Seven Management and Planning Tools

Layers of Management ThoughtLayer 9: Tools and TechniquesToolAlso known as M7, Seven new QC tools, New seven, Management and planning tools

Developed in Japan in the 1970s by a committee of the Society for QC Technique Development, and brought to Western readers in Michael Brassard's The Memory Jogger Plus+ (GOAL/QPC, 1989).

Seven diagrams and matrices, from affinity grouping to activity networks, that carry a team from scattered ideas and opinions to a structured, prioritized, and scheduled plan of action.

Seven planning steps, each with its own tool

A bank's operations team turns sixty scattered notes into a plan to speed up loan decisions. At each step pick the tool that fits, and see what it produces. Illustrative.

Planning team

The workshop

Planning team

The workshop

Select a stage to read it, or play the sequence.Sixty scattered notes. A review of loan processing gathered sixty notes from staff and customers. They overlap and contradict one another, and the team needs to see the themes in them.Pick a move to see the reply.Six groups emerge, among them unclear requirements, waiting between steps, and re-keying data. The team names each group in its own words.Right: grouping words by meaning.Forty minutes go to arguing what each note means. The scores rest on readings that nobody has agreed on.Scores before the notes are understood.Which group drives? The groups affect each other, so fixing a symptom first would waste effort. The team needs to see the direction of influence.Pick a move to see the reply.Unclear requirements sends arrows to four other groups and receives none. It is the driver.Right: shows which theme causes which.Waiting between steps has the most notes, so the team would start there. It is mostly an effect of unclear requirements.Counts symptoms and misses the driver.The driver is clear. The team agrees on a goal: fewer days from application to decision, beginning with clear requirements.From goal to actions. The goal is to cut days from application to decision by making requirements clear. The team must turn it into specific actions.Pick a move to see the reply.The goal splits into three means and eleven tasks, such as one checklist, an intake call, and a document template.Right: a breakdown down to tasks someone can do.The days wander inside the limits. The process is steady, and tasks are still missing.Describes the process and proposes nothing.Eleven tasks, limited time. Only a few of the eleven tasks can be funded this quarter. The team agrees on three criteria: effect on decision time, cost, and ease.Pick a move to see the reply.The single checklist and the intake call score highest. The scores are the team's judgment, and the weights are written down for anyone to challenge.Right: open criteria for a choice among options.The loudest manager's project wins, and the team cannot explain why the others lost.Gives a result with no criteria to defend.Who does what? The four chosen actions touch operations, compliance, IT, and branch staff.Pick a move to see the reply.Compliance turns out to own three of the actions and has no time. The team adds a second owner for two of them.Right: relates two lists at a glance.It restates the actions and does not show who takes part in each.Shows breakdown and not ownership.In what order? Some tasks cannot start until others finish. The team needs the order and the longest chain.Pick a move to see the reply.The template must precede the intake script, and that chain takes nine weeks. Everything else fits inside it.Right: sequence and timing across tasks.The tasks fall into tidy groups that say nothing about order or duration.Groups ideas and does not sequence them.What could go wrong? The plan is ready, and the team wants to find its weak points before acting.Pick a move to see the reply.The chart flags that compliance may reject the new checklist. A review with compliance in week two goes into the plan as a countermeasure.Right: anticipates failure before it happens.It re-ranks the same actions and says nothing about what can fail in carrying them out.Chooses among options that are already chosen.A plan with fallbacks. The team leaves with a plan built from sixty scattered notes. Every step has an owner, a place in the order, and a fallback.

Right tool for the step: 0 of 7Right tool for the step: 1 of 7Right tool for the step: 2 of 7Right tool for the step: 3 of 7Right tool for the step: 4 of 7Right tool for the step: 5 of 7Right tool for the step: 6 of 7Right tool for the step: 7 of 7

  1. Sixty scattered notes (Planning team). A review of loan processing gathered sixty notes from staff and customers. They overlap and contradict one another, and the team needs to see the themes in them.
    • Affinity diagram: group notes that belong together Six groups emerge, among them unclear requirements, waiting between steps, and re-keying data. The team names each group in its own words. Right: grouping words by meaning.
    • Prioritization matrix: score all sixty notes Forty minutes go to arguing what each note means. The scores rest on readings that nobody has agreed on. Scores before the notes are understood.
  2. Which group drives? (Planning team). The groups affect each other, so fixing a symptom first would waste effort. The team needs to see the direction of influence.
    • Interrelationship digraph: arrows from cause to effect Unclear requirements sends arrows to four other groups and receives none. It is the driver. Right: shows which theme causes which.
    • Rank the groups by number of notes Waiting between steps has the most notes, so the team would start there. It is mostly an effect of unclear requirements. Counts symptoms and misses the driver.
  3. The driver is clear (The workshop). The team agrees on a goal: fewer days from application to decision, beginning with clear requirements.
  4. From goal to actions (Planning team). The goal is to cut days from application to decision by making requirements clear. The team must turn it into specific actions.
    • Tree diagram: goal, means, and tasks The goal splits into three means and eleven tasks, such as one checklist, an intake call, and a document template. Right: a breakdown down to tasks someone can do.
    • Control chart of processing days The days wander inside the limits. The process is steady, and tasks are still missing. Describes the process and proposes nothing.
  5. Eleven tasks, limited time (Planning team). Only a few of the eleven tasks can be funded this quarter. The team agrees on three criteria: effect on decision time, cost, and ease.
    • Prioritization matrix: score actions against weighted criteria The single checklist and the intake call score highest. The scores are the team's judgment, and the weights are written down for anyone to challenge. Right: open criteria for a choice among options.
    • Vote by show of hands The loudest manager's project wins, and the team cannot explain why the others lost. Gives a result with no criteria to defend.
  6. Who does what? (Planning team). The four chosen actions touch operations, compliance, IT, and branch staff.
    • Matrix diagram: actions in rows, owners in columns Compliance turns out to own three of the actions and has no time. The team adds a second owner for two of them. Right: relates two lists at a glance.
    • Tree diagram again It restates the actions and does not show who takes part in each. Shows breakdown and not ownership.
  7. In what order? (Planning team). Some tasks cannot start until others finish. The team needs the order and the longest chain.
    • Activity network diagram: tasks, order, and longest path The template must precede the intake script, and that chain takes nine weeks. Everything else fits inside it. Right: sequence and timing across tasks.
    • Affinity diagram of the tasks The tasks fall into tidy groups that say nothing about order or duration. Groups ideas and does not sequence them.
  8. What could go wrong? (Planning team). The plan is ready, and the team wants to find its weak points before acting.
    • Process decision program chart: risks and countermeasures The chart flags that compliance may reject the new checklist. A review with compliance in week two goes into the plan as a countermeasure. Right: anticipates failure before it happens.
    • Prioritization matrix again It re-ranks the same actions and says nothing about what can fail in carrying them out. Chooses among options that are already chosen.
  9. A plan with fallbacks (The workshop). The team leaves with a plan built from sixty scattered notes. Every step has an owner, a place in the order, and a fallback.

An example

A regional bank's operations group had to cut the time from loan application to decision, and a first round of interviews produced sixty notes from staff and customers that overlapped and contradicted one another. In one workshop a facilitator had the team sort the notes into groups by meaning, and six themes appeared. A second diagram drew arrows between themes to show which caused which. Unclear requirements sent arrows to four other themes and received none, so it moved to the top of the list.

The team broke the goal into means and tasks, scored eleven tasks against three weighted criteria, and assigned owners in a matrix. A network of the tasks showed that one template had to be finished before an intake script, and a chart of what could go wrong flagged that compliance might reject the new checklist. Three workshops produced a plan that the whole group could explain, and decision time fell from eleven days to six.

The core idea

The seven tools are the affinity diagram, the interrelationship digraph, the tree diagram, the prioritization matrix, the matrix diagram, the process decision program chart, and the activity network diagram. Lists differ a little: Japanese lists name matrix data analysis in place of the prioritization matrix. They are meant to be used in sequence. The affinity diagram groups scattered ideas by meaning. The digraph shows which group drives which. The tree breaks a goal into means and tasks. The prioritization matrix scores options against weighted criteria, and the matrix diagram relates two lists, such as actions and owners. The process decision program chart anticipates what could go wrong, and the activity network sets the order and timing of tasks.

The insight is that these tools handle the material of planning, which is words, opinions, and relationships, with the same discipline the basic quality tools bring to numbers. They also open planning to more people, since a diagram on a wall gives everyone in the room something to point at and change.

The thinking behind it

A committee of the Society for QC Technique Development in Japan The tools come from a committee of Japan's Society for QC Technique Development, which, in Ronald Anjard's 1995 account, refined and tested the individual tools and their sequence between 1972 and 1979. Another history dates the committee's proposal to 1976, its reconstitution as a research group in 1978, and the first symposium on the tools to 1979. The titles of the early English books, Management for Quality Improvement: The 7 New QC Tools (1988) and The Seven New QC Tools: Practical Applications for Managers (1994), show who the audience was. Michael Brassard's The Memory Jogger Plus+, published by GOAL/QPC in 1989, carried the seven to many Western companies and fixed the list most often used there.

Where it sits in the layers

The seven tools sit in Layer 9, Tools and Techniques, as instruments for structuring planning work. They carry the habit of fact-based group problem solving from Total Quality Management in Layer 6 into the planning stage, and they feed the policy deployment of Hoshin Kanri in Layer 8, where goals must be broken into means and owners. Two of the seven, the activity network and the process decision program chart, overlap with Critical Path Method scheduling and risk planning. Below, they are put into practice in the planning workshops and quarterly reviews of Layer 10. The common mistake is asking the tools to produce evidence. They give shape to judgment and consensus, and a prioritization matrix full of scores is an organized opinion until data backs each score.

How organizations put it to work

Ownership sits with the quality, strategy, or operational excellence function, which trains facilitators and runs the workshops. Each tool is a working session of two to three hours with a facilitator, a wall, and the people who hold the knowledge. The first workshops usually take a real planning problem all the way from the affinity diagram to a schedule, so the sequence is learned by doing.

The structural change is that plans leave the workshop as artifacts: a tree that becomes project charters, a matrix of actions and owners, and a network that becomes a calendar. The measures are time from idea to approved plan, the share of planned actions finished on time, and how well participants from different functions agree on the plan afterward.

Sustaining it takes trained facilitators in each function and a rule that significant plans arrive in a standard form. In the first year a leader should expect energy and clear gains in alignment, a wave of sticky-note workshops that run too long, and some groups that use the diagrams as ritual after the decision has already been made.

Where it goes wrong

The first failure is scores treated as data. A prioritization matrix turns judgment into numbers, and the numbers can look more certain than they are. The sign is a ranking that flips when one weight changes slightly.

The second is the full sequence applied by rote. Not every problem needs all seven tools, and a heavy method on a small question wears out participants. The sign is workshops that run for days and plans that arrive after the window for acting has closed.

The third is the loudest voice. Diagrams are built by groups, and groups defer to rank. The sign is a diagram that matches what the most senior person said before the workshop started.

Related and rival frameworks

  • Seven Basic Tools of Quality. The companion set for numerical data, such as defect counts and measurements. Better when the problem has numbers and the question is where to look.
  • Affinity Diagram. The first of the seven, treated as a stand-alone technique. Better when the task is only to make sense of a pile of ideas.
  • Quality Function Deployment. A large matrix that links customer wants to design features. Better when the planning problem is product design.

Go to the source

  • Management and planning tools, Training for Quality 3(2), 34 to 37, by Ronald P. Anjard, 1995
  • The Memory Jogger Plus+: Featuring the Seven Management and Planning Tools, GOAL/QPC, Methuen, Massachusetts, 1989
  • Management for Quality Improvement: The 7 New QC Tools, Productivity Press, edited by Shigeru Mizuno, 1988

Back to the catalog