Last Planner System

Layers of Management ThoughtLayer 8: Methodologies and Operating SystemsMethodologyAlso known as LPS, Last Planner

Developed by Glenn Ballard and Greg Howell through the 1990s, set out in their paper Shielding Production (1998) and in Ballard's doctoral thesis The Last Planner System of Production Control (2000).

A production planning system for construction in which the people who do the work make weekly commitments, only after removing what could block them, and measure how reliably they keep their promises.

One week's promises on an office fit-out, and how many survive when crews promise only work that is ready

The crews promise 25 tasks for the week. A task that has been made ready, with its materials, drawings, and space cleared, finishes 90 percent of the time. One that has not finishes 40 percent of the time. Set how many of the 25 are made ready before the promise is made and read the percent plan complete against the 70 percent benchmark. Illustrative.

0%
Tasks promised for the week
25
Tasks finished
10
Percent plan complete
40%
Tasks that slip to next week
15

Percent plan complete70 percent benchmark

0%25%50%75%100%0%20%40%60%80%100%0%25%50%75%100%0%20%40%60%80%100%

At this share made ready0%: Nothing was made ready, so most promises meet a missing drawing, a locked room, or late materials.20%: One task in five was made ready. The crews still promise work they cannot start, and the plan keeps slipping.40%: Two in five. The plan is more often met than missed, but it is far below the benchmark.60%: Three in five. Past the 70 percent benchmark is within reach.80%: Four in five. Crews are promising work that is nearly all ready to start, and the week's plan can be trusted.100%: Every promise was made ready first. The remaining misses are the surprises no planning could have seen.

An example

A general contractor was fitting out the interior of a ten-story office building, with a dozen trades sharing each floor. The master schedule showed every trade working in sequence, and every week the real work looked different: drywall crews arrived to find ceiling ductwork unfinished, electricians waited for a delayed panel, and painters could not enter a room still full of materials. Foremen kept about two in five of their weekly promises.

The contractor changed how it planned. Each Monday the foremen met and each described what they could do in the coming weeks. Before anyone promised a task for the following week, a short review asked what was blocking it, and someone took each blocker away or the task came off the list. Foremen then made weekly promises, and on Friday the team counted the share of promised tasks finished and noted why the rest were not. Within eight weeks, the share of promises kept had risen from about two in five to about four in five.

The core idea

The Last Planner System treats construction planning as a way to get reliable commitments from the people who direct the work, called the last planners. The Lean Construction Institute describes it as organized into five conversations. What should be done is set by milestone and pull planning, which works backward from a target date. What can be done is set by make-ready planning, which removes the constraints that would stop upcoming work. What will be done is the weekly work plan, in which each crew commits to tasks. What did get done is tracked in daily huddles and in percent plan complete, the share of promised tasks finished. What to learn is a weekly review of why plans failed.

The insight is that much schedule failure comes from promising work that is not ready. Traditional controls look back to see where work departed from plan. This system works ahead of the week, shielding crews from work they cannot yet do, so that the plan holds. Reliability of the plan is measured, and improving it improves productivity.

The thinking behind it

Glenn Ballard Glenn Ballard worked out the system with Greg Howell and wrote its fullest account in his doctoral thesis, The Last Planner System of Production Control, at the University of Birmingham in 2000. Where project controls had long looked back to find where work had strayed from plan, he wanted a system that makes plans come true in the first place. Specialty contractors had already used it on their own work, and the thesis carried it to the people who coordinate many specialists, in design as well as construction. He co-founded the Lean Construction Institute in 1997 and became its research director in 1999.

Greg Howell Greg Howell co-founded the Lean Construction Institute in 1997 with Ballard, Iris Tommelein, and Todd Zabelle, and became its executive director in 1999. With Ballard he published Shielding Production: Essential Step in Production Control in the Journal of Construction Engineering and Management in 1998. The two had worked on the system for four or five years before they used it to turn around a struggling project in Venezuela.

Where it sits in the layers

The Last Planner System is placed in Layer 8, Methodologies and Operating Systems, as a prescribed planning and control method for production work. It takes for granted the commitments of the layers above: the lean idea that flow and reliability matter more than the best plan on paper, and the view that those who do the work are best placed to say what they can do, ideas from Lean Thinking in Layer 6. It supports routines in Layer 10, such as the weekly planning meeting and the daily huddle, and it pairs naturally with Integrated Project Delivery. The common mistake is asking it to replace the master schedule or the contract. It governs near-term commitments, and it needs an overall plan and a shared structure of incentives above it.

How organizations put it to work

The project's general contractor or construction manager usually owns it, with a trained facilitator running the sessions and the foremen of each trade as the central actors. It changes structure little but changes authority: the last planners make the commitments, and a scheduler no longer does. It changes decisions, since work is promised only after constraints are cleared, and routines, with weekly planning sessions, daily huddles, and a Friday review of reasons for variance.

The measures are percent plan complete, constraints removed ahead of the date, and the reasons plans failed, grouped for action. Ballard's thesis notes a benchmark of about 70 percent, which earlier research linked to productivity gains, and a case that reached 90.

Sustaining it takes a facilitator, honest counting, and foremen who are expected to say why a commitment was missed and are not punished for it. In the first months, expect the percent to start low, uncomfortable meetings about who is blocking whom, and then a quick rise as constraints are removed. The business gains reliable handoffs between trades, less rework, and projects that depend less on one superintendent who keeps the real plan in a notebook.

Where it goes wrong

The most common failure is the metric as a score. Percent plan complete is reported to the owner as a performance grade, and foremen start promising less to look better. The sign is a high percent beside a late project.

Close behind is skipping make-ready. Weekly meetings take place, but nobody takes on the work of removing constraints, so promises are made as before. The sign is the same reasons for variance appearing every week.

Last is the limit of scope. The system governs the next weeks of work, and a project can be well planned weekly and still fail on design, cost, or contract disputes. It also relies on trust between trades, which a traditional contract that rewards each party separately may not support. The sign is crews who plan together and fight over change orders.

Related and rival frameworks

  • Integrated Project Delivery. A contract and team structure that aligns the parties' incentives. The better pick when the problem is the relationship among owner, designer, and builder.
  • Critical Chain Project Management. Schedules with buffers at the project level and aims at the bottleneck resource. Choose it when the work is a project schedule.
  • Lean Thinking. The philosophy of flow and waste reduction behind the system. Read it for the principles the method puts into practice.