Layers of Management ThoughtLayer 9: Tools and TechniquesToolAlso known as DICE, Duration, Integrity, Commitment, Effort, The hard side of change management

Set out by Harold Sirkin, Perry Keenan, and Alan Jackson of the Boston Consulting Group in their article The Hard Side of Change Management (Harvard Business Review, October 2005), from the firm's change work.

Scores a change program's risk before launch from four hard factors, duration, team integrity, commitment of leaders and staff, and extra effort, and sorts it into win, worry, or woe.

A warehouse system rollout scored on four hard factors, with senior commitment and team integrity counted double

Rate each factor from the most favorable to the least. The score is D + 2I + 2C1 + C2 + E, from 7 to 28: up to 14 is win, 15 to 17 is worry, and over 17 is woe. The bars show what each factor adds. Try improving the sponsor's commitment, which counts double. Illustrative.

2 to 4 months
Capable
Supportive
Willing
Heavy
DICE score
15
Zone
Win: likely to succeedWorry: riskyWoe: likely to fail

Points added to the score

0246824423DurationIntegrity x2Senior x2StaffEffort0246824423DurationIntegrityx2Senior x2StaffEffort

An example

A logistics company planned to roll out a new warehouse management system to nine distribution centers over eighteen months. The steering group's confidence was high. The vendor was credible, the budget was approved, and the sponsor spoke warmly about the plan at every meeting.

The program director ran the plan through a scoring exercise before the contract was signed. Reviews were scheduled every three months, which scored low risk. The project team had delivered one similar rollout, a middle score. Senior leaders were supportive and not visible: they approved the plan and would not attend site reviews. Staff at the sites were willing but already stretched, and the extra work would fall on the same supervisors who ran the sites. The total landed in the worry zone, driven by the weak commitment above and below.

The sponsor agreed to attend each site review, the rollout was cut to a pilot at three centers first, and temporary staff were hired to cover the supervisors' added load. The re-scored plan came out in the win zone.

The core idea

DICE gives a change program a risk score from four factors, each rated from 1, very favorable, to 4, highly unlikely to contribute to success. Duration is the time to completion, or on a long program the gap between formal reviews. Integrity is the capability and the reliability of the project team. Commitment has two parts: C1, the commitment of senior management, and C2, that of the employees the change affects. Effort is the extra work the change asks of staff beyond their usual duties.

The score is D plus two times I, plus two times C1, plus C2, plus E, so the team's integrity and senior commitment count double. Scores run from 7 to 28. A score of 14 or less is the win zone, where the program is likely to succeed, 15 to 17 is the worry zone, and above 17 is the woe zone. The factors can be assessed before launch, from facts such as the review schedule and the sponsor's calendar, and they can be changed. The score says which one to fix.

The thinking behind it

Harold L. Sirkin Harold Sirkin, Perry Keenan, and Alan Jackson, all of the Boston Consulting Group, published The Hard Side of Change Management in the Harvard Business Review in October 2005. Their argument was that discussions of change dwell on soft factors such as culture and motivation, and that four hard factors do more to predict how a program turns out: duration, integrity, commitment, and effort. They proposed a scoring method that managers could apply to a program before launch, with extra weight on the factors they judged to matter most. The problem they set out to solve was the large number of change programs that fail, and the lack of any way to see the risk in advance.

Where it sits in the layers

DICE sits in Layer 9, Tools and Techniques, because it is an instrument for one piece of analysis: scoring a change program's risk from four hard factors before it is funded. It takes for granted the premise of decision theory in Layer 1, that a choice can be weighed in advance from its known factors, and it serves the methodologies of Layer 8, such as PRINCE2, whose stage reviews and sponsor role it scores. Beside it in this layer sits the pre-mortem, which asks what could make a plan fail, and its score is reviewed in routines such as the monthly business review in Layer 10. The common mistake is asking it to explain why people resist. It scores the program's hard factors and offers little on the soft ones, such as trust, culture, and fear.

How organizations put it to work

Companies use DICE as a risk check at the start of a program and at intervals, usually owned by the program office or the transformation lead, with the sponsor accountable for the commitment scores. It changes decisions: a program that scores in the woe zone is redesigned or deferred before it is funded in full. It changes structure little, but it changes the plan: reviews are scheduled at intervals of two months or less, a weak team is strengthened, and the sponsor's role is written into their calendar. It changes routines, with a short re-score at each review. And it changes measures: the score is tracked alongside cost and schedule.

Sustaining it takes honest scoring. A team that scores its own program tends to rate it kindly, so a neutral reviewer or the program office does the rating.

In the first year a leader should expect the first scoring to be uncomfortable, mostly on the sponsor's commitment and the load on staff. The return is a risk that is named before it hurts, a program that gets the commitment it needs, and less reliance on one confident sponsor's judgment of the odds.

Where it goes wrong

The first failure is false precision. Factors are rated from 1 to 4, with fractions allowed, and the weighted total looks exact, though each rating is a judgment. Sources even give slightly different boundaries between the zones. The sign is a debate about whether a program is a 14 or a 15.

The second is gaming. Teams rate the factors to reach the zone they want, and a sponsor who is asked to rate their own commitment will rate it high. The sign is a score that moves toward win whenever the program is questioned.

The third is ignoring the soft side. The framework deals with hard factors by design, and a program can score well and still fail for lack of trust or a belief in the change. The sign is a win-zone program that stalls at the front line.

Related and rival frameworks

  • Kotter's 8-Step Change Model. Gives a sequence for leading a change, where DICE gives a risk score. Use Kotter to plan and DICE to check the odds.
  • Prosci Change Management. Adds a process, a sponsor role, and an assessment that covers the people side. A fuller approach where DICE is a short check.
  • Change Management Iceberg. Draws attention to the perceptions and politics below the waterline. The complement to DICE, which looks at the hard factors above it.

Go to the source