From Watts Humphrey's Characterizing the Software Process: A Maturity Framework (1988), developed at the Software Engineering Institute into the Capability Maturity Model for Software, version 1.1, by Mark Paulk, Bill Curtis, Mary Beth Chrissis, and Charles Weber (1993).
Rates a software organization on five maturity levels, from dependence on competent people to continuous process improvement, so that each level names the practices that make results repeatable and the next level's work clear.
Eight key process areas of the Software CMM, placed on the level where the model puts them
Each level beyond the first adds a focus: project management, then engineering and organizational support, then quality measured by numbers, then continuous improvement. Select an area, then the level it belongs to. The level lights and says what that focus asks of a team. Show the sort to compare yours. The areas are the model's own, and the examples are invented. Illustrative.
- Not placedPlacedProject controlShared standardsQuality by numbersImproving
- Not placedPlacedProject controlShared standardsQuality by numbersImproving
- Not placedPlacedProject controlShared standardsQuality by numbersImproving
- Not placedPlacedProject controlShared standardsQuality by numbersImproving
- Not placedPlacedProject controlShared standardsQuality by numbersImproving
- Not placedPlacedProject controlShared standardsQuality by numbersImproving
- Not placedPlacedProject controlShared standardsQuality by numbersImproving
- Not placedPlacedProject controlShared standardsQuality by numbersImproving
Maturity level
Key process areas
Your sort matched 0 of 8.Your sort matched 1 of 8.Your sort matched 2 of 8.Your sort matched 3 of 8.Your sort matched 4 of 8.Your sort matched 5 of 8.Your sort matched 6 of 8.Your sort matched 7 of 8.Your sort matched 8 of 8.
- Project control
- The focus is on making each project's success repeatable: plan it, track it, control its requirements and changes.
- Shared standards
- The focus is on one standard process for the whole organization, with training, reviews, and coordination across groups.
- Quality by numbers
- The focus is on measuring the process and the product quantitatively, so that quality is managed against numbers.
- Improving
- The focus is on improving the process continuously, preventing defects, and managing technology change.
The sort
- Requirements Management: Project control. A project-level control that every repeatable project needs first. Without it, a plan has nothing stable to estimate against.
- Software Project Planning: Project control. Planning is a project management practice and so belongs at the second level.
- Peer Review: Shared standards. A practice built on a standard organizational process, which is the third level's focus.
- Training Program: Shared standards. Organizational support for a defined process, a third-level area.
- Integrated Software Mgmt: Shared standards. Tailoring a defined standard belongs to the third level.
- Quantitative Process Mgmt: Quality by numbers. Managing performance by numbers is the fourth level's focus.
- Defect Prevention: Improving. Preventing defects from their causes is continuous improvement, the fifth level.
- Technology Change Mgmt: Improving. Managing the introduction of new technology is a fifth-level area.
An example
A software house of two hundred people won contracts on the strength of its best engineers and lost money on most of them. Schedules were guesses, requirements changed in the hallway, and the last three projects had each finished late in a different way. A prospective government customer asked for a process maturity assessment. The company's own leaders expected a middling result.
The assessors rated the company at the first level: results depended on competent people and heroics. They explained that the next level asked for project management that anyone could repeat: managed requirements, a written plan, tracking against the plan, and control of changes to the code. The company spent a year on those four practices and nothing else. Estimates still missed, but by a smaller and more consistent amount, and managers could now see a late project in the second month instead of the ninth. The best engineers, freed from rescuing projects, started two new products.
The core idea
The model holds that a software organization matures in a fixed order, and it names five levels. At the first, success rests on capable people and heroics. The second makes a project's success repeatable through project management: managed requirements, a written plan, tracking against it, and control of changes. The third gives the whole organization one standard process, with training and peer reviews behind it. The fourth manages product and process quality by measurement, and the fifth improves the process continuously, preventing defects at their causes.
Every level above the first is built from key process areas, each with goals that assessors rate as met or not, and the levels are cumulative. The insight is that the quality of the process largely decides the quality of the product, and that the habits have to be built in order: measuring a process that projects do not yet plan and track produces numbers nobody can use.
The thinking behind it
Watts S. Humphrey Watts Humphrey came to the Software Engineering Institute at Carnegie Mellon in 1986 after a career at IBM, as the institute began building a process maturity framework, partly in answer to a federal request for a way to assess software contractors. In 1987 the institute released a maturity questionnaire, which was too often taken for the model itself, and in March 1988 Humphrey set out the framework's five levels for a wide readership in Characterizing the Software Process: A Maturity Framework, in IEEE Software.
Mark C. Paulk Mark Paulk was the lead author of the report that turned the framework into a fully defined model. After four years of experience with the framework and questionnaire, the institute published the Capability Maturity Model for Software, version 1.1, in February 1993, by Paulk, Bill Curtis, Mary Beth Chrissis, and Charles Weber. The report specifies the key process areas at each level. It gave process improvement programs better guidance than the questionnaire, and an article summarizing it appeared in IEEE Software the same year.
Where it sits in the layers
The model sits in Layer 7, Assessment and Maturity Models, because assessors rate an organization against a staged standard and the level they award names what to build next. It takes for granted a belief from the quality philosophy of Layer 6, in Total Quality Management, that a better process produces a better product. It supports project practice in Layer 8 such as the PMBOK, whose planning and control routines match its second level, and it is put into daily use through Layer 10 habits such as Code Review, the descendant of its peer review practice. The common mistake is asking it to pick a development method. It says which management practices should exist at each level. It does not say whether to build software in sprints or in phases.
How organizations put it to work
A software engineering process group usually owns it, backed by a senior sponsor who funds the improvement and reads the assessment. Adoption begins with an assessment against the key process areas, then a plan to reach the next level only. It changes structure by creating the process group and giving each project a planner, and it changes decisions by making plan, size estimate, and requirement baseline the basis of commitments to customers. Measures begin with schedule and cost variance against plans, and grow into defect and process data at the higher levels.
Sustaining it takes steady funding through the dull middle years, since moving up a level took many organizations a year or two, and a sponsor who will not trade the process away in a deadline crisis. In the first year, a leader should expect more planning and more visible status reporting than engineers like, and the first gains to come in predictability. The return is projects that finish when promised, a business less dependent on a few heroes, and a record of capability that customers with contract risk can examine.
Where it goes wrong
The first failure is the level as the goal. Teams game the assessment, produce paper for every key process area, and stop when the rating arrives. The sign is a process manual that engineers do not follow and a rating that has outlived the practices.
The second is burden on small and fast teams. The model was designed around large defense-style projects, and its documents and reviews can overwhelm a team of ten. The sign is process work that exceeds the work it protects.
The third is weak evidence that the levels, not other factors, produce the gains. An SEI study of 676 assessments found the key process areas at level 2 so closely related to each other that they may not be separate things, which raises the question of whether assessors measure distinct capabilities. The sign is a company at a high level whose projects are no more predictable. The model is also largely superseded by CMMI.
Related and rival frameworks
- CMMI. The successor that replaced it and its siblings with one integrated model. It is the better pick today, since the Software CMM is no longer maintained.
- People Capability Maturity Model. The same staged logic applied to workforce practices. Use it when the limit on software maturity is hiring, training, and career structure.
- Test Maturity Model integration (TMMi). A five-level model for testing alone. Pick it when testing is the weak link and the broader model would be too much.
Go to the source
- Characterizing the Software Process: A Maturity Framework, IEEE Software 5(2), 73 to 79, 1988
- Capability Maturity Model for Software, Version 1.1, Software Engineering Institute, CMU/SEI-93-TR-024, 1993
- The Internal Consistency of Key Process Areas in the Capability Maturity Model for Software, Software Engineering Institute, CMU/SEI-2002-TR-037, 2002