Daily Management System

Layers of Management ThoughtLayer 10: Practices and RitualsPracticeAlso known as Lean daily management, Lean management system, DMS

From the daily management of Toyota's production system, set out for other companies by David Mann in Creating a Lean Culture (2005) as a lean management system of four elements: leader standard work, visual controls, a daily accountability process, and leadership discipline.

The daily routine of standard work for leaders, visual boards, short tiered meetings, and disciplined follow-up through which an operation finds and fixes problems every day and keeps its improvements from fading.

Scoring the cabinet plant's daily management against Mann's four elements

Eight checks, two for each element, scored from 0 (absent) to 3 (every day, without fail). The scores open on the plant two years after its lean tools went in. Raise the checks the plant manager changed and watch the verdict move. Illustrative.

Leader standard work: team leaders check their cell's board every hour, by a written routine

Score1

Leader standard work: supervisors and managers have written routines of their own

Score0

Visual controls: every cell shows planned against actual, hour by hour

Score1

Visual controls: each miss is written up with its cause as it happens

Score1

Daily accountability: each tier meets at its board daily, at a fixed time, in fifteen minutes or less

Score1

Daily accountability: what a tier cannot fix goes up the same day, with an owner and a date

Score0

Leadership discipline: open actions are checked at each meeting until closed

Score0

Leadership discipline: senior leaders keep the routine in busy weeks

Score1

Average score0.6

VerdictScore every row to see the verdict.Boards on the wallThe tools are up, nobody's day depends on them, and the gains will fade.Partly workingSome loops close. Fix the element that breaks most often first.A daily systemProblems surface within the hour and reach someone who can fix them within the day.

An example

A maker of kitchen cabinets had installed lean tools two years earlier: cells, kanban, and labeled workplaces. Most of the gains had faded. Boards showed last month's numbers, and problems surfaced at the weekly operations meeting, days late.

The plant manager built a daily management system around the tools. Each cell got an hour-by-hour board, planned against actual, with a line for the cause of any miss. Team leaders checked their boards every hour, supervisors walked them twice a shift, and the plant manager walked the floor each morning, each following written standard work. Cells met at 7:00 for ten minutes at the board, supervisors at 7:30, and the plant's managers at 8:00, and anything a tier could not fix went up with an owner and a date.

In the second week three cells logged the same miss, hinge holes drilled out of position. It reached the 8:00 meeting that morning, and maintenance replaced a worn fixture by afternoon. Within four months on-time completion rose from 84 to 95 percent, and the earlier lean gains held.

The core idea

A daily management system is the set of routines by which leaders run an operation day by day once lean tools are in place. David Mann named four elements. Leader standard work sets what each level of leader checks and when: team leaders several times an hour, supervisors and managers at set intervals in each shift. Visual controls show, at the point of work, expected against actual, so a miss is visible at a glance. A daily accountability process brings each level together for a short, fixed meeting at its boards, escalates what it cannot solve, and assigns actions with owners and dates. Leadership discipline holds the routines in place, with leaders keeping their own standard work and checking that others keep theirs.

The logic is a daily closed loop. Problems and drift appear every day, so a weekly or monthly review finds them late. The insight is that lean tools change how the work is done, and only a change in how managers spend each day keeps those changes alive.

The thinking behind it

David Mann David Mann applied lean at Steelcase for fifteen years and built the management system behind more than forty of its value stream conversions. Creating a Lean Culture (2005), which won a Shingo Prize in 2006, argued that lean conversions last only when managers change their own daily work. Its remedy was a management system of four principal elements, leader standard work, visual controls, a daily accountability process, and leadership discipline, with each level of leader checking on a schedule that the level below keeps its routine. Leaders, Mann wrote, must learn to impose on themselves "the same kind of disciplined adherence to process" they expect of operators.

Where it sits in the layers

The daily management system is a Layer 10 practice, the hour-by-hour and day-by-day routine of running an operation. It puts to work the Toyota Production System and Just-in-Time from Layer 6, and the Layer 8 method of Hoshin Kanri, whose yearly priorities it tracks on the boards. Its parts are practices beside it in this layer: the gemba walk, the tiered huddles, and the response to an andon cord. The common wrong-layer mistake is treating the system as a set of boards and meetings to install, a Layer 9 toolkit. Boards without leader standard work and discipline go stale within weeks.

How organizations put it to work

Operations leadership owns the system, usually the plant or site manager, with a lean or operational excellence group to design the boards and coach leaders. It changes structure first: each level needs leaders with time to check and respond, which often means more team leaders than before. It changes routines: written standard work for every leader, fixed meeting times for each tier, and a clear path for escalating a problem with an owner and a date. It changes measures: hour-by-hour output against plan, misses and their causes, and the age of open actions become the numbers leaders look at first.

Sustaining it is the hard part. Leaders at the top have to walk the floor and check the standard work of the leaders below them, or the routine decays from the top down.

In the first year, expect the first boards to be too complicated, meetings to run long, and the early weeks to surface far more problems than anyone expected. After several months, problems should reach the person who can fix them within a day, improvements should hold, and the operation should run less on a few experienced managers who used to carry it in their heads.

Where it goes wrong

The first failure is wallpaper. Boards go up, numbers get filled in at the end of the shift, and nobody looks at them during the day. Spot it in boards completed in one handwriting, after the fact, and meetings that read numbers without asking about causes.

The second is escalation without closure. Problems go up the tiers and stay open, owned by nobody who can fix them. Spot it in open actions more than two weeks old and the same problem raised every morning.

The third is decay from the top. Senior leaders stop walking the floor or skip their own meetings during a busy month, and within weeks the levels below follow. Spot it when the plant manager's own standard work is the first missed. The system also costs leaders' time every day, and it lasts where that time is planned into their jobs.

Related and rival frameworks

  • Tiered Huddles. The meeting element of the system: short, stacked huddles from the front line to the plant manager. A daily management system without them has no way to escalate.
  • Gemba Walk. A leader goes to see the work. In a daily management system it becomes leader standard work, scheduled and checked.
  • Weekly Business Review. A weekly review of metrics for an organization run on data more than on shop-floor boards. Better for a large company where the operating signals live in systems.