Created by A. Ernest Fitzgerald in his Earned Value Summary Guide (1965) for the US Air Force's Minuteman program, and made a Defense Department requirement as the Cost/Schedule Control Systems Criteria by a 1967 instruction.
A method that measures project performance by comparing the value of work actually done with both the plan and the money spent, giving an objective index of schedule and cost and a forecast of the final cost.
A $10 million signaling upgrade at the halfway point of its schedule
The plan called for $5.0 million of work to be done by now. Set the share of the work that is actually complete and the money spent so far. The bars compare planned value, earned value, and actual cost, and the forecast is the budget divided by the cost performance index. Illustrative.
$ million
An example
A transit authority was halfway through the schedule of a signaling upgrade budgeted at ten million dollars. The monthly report said it had spent five and a half million, which was right on track for a project that should have spent five, and the contractor called the project healthy. The program director was uneasy. The cabling in two stations looked far from finished.
Her analyst restated the report in three numbers. The plan said five million dollars of work should be done by now. The work that was actually finished, valued at its budgeted price, came to four million. The money spent was five and a half. Work was behind plan by a fifth, and each dollar spent had earned about seventy-three cents. At that rate the final cost would be nearly fourteen million. She took the new figures to the board, which cut scope on two stations and replaced the contractor's reporting with this method at once, a year earlier than the overrun would have otherwise surfaced.
The core idea
Earned value management values every piece of planned work at its budgeted cost and counts that budget as earned when the work is done. Three quantities follow. Planned value is the budgeted cost of the work scheduled to date. Earned value is the budgeted cost of the work actually completed. Actual cost is what was spent. Comparing them gives two indices. Earned value over planned value is the schedule performance index, and earned value over actual cost is the cost performance index. Below one, the project is behind plan or over budget.
The cost index also yields a forecast: divide the budget at completion by it to estimate the final cost. The method rests on a measurement baseline that does not flex, so that revisions are limited to the addition or deletion of specific work, and overruns cannot be hidden by adjusting the plan after the fact. The insight is that spending alone says nothing about progress. A project that has spent half its budget is healthy only if it has done half its work.
The thinking behind it
A. Ernest Fitzgerald A. Ernest Fitzgerald, an industrial engineer, created earned value in the mid-1960s through his firm Performance Technology Corporation. Its Earned Value Summary Guide, delivered in 1965 to the Air Force's Ballistic Systems Division, put the idea in one sentence: an estimated value can be placed on all work to be performed, and once it is done that value is earned. The criteria were applied to the Minuteman missile contractors. The problem he addressed was that estimates at completion on large programs were notoriously inaccurate. The Air Force and then the Defense Department adopted the approach, and a 1967 instruction required the cost and schedule control systems criteria on selected acquisitions.
Where it sits in the layers
Earned value management belongs in Layer 8, Methodologies and Operating Systems, as a prescribed system for measuring project performance. It takes for granted that work can be broken into pieces with budgets and that progress can be judged against a plan, the planning assumptions of the improvement philosophies in Layer 6. It is put to work through tools in Layer 9, such as the work breakdown structure that carries the budgets, and through the monthly review in Layer 10. The common mistake is asking it to say whether the project should be done at all. It reports whether a project is going to plan, and a project that is on budget and on schedule can still deliver something nobody needs.
How organizations put it to work
A project controls group or a program office usually owns the system, with the project manager accountable for the numbers. It changes structure by creating control accounts, a unit of work with one owner, one budget, and one schedule, and it changes decisions: money is released against earned progress, and corrective action starts when an index falls below one. It changes routines, with a monthly performance report and a forecast of final cost that is revisited each month.
The measures are the two indices, the variance of each from plan, and the forecast against the budget. Sustaining it takes a stable baseline, honest rules for crediting progress, such as counting a task complete only when specified milestones are met, and reviewers who ask about the cause of a variance and leave blame aside.
In the first year, expect extra effort to build the baseline, early arguments over how to credit partial work, and a first forecast that is worse than the sponsor expected. The business gains early warning of an overrun and depends less on a project manager's reassurance.
Where it goes wrong
The most common failure is soft progress credit. If percent complete is a manager's estimate, optimism enters the earned value, and the index looks healthy while the work is not. The sign is a project that sits at ninety percent complete for months.
Close behind is overhead on small or uncertain work. The method grew up on large defense programs and suits work planned in detail up front. On a small project it costs more than it returns. The sign is a controls staff larger than the work warrants.
Last is false precision. The forecast assumes the future will cost what the past has, and a project that fixes its worst problems early will end below the forecast. Its history also shows confusion over terms, which caused practitioners and executives to misread the reports. The sign is a forecast that moves each month.
Related and rival frameworks
- PMBOK Guide. A general body of project knowledge that includes cost and schedule control. Choose it for the wider discipline, and use earned value as one of its measurement methods.
- PERT. Estimates the duration of each task from three scenarios. It describes the plan's uncertainty and does not measure performance against the plan.
- Critical Chain Project Management. Manages a schedule through a shared buffer, with no task-by-task variance. The better pick when time and resources matter more than cost.
Go to the source
- How It All Began: The Creation of Earned Value and the Evolution of C/SPCS and C/SCSC, The Measurable News, College of Performance Management (James B. Morin), 2016