Critical Path Method

Thinking Tools6.2 Creating an Action PlanAlso known as Critical Chain, CPM

Critical Path Method developed by James E. Kelley Jr. and Morgan R. Walker (Critical-Path Planning and Scheduling, 1959); Critical Chain by Eliyahu M. Goldratt (Critical Chain, 1997).

Finds the longest run of dependent tasks, which sets a project's earliest possible finish, and in the Critical Chain version swaps padded task estimates for shared buffers.

When to reach for it

Planning or rescuing a project with dependent tasks and shared people, when the question is which tasks actually decide the finish date.

How it runs

  1. List the tasks and which must finish before each can start.
  2. Estimate each task's duration; use median estimates for Critical Chain.
  3. Trace the longest dependent chain: the critical path.
  4. Add resource conflicts and move padding into shared project and feeder buffers.
  5. Track buffer use, and act when it runs ahead of progress.

Where it sits in SOLVE eX

Go to the source

  • Critical-Path Planning and Scheduling, Eastern Joint Computer Conference, 1959
  • Critical Chain, North River Press, 1997