Critical Chain Project Management

Layers of Management ThoughtLayer 8: Methodologies and Operating SystemsMethodologyAlso known as CCPM, Critical chain scheduling

Developed by Eliyahu Goldratt in his book Critical Chain (1997), which applies his theory of constraints to project management.

A project management method built on the theory of constraints that plans around resource limits, removes the padding from each task's estimate, and pools that safety into buffers whose consumption signals when to act.

A five-task software release planned with trimmed estimates and one project buffer, and how the buffer is used up

Each of five tasks was estimated at 10 days with padding. The plan keeps 6 days per task, so the chain runs 30 days, and holds 10 days of the removed safety in one buffer at the end, for a promised finish on day 40. Set the delay the tasks have absorbed so far and read how much of the buffer is gone and what the team should do. Illustrative.

6
Projected finish day
36
Share of the buffer used
60%
Days late against the promise
0
What the team does
Nothing: delays are inside the bufferPrepare a recovery plan and watch the next tasks closelyThe buffer is gone: tell the customer the date will move

Projected finish dayPromised day 40Padded plan, day 50

30405002468101214163040500246810121416

At this delay0: No delay: the work finishes on day 30 and the 10-day buffer is untouched.2: Two days of delay. The buffer absorbs it, and no one outside the project needs to know.4: Four days of delay, 40 percent of the buffer used. Still no action needed.6: Six days of delay. More than half the buffer is gone, so it is time to prepare a recovery plan.8: Eight days of delay. The buffer is nearly gone and every remaining task is now critical.10: Ten days of delay. The buffer is exactly used up and the finish is day 40.12: Twelve days of delay. The promised date is missed by two days.14: Fourteen days of delay. The promised date is missed by four days.16: Sixteen days of delay. The promised date is missed by six days, though the padded plan's day 50 would still hold.

An example

A software company's release projects always ran late, and each plan looked sensible. Every task carried a generous estimate, and every manager knew the schedule had padding. Developers who finished a week early held the work back to polish it, those with time to spare started late, and the same people were shuffled across three projects at once. The release date was a hope.

A new project office rebuilt one release plan. It cut each task estimate to the time it would take if things went reasonably well and collected the removed safety into one buffer at the end. The plan also noted that two tasks needed the same senior engineer and sequenced them so that they no longer overlapped. Developers were told to work one task at a time and hand it on at once when done. The release date moved up and stayed there. Instead of asking whether each task was on time, the project office watched how much of the buffer had been used, and acted only when the buffer ran low.

The core idea

Critical chain project management plans a project around the resources that limit it as well as the order of its tasks. The critical chain is the longest sequence of tasks once resource conflicts are resolved, which equals the critical path only when resources are unlimited. The plan is built backward from the completion date.

The method makes three moves. It cuts task estimates to aggressive durations, since each estimate carries safety that tends to be used up. It pools the removed safety into buffers: a project buffer at the end, feeding buffers where side chains join the critical chain, and resource buffers that warn of unavailable people. It also asks workers to avoid multitasking and to hand each task on as soon as it is done, like a relay race.

Execution is managed by buffer. The question is how much of the buffer has been consumed, and the response grows with the answer. The insight is that safety is worth more when shared across a project than when held privately by each task.

The thinking behind it

Eliyahu M. Goldratt Eliyahu Goldratt introduced the method in his 1997 book Critical Chain, applying his theory of constraints to project management. The book argues that projects run late because of how safety is held, inside each task, where it tends to be used up. The North River Press page describes its purpose as teaching companies to finish projects on time, within budget, and without compromise. His method gave project managers a way to plan around the scarcest resource and to protect the date with a visible buffer.

Where it sits in the layers

Critical chain lives in Layer 8, Methodologies and Operating Systems, as a prescribed way to plan and run projects. It takes for granted the theory behind it, the Theory of Constraints from Layer 6, which says that every system has a constraint that governs its output and that improvement starts there. It is put to work through buffer reports and a weekly review in Layer 10, and it replaces the task-by-task schedule tracking of the critical path method with buffer consumption. The common mistake is to treat it as a scheduling trick. The method asks people to change behavior, working on one thing at a time and ignoring task-level due dates, and without that change the buffers do not work.

How organizations put it to work

A project office or a portfolio leader usually owns it, with project managers trained in buffer management. It changes structure little, but it changes who owns the date: the project manager defends the buffer, and task owners are asked for an honest estimate without padding. It changes decisions: people are assigned one task at a time, new projects start only when a constrained resource is free, and reporting centers on buffer consumption. It changes routines, with a short daily or weekly check of the chain and the buffers.

The measures are buffer use against progress, the finish dates actually achieved, and the amount of multitasking. Sustaining it takes managers who stop asking every team whether its task is on time, because such questions bring the old padding back. In the first year, expect resistance to aggressive estimates, a few early projects that overrun when buffers are set too small, and a gradual improvement in promised dates. A business that plans this way delivers more reliably with the same people and depends less on heroics at the end of a project.

Where it goes wrong

Failure often starts with estimates cut without the behavior change. Managers trim the padding, keep the task due dates, and multitask as before, so the project is shorter on paper and later in practice. The sign is a buffer consumed within the first weeks.

It also comes from buffers sized by a rule of thumb. The common rule cuts estimates in half and sets the buffer at half the removed time, and when Herroelen and Leus tested it on benchmark problems in 2001, they found it could greatly overstate the protection needed. The sign is buffers that are either never touched or always empty.

And there is a larger criticism. Raz, Barnes, and Dvir concluded in 2003 that the method holds useful ideas but is not a full answer to managing projects, and they warned against discarding conventional techniques along with the old schedule. The sign is a plan that ignores a dependency a standard schedule would have caught.

Related and rival frameworks

  • Critical Path Method. Schedules by task order alone, with no pooled buffers. The better pick when resources are plentiful and the tasks are well understood.
  • PERT. Builds expected durations from three-point estimates. Choose it when the uncertainty in each task is the main issue and resource limits are not.
  • Drum-Buffer-Rope. The factory version of the same logic, with a buffer ahead of the bottleneck. Choose it for production work.