Created in 1994 by project practitioners across many companies who formed the DSDM Consortium, now the Agile Business Consortium, to build quality into rapid application development.
Governs an agile project with a fixed time, cost, and quality and a variable scope, using MoSCoW priorities and timeboxes so that a viable solution arrives on time even when the work turns out larger than planned.
A fixed-date project when the work runs over: what a MoSCoW plan drops, and what it protects
A mortgage lender must go live on a fixed date and budget, so the timebox holds 100 units of effort. Set the Must and Could shares and the overrun: work is done in priority order, and the bars show what each tier gets against what it now needs. Illustrative.
Effort delivered in the timeboxEffort the tier needs after the overrun
An example
A mortgage lender needed a new application system before a rule change took effect in September. The sponsor refused to move the date. The project manager and the business ambassador sorted the requirements with MoSCoW. Identity checks and affordability calculations were Must Haves: without them the system could not be used. Document upload and a status tracker were Should Haves. A progress bar and saved drafts were Could Haves.
The Musts took about sixty percent of the planned effort, and the Coulds about twenty. In the third timebox the affordability rules proved harder than estimated, and the team dropped the progress bar and deferred the draft feature, with the business ambassador's agreement and no meeting. The system went live on the date with every Must and most of the Shoulds. The deferred items were recorded as Won't Haves for this release, so nobody could slip them back in, and went into the next one.
The core idea
DSDM starts from the four things every project trades against each other: time, cost, features, and quality. Fixing all four at the outset assumes the need will not change, everything is known in advance, and nothing will go wrong, and those assumptions rarely survive a project. So DSDM fixes three of them, the date, the budget, and the quality standard, once the early Foundations work is done, and lets the features flex.
MoSCoW governs the flex. Every requirement is a Must Have, Should Have, Could Have, or Won't Have this time, and the Musts form the minimum usable system the project guarantees. Because the Musts are held to about sixty percent of the effort, an overrun eats the Coulds and then the Shoulds, never the date. Work runs in timeboxes of a few weeks within a project of six phases, from Pre-Project to Post-Project, and eight principles, from focusing on the business need to never compromising quality, hold the method together.
The thinking behind it
A framework created in 1994 by project practitioners from many companies, who formed the DSDM Consortium as a not-for-profit DSDM has no single author. It began in 1994, when practitioners from many companies pooled what they knew about rapid application development, the fast, prototype-led way of building business systems then spreading, because they wanted it to deliver quality as well as speed. Their companies set up the DSDM Consortium as a not-for-profit to own and develop the method, and in 2007 the consortium made it free to view and use. The current DSDM Agile Project Framework, first printed in 2014, grew out of the earlier DSDM Atern, and the consortium now calls itself the Agile Business Consortium. The center has not moved: a fixed date at a fixed quality, with the features as the part that flexes.
Where it sits in the layers
DSDM sits in Layer 8, Methodologies and Operating Systems, because it is a full operating method for a project, with defined phases, roles, products, and practices. It takes for granted the values of the Agile Manifesto in Layer 6, adding the governance a corporate sponsor expects. Beneath it, the routine of ranking requirements is carried by MoSCoW Prioritization in Layer 9, a technique that DSDM treats as part of the method. The common mistake is to use the method's vocabulary without its trade. Teams label requirements Must Have and still promise every feature, so the contingency that MoSCoW creates is never used.
How organizations put it to work
An organization adopts DSDM for projects where the business sponsor wants agile delivery with the controls of a corporate project. A project manager runs the process, with business roles that matter as much: a sponsor, a visionary, and ambassadors in the team who have the authority to make day-to-day business decisions without referring up. The structural change is that business people sit inside the team.
Decisions change in two ways. A project sets time, cost, and quality at the end of Foundations, and thereafter the only variable is scope, decided by MoSCoW. Business ambassadors decide small matters on the spot. Routines run in fixed increments and timeboxes, and priorities are reviewed at the end of each one. After the last deployment a Post-Project phase assesses whether the expected benefits arrived.
Sustaining it takes a sponsor who accepts that scope will flex, and a rule that Must Haves take no more than about sixty percent of effort, so that room for contingency remains. In the first year a leader should expect some difficulty getting business people to commit to the team, and early arguments about what is truly a Must. The return is more predictable delivery, with fewer last-minute surprises.
Where it goes wrong
The first failure is Must Have inflation. Every requirement becomes a Must, no contingency remains, and the project is back to a fixed scope with a fixed date. The sign is a Must Have list above sixty percent of effort, which the framework treats as adding risk unless estimates are accurate.
The second is an absent ambassador. The framework depends on someone from the business who can decide without waiting for a committee. When decisions wait for the next scheduled approval meeting, the deadline suffers.
The third is foundations skipped or overdone. DSDM wants enough early analysis and design to make the project's foundations firm, but not so much that the project stalls on detail. The sign is a project that either starts building with no agreed scope or spends months in analysis.
A wider criticism is weight. Its roles, products, and phases suit corporate projects, and a small team may find it heavy.
Related and rival frameworks
- PRINCE2. A project management method that controls work by stages and tolerances. The better pick when scope is well understood and the main need is control. DSDM suits work where scope must flex.
- Scrum. A lighter frame for a single product team, with no phases or governance roles. The better pick when the team owns the whole product and the sponsor needs no formal project controls.
- Stage-Gate Process. Moves a project through gates where funders decide whether to continue. Use it to govern a portfolio of ventures, where DSDM governs how one project delivers.
Go to the source
- The DSDM Agile Project Framework Handbook, Agile Business Consortium (the framework was first printed in 2014 as an evolution of DSDM Atern), 2014