Layers of Management ThoughtLayer 9: Tools and TechniquesToolAlso known as Motion study, Micromotion study, Therbligs

Developed by Frank and Lillian Gilbreth, from Frank's Motion Study (1911) and their joint collection Applied Motion Study (1917), with Lillian bringing the human side of the work.

Studies each job as a chain of elementary motions, recorded frame by frame, and removes the motions that add nothing, so the same work takes less time and effort.

Sixteen motions to fit one connector: which fixes remove the wasted ones?

The line counts the motions in each part of fitting one connector now, and the bars show what the work actually needs. Bins moved within reach is set; turn the other two fixes on and off and watch the count, the time per connector, and the shift's output change. Illustrative.

Yes
No
No
Elemental motions per connector
11
Seconds per connector
13.2
Connectors fitted per eight-hour shift
2,182

Motions the work needsMotions in the job now

024110121ReachGraspTurn the partCarryPlaceReturn024110121ReachGraspTurnthepartCarryPlaceReturn

An example

An electronics plant assembled control panels at a long bench and was missing its output targets. The plant engineer set a camera above one bench, with a clock in the frame, and watched a skilled assembler's shift in slow motion. The assembler's hands were never idle, which was the problem. Parts sat in bins at arm's length. Each connector had to be turned over before it would seat. Her left hand waited while her right one worked.

The engineer counted sixteen separate motions to fit each connector and drew them as a strip of small steps. With the assembler, she then rebuilt the bench: bins within reach, connectors laid in the tray the way they would be used, and the left hand given its own job. The assembler was the first to say the new bench was easier on her wrists. Connectors fitted per shift roughly tripled within a month, the panels left the bench on schedule, and the assembler trained two others on the new layout.

The core idea

The Gilbreths broke a task into its fundamental motions, studied each, and then recombined them in the least wasteful way. Frank Gilbreth had started as a bricklayer and noticed that individual bricklayers did not always use the same motions. By redesigning the scaffold, the stacking of bricks, and the placement of brick and mortar, he cut the motions needed to lay a brick from eighteen to four and a half.

To see motions too quick for the eye, the Gilbreths developed micromotion study: filming work with a motion-picture camera and a timing device that marks intervals on the film. They classified the basic elements of work and named them therbligs, a play on the name Gilbreth spelled backward. The insight is that the best method of working is found by analyzing the motions and the workplace together, and not by asking the worker to try harder. The motions of a skilled worker, once visible, can be taught.

The thinking behind it

Frank Bunker Gilbreth Frank Gilbreth, born in 1868 in Fairfield, Maine, worked as a bricklayer and a building contractor before he became a management engineer. His book Motion Study, published in New York in 1911 with an introduction by Robert Thurston Kent, set out a method for increasing the efficiency of the workman. In it and in later papers collected in Applied Motion Study, he argued that waste hides in motions nobody has measured. His problem was the variation he saw among workers doing the same job, and his answer was to film the work and study it.

Lillian Moller Gilbreth Lillian Gilbreth, born in Oakland, California, in 1878, worked beside Frank throughout their marriage, and the two raised twelve children. Where Frank concentrated on the technical side of efficiency, she took the human element. In The Psychology of Management (1914) she studied how the mind shapes the finding, teaching, and installing of better methods, and the Gilbreths' papers insist that a new method is of no use to an employer without the worker's cooperation. After Frank died in 1924 she kept their firm going, and in 1935 she became the first woman on Purdue's engineering faculty.

Where it sits in the layers

Time and motion study sits in Layer 9, Tools and Techniques, because it is an instrument for one piece of analysis: break a job into its elementary motions, record them, and redesign the workplace so the wasted ones disappear. It takes for granted from the layers above the positivist stance that work can be observed and measured like any natural process, and it serves the improvement philosophies of Layer 6, Taylor's Scientific Management first and later Lean Thinking. Beside it in this layer, Value Stream Mapping looks at a whole flow where motion study looks at one bench, and its findings are checked on the floor in Layer 10 practices such as the gemba walk. The common mistake is asking it to decide what the business should make. It reveals waste in how work is done and says nothing on whether the work is worth doing.

How organizations put it to work

A manufacturing or process engineer usually owns the study, with a line supervisor and one or two of the people who do the work. The method changes three things. Structure: workplaces are redesigned so that parts, tools, and both hands have a defined place. Routines: standard methods are written from the best observed motions, taught to every new worker, and revisited whenever the work changes. Measures: cycle time per unit and the count of motions per unit are tracked beside output, so an improvement is visible as fewer steps.

Sustaining it takes the workers' cooperation, which the Gilbreths themselves stressed. A study done to people breeds resistance, and a study done with them yields better designs. It also takes a habit of looking again, since methods drift back.

In the first year a leader should expect sizable gains at the first few benches, a smaller gain at each later one, and a standard method that makes training faster. The return is output that depends less on a few expert workers, since a good method can be taught.

Where it goes wrong

The first failure is treating workers as machines, the charge critics leveled at scientific management from the start. A 2014 history by Maarten Derksen argues the human side was never absent from the movement, though it was treated as one more factor to manage. The sign is a redesign that saves seconds, loses the worker's judgment, and is followed by errors.

The second is optimizing the wrong thing. A bench made fast can still feed a process that waits, so a gain at one step may do nothing for the whole flow. The sign is a faster station that builds inventory in front of the next.

The third is rigidity. A fixed standard motion fits a stable task and fits poorly where the work varies by customer or by day. The sign is people departing from the written method because the work has changed and the method has not.

Related and rival frameworks

  • Taylor's Scientific Management. Studies the time a task takes and sets the wage and the standard around it. The better pick for a pay system, where motion study is the better pick for redesigning the work itself.
  • Value Stream Mapping. Maps the flow of material and information across a whole process. Use it when the waste is between stations, where motion study finds it within one.