Guide among them, treat the register as the main record of identified risks. The practice answers a plain problem: risks known to someone are not known to the team, and a risk nobody owns is rarely acted on.

Where it sits in the layers

The risk register sits in Layer 9, Tools and Techniques, as a log that any project or function can keep. It puts into practice the expected-loss logic of Decision Theory in Layer 1, in which a risk is judged by how likely it is and how much it would cost. It serves the risk processes that ISO 31000 and PMBOK in Layer 8 set out, which call for risks to be recorded and owned, and below, it is reviewed in the weekly risk meetings of Layer 10. The common mistake is asking the register to find the risks. It records what people have thought of, and the quality of the entries depends on the thinking behind them. A register full of risks everyone already knew still leaves out the ones nobody has imagined.

How organizations put it to work

Ownership sits with the project manager for a project register and with a risk or compliance function for an enterprise one. Every entry has a named owner who is accountable for the response. The register is reviewed on a fixed rhythm, weekly on a fast project and monthly elsewhere, and risks above a threshold are escalated to a steering group.

The structure it adds is a link between risk and money. Responses that cost something are funded or declined in the open, and contingency in the budget is tied to the risks on the register. The measures are the number of open risks by band, actions that are overdue, risks closed, and risks that happened without having been logged. A register becomes more useful when entries give the cost and the probability as numbers with ranges as well as colors.

Sustaining it takes a short, regular review and a habit of closing risks. In the first year a leader should expect the list to balloon, some arguments over scoring, and a first real test when a logged risk occurs and the prepared response either works or does not.

Where it goes wrong

The first failure is the matrix itself. Tony Cox's 2008 analysis found that a typical matrix ranks fewer than one in ten randomly chosen pairs of risks unambiguously, lumps very different risks into one rating, and for some risks steers decisions worse than chance. The sign is two risks in the same color with very different dollar figures.

The second is the register as paperwork, filed and forgotten. The sign is a list unchanged for months, with owners who cannot say what they are doing about their risks. Alexander Budzier's 2011 commentary, The Risk of Risk Registers, puts the point in its subtitle: managing risk is managing discourse.

The third is ranking without interactions. Scoring each risk alone ignores the way one response can reduce several risks at once, and Cox showed in 2009 that ranking falls short of the best reduction when those effects are correlated. The sign is a budget spent down the list, ignoring shared remedies.

Related and rival frameworks

  • Premortem. Asks a team to imagine the project has failed and explain why. Better for finding risks before the register is started.
  • Failure Mode and Effects Analysis. Scores failure modes by severity, occurrence, and detection. Better for engineered products and processes, where each failure can be traced to a step.
  • Monte Carlo Simulation. Turns uncertain costs and probabilities into a distribution of outcomes. Better when the register's colors need to become numbers that can be added up.