Published by TSO in 2011 as UK government best-practice guidance, in the family that includes PRINCE2 and Managing Successful Programmes, which later passed to AXELOS.
Guidance for running an organization's portfolio of projects and programs as a whole, choosing which to start, balancing them against capacity and risk, and tracking whether together they deliver the strategy.
Four candidate projects for a water utility's next investment cycle
A portfolio can fund only so much. A project with no link to a stated objective is out, whatever it scores. The rest are ranked by weighted score, and the portfolio's cycle then asks whether the top choices form a balanced set. Change a score, a weight, or the link and watch the ranking move. Illustrative.
Supports a stated strategic objective
MustBilling replacementDepot appMeter rolloutIntranet refreshBenefit to customers
WeightBilling replacementDepot appMeter rolloutIntranet refreshContribution to the cost goal
WeightBilling replacementDepot appMeter rolloutIntranet refreshDelivery risk (10 is low risk)
WeightBilling replacementDepot appMeter rolloutIntranet refreshFits what the teams can deliver
WeightBilling replacementDepot appMeter rolloutIntranet refreshWeighted total
Billing replacement131OutDepot app154OutMeter rollout157OutIntranet refresh131OutComes out on topNo option passes every must: rescope or find another.Billing replacementDepot appMeter rolloutIntranet refresh
In order
- 157Billing replacementDepot appMeter rolloutIntranet refreshOut: fails a must (Supports a stated strategic objective).
- 154Billing replacementDepot appMeter rolloutIntranet refreshOut: fails a must (Supports a stated strategic objective).
- 131Billing replacementDepot appMeter rolloutIntranet refreshOut: fails a must (Supports a stated strategic objective).
- 131Billing replacementDepot appMeter rolloutIntranet refreshOut: fails a must (Supports a stated strategic objective).
An example
A regional water utility had forty-six projects under way, and nobody could list them on one page. Each had a sponsor, each was reasonable, and together they needed twice the engineers the utility employed. Deadlines slipped in every project at once, and the board learned about the clash only when two major schemes asked for the same crew in the same month.
The finance director proposed to treat the work as one portfolio. A small team listed every project, sorted them by the strategic objective each served, and scored them on customer benefit, contribution to the cost goal, delivery risk, and fit with available people. Eleven had no clear link to an objective and were stopped or folded into other work. Six more were deferred a year to leave room for the rest. The board then reviewed the portfolio quarterly, so a new proposal had to show what it would displace. In the first year the number of overdue projects fell by more than half.
The core idea
Management of Portfolios holds that a portfolio, the full set of an organization's projects and programs, is something to be managed in its own right, apart from the individual projects. It was published in 2011 as UK government guidance to recognize portfolio management as a discipline distinct from project and program management.
The approach has two cycles. The portfolio definition cycle decides the right, prioritized set of work and has five practices: understand the current work, categorize it, prioritize it, balance it, and plan it. The portfolio delivery cycle keeps that set on track against strategy through practices such as stakeholder engagement, organizational governance, resource management, risk management, financial management, benefits management, and management control. The insight is that projects can each be well run and the portfolio still fail, because the failure sits in the choices of what to start, what to stop, and how much the organization can carry at once. Balance means a mix of quick and slow, safe and risky, and sustaining and changing work.
The thinking behind it
British government best-practice guidance, later owned by AXELOS Management of Portfolios appeared in 2011 from TSO, the publisher of the UK government's best-practice guidance, in the same family as PRINCE2 for projects and Managing Successful Programmes for programs. That family later passed to AXELOS. A scholarly paper on the subject records that in 2011 the UK government judged portfolio management ready to stand as a discipline of its own, apart from project and program management, and the guide answers with one cycle for defining what belongs in the portfolio and another for delivering it. It names no single author. It is a standard written for public bodies and drawn from their experience, and its training runs through accredited courses.
Where it sits in the layers
Management of Portfolios sits in Layer 8, Methodologies and Operating Systems, as a prescribed method for one level of an organization's work. It takes for granted the commitments above it: that strategy can be translated into discrete pieces of change, and that choices among them improve results, an assumption of the improvement philosophies in Layer 6. In this same layer it governs the work that PRINCE2 and Managing Successful Programmes deliver, and below it, it uses tools such as a risk register and a prioritization matrix. The common mistake is asking it to supply the strategy. It sorts and balances proposals that serve objectives already chosen, and gives no way to choose the objectives.
How organizations put it to work
A portfolio office usually owns it, working for a board-level sponsor, often the finance or strategy director. It changes structure by creating that office and a portfolio board that meets on a fixed rhythm. It changes decisions: proposals compete against each other for capacity, and starting something now means deferring or stopping something else. It changes routines, with a standing inventory of all change work, a quarterly portfolio review, and regular benefit and risk reporting.
The measures are the share of projects linked to a stated objective, the load on scarce people, the benefits expected and realized, and how many projects were stopped on purpose.
Sustaining it takes a complete and honest inventory and a board willing to stop work that is still popular. In the first year, expect the first inventory to find more projects than anyone expected, resistance from sponsors whose work is deferred, and a period in which the office is accused of adding bureaucracy. The business gains steadier delivery, fewer clashes for the same people, and a board that sees the whole load, so results depend less on a few sponsors who shout loudest.
Where it goes wrong
Failure often starts with a portfolio in name only. The office lists projects and reports on them but has no power to start, stop, or defer anything. The sign is a portfolio that only grows.
It also comes from scoring theater. Weighted scores give an air of objectivity, but the weights and scores are set by the same people who sponsor the projects, so the ranking confirms what they wanted. The sign is a ranking that never surprises anyone.
And there is weight for small organizations. A company with a dozen projects does not need two cycles and seven practices, and the overhead can exceed the benefit. The guidance was written for the public sector, and its terms, such as program and tranche, sit awkwardly in many private firms. The sign is a portfolio meeting that repeats work the executive team already does.
Related and rival frameworks
- Managing Successful Programmes (MSP). Manages a single program of related projects that deliver one change. The better pick when the question is one large transformation.
- PRINCE2. Controls the delivery of one project. It sits below the portfolio and is the usual place the approved work is run.
- PMBOK Guide. A general body of project knowledge from a professional association. Choose it for project method; it says less about portfolios.
Go to the source
- Management of Portfolios, TSO (later AXELOS), 2011