Developed by Corey Ladas in his 2008 paper Scrum-ban and gathered in his book Scrumban: Essays on Kanban Systems for Lean Software Development (2008).
A hybrid of Scrum and Kanban that keeps Scrum's roles and cadence, replaces the sprint commitment with limits on work in progress, and plans new work when the board runs low.
How many items a four-person team should hold in progress at once
A four-person maintenance team can finish at most six items a week, and each person can work one item at a time. It opens with twelve items in progress, as the team ran before. Set the limit and read how long an item takes and how many sit waiting: the time stays flat up to four and climbs after. Illustrative.
Days in progress
At this limit1: One person works while three wait for the next item, so the team finishes far less than it could.2: The team is starved: not every person has an item, and weekly output is below what four people can do.3: The team is starved: not every person has an item, and weekly output is below what four people can do.4: Every person has an item and output is at its ceiling of six a week. This is the smallest limit that keeps the team busy.5: More items are open than people can work on, so the extra ones age on the board and each item takes longer.6: More items are open than people can work on, so the extra ones age on the board and each item takes longer.7: More items are open than people can work on, so the extra ones age on the board and each item takes longer.8: More items are open than people can work on, so the extra ones age on the board and each item takes longer.9: More items are open than people can work on, so the extra ones age on the board and each item takes longer.10: More items are open than people can work on, so the extra ones age on the board and each item takes longer.11: More items are open than people can work on, so the extra ones age on the board and each item takes longer.12: More items are open than people can work on, so the extra ones age on the board and each item takes longer.
An example
A utilities billing software team of four was supposed to run two-week sprints, and every sprint was broken by urgent fixes from the production floor. Planning meetings promised sixteen stories and delivered nine. Half of every retrospective was spent explaining why. The product owner stopped trusting the sprint forecast, and the support manager stopped trusting the team.
The team kept its roles, its daily meeting, and its retrospective. It replaced the sprint backlog with a board that had columns for each state of work and a limit of four items in progress, one for each person. Planning happened when the ready column fell to two items, and urgent fixes took a reserved slot and no longer broke a commitment. After two months the average time an item spent in progress had dropped from ten days to about three, the support manager could see where each fix stood on the board, and sprint forecasts were no longer the subject of meetings.
The core idea
Scrumban starts from Scrum and adds the controls of Kanban. The work lives on a board of states, and each state has a limit on how many items it may hold. A card moves on only when it meets the state's completion criteria and the next state has room. Queues between active states show where work is waiting, which is where the bottleneck is.
The parts of Scrum are kept or dropped by need. A team may keep roles and the retrospective while giving up fixed-length iterations, estimating every story, and the burndown chart. Planning becomes a response to the board: when the ready column runs low, the product owner refills it. The insight is that limiting work in progress does the job a sprint commitment was meant to do. It keeps the team from taking on more than it can finish, and it does so continuously, so urgent work can be absorbed without a broken plan.
The thinking behind it
Corey Ladas Corey Ladas introduced Scrumban in 2008 in a paper titled Scrum-ban, which described how a Scrum team might introduce kanban and, taken far enough, replace most of Scrum. The paper treated estimation as waste to be reduced and gave the product owner a limited number of kanban cards to spend on priorities. He then collected the ideas in a book, Scrumban: Essays on Kanban Systems for Lean Software Development, published in November 2008 according to its publisher's listing. The essays cover metrics and daily management for continuous improvement.
Where it sits in the layers
Scrumban sits in Layer 8, Methodologies and Operating Systems, as a method assembled from two others. It takes for granted the commitments of the layers above: the lean idea that flow and limited work in progress improve results, the philosophy behind Lean Thinking, and the agile belief in small, frequent delivery. It is put to work through the daily meeting and the retrospective in Layer 10, and through the board and its measures, such as cycle time, in Layer 9. The common mistake is treating it as a license to drop discipline. A team that borrows from both methods and keeps the limits of neither ends up with a board that only displays work.
How organizations put it to work
The team's own leads usually own the board, with the product owner responsible for what enters it and a manager responsible for the limits. The change in structure is small, since roles stay. The change in decisions is large: the limit on work in progress becomes the rule, and new work enters only when there is room. Priority calls move from sprint planning to the moment a slot opens.
The routines shorten. The team keeps its daily meeting, now organized around the board, and the retrospective turns to measures such as how long items take and where they wait. Each change in the limits is a small experiment with a stated expectation.
Sustaining it takes discipline at the edges: someone must refuse to start new work when the column is full, and leaders must accept visible queues. In the first year, expect the first weeks to feel slower as the board exposes work nobody was finishing, followed by steadier delivery and more honest forecasts. The business becomes less dependent on heroics, since an urgent request is taken into the flow with its cost visible.
Where it goes wrong
Failure often starts with limits that nobody enforces. The board shows columns, and everyone starts new work whenever a person is free. The sign is a work-in-progress count that sits above the limit for weeks.
It also comes from dropping the useful parts of Scrum together with the useless ones. Teams that abandon the retrospective and the product owner lose the habit of improving and the voice of priority. The sign is a board that fills with items no one chose.
And there is the criticism from both sides. Scrum purists say a hybrid removes the time box that creates focus and commitment. Kanban purists say a team that keeps Scrum's ceremonies is carrying weight it does not need. Both have a point, and the answer depends on the work: it suits mixed maintenance and feature teams and is poor value for a team whose work arrives in planned bursts.
Related and rival frameworks
- Scrum. The method Scrumban starts from. The better pick when work can be planned in fixed intervals and the team benefits from a commitment.
- Kanban Method. The full approach, with its own principles for evolving the process. See Kanban when the team has no sprints to keep.
- Cumulative Flow Diagram. A chart of the work in each state over time. The better pick once a board is in place and the question is where queues are building.