SMED

Layers of Management ThoughtLayer 9: Tools and TechniquesToolAlso known as Single-Minute Exchange of Die, Quick changeover

Developed by Shigeo Shingo from changeover work at Toyota and other Japanese manufacturers, where Toyota's own engineers had been cutting setup times since the late 1940s, and set out in A Revolution in Manufacturing: The SMED System (English edition, 1985).

Shortens the time a machine stands idle between products by separating changeover work that needs the machine stopped from work that can be done while it runs, which makes small batches affordable.

A press changeover: which steps can happen while the machine runs?

Done entirely on a stopped press, the die change takes 96 minutes; fetching the next die has already been moved to the running side. For each other step, decide whether it can be done while the press runs, and watch the idle time fall. A step that needs the press cannot be moved, and the figure says so. Illustrative.

Machine running
Machine stopped
Machine stopped
Machine stopped
Machine stopped
Machine stopped
3
Press stopped per changeover
81 min
Share of a 480-minute shift spent changing over
51%
Are the moves possible?
Yes: every step moved can be done with the press runningNo: a step that needs the stopped press is marked as running

Minutes the press is stopped

010203002010142512Fetch diePreheatRemove oldMount newAdjustReturn old010203002010142512FetchdiePreheatRemoveoldMountnewAdjustReturnold

An example

A stamping plant ran its main press in lots of eight thousand parts, because each die change took 96 minutes. The schedule had grown around that number: big lots, shelves of unsold parts, and urgent orders that waited days for the next open slot. A team of two operators, a tool-room technician, and an engineer filmed one changeover and watched it on a screen with a stopwatch. They sorted every step into two columns. In the first went work that could only be done with the press stopped, such as pulling the old die and clamping the new one. In the second went everything else.

The second column held more than they expected: fetching the next die and tools, heating the die, and carrying the old die back to the store. Doing those while the press ran cut the stoppage from 96 to 49 minutes in the first month. Lot sizes fell to three thousand, inventory shrank, and a rush order's wait went from days to a shift.

The core idea

A changeover is the time from the last good piece of one product to the first good piece of the next. SMED divides the work in it into two kinds. Internal work can be done only while the machine is stopped, such as removing a die. External work can be done while the machine is running, such as bringing the next die to the machine's side or heating it. The first move is to list every step and label it one or the other. The second is to push as much work as possible into the external column, and the third is to shorten what remains by simplifying adjustments, standardizing fasteners, and preparing tools in kits. The name states the aim: a changeover short enough to be counted in single digits of minutes.

The insight that makes it a management framework is economic. When changeovers are long, lots must be large to spread the cost, and large lots mean inventory and slow response. Short changeovers let a plant make small lots of many products in a day.

The thinking behind it

Shigeo Shingo Shigeo Shingo was an industrial engineer who first met Toyota through a seminar in the mid-1950s and then advised its engineers for about two decades. In an account by Toyota's Isao Kato, Shingo led a workshop in 1969 on a forging press and introduced the distinction between internal and external work. Toyota's engineers had been cutting changeovers since the late 1940s and brought stamping to about three minutes by 1971, and Kato argues that Shingo's best-known anecdote about a 1,000-ton press is misrepresented. Shingo's book, A Revolution in Manufacturing: The SMED System (English edition 1985), presents the theory and practice with twelve case studies from Japanese manufacturers.

Where it sits in the layers

SMED sits in Layer 9, Tools and Techniques, as a method that any plant can apply to a single machine or line. It serves two ideas in Layer 6. The Toyota Production System treats inventory as waste and wants production to follow demand, and Just-in-Time depends on short changeovers to make small batches affordable. In Layer 9 itself it enables Heijunka, which cannot level a mix of products without them. Below, it is put into practice in the changeover standards and daily production meetings of Layer 10. The common mistake is asking SMED to fix planning. It makes switching cheap, and it says nothing about what to build next, how much demand to expect, or whether the plant has the right products. Those belong to the scheduling methods above it.

How organizations put it to work

Ownership sits with the plant's operations or lean leader, with a team that includes the operators who do the changeover, a maintenance or tooling technician, and an engineer. The team records a real changeover, lists the steps, classifies each as internal or external, moves work, and then shortens what remains. The new sequence becomes a written standard, often a checklist at the machine.

Physical changes follow: a place for dies and tools near the machine, carts and kits staged in advance, fasteners and settings made uniform, and quick-release clamps where they pay back. The measures are changeover time to first good piece, lot size, inventory days, and available machine hours. The effect reaches scheduling as lots shrink, which means planners release smaller orders more often.

Sustaining it takes changeover times posted at the line and a team that revisits them when products change. In the first year a leader should expect the first big gains to come from reorganizing work and spending little on equipment, then smaller gains that need fixtures and design changes, and a tension between the plant, which wants small lots, and a schedule built for large ones.

Where it goes wrong

The first failure is speed without a standard. If operators rush adjustments, the first parts come out wrong, and scrap erases the time saved. The sign is rising scrap or rework at the start of each run.

The second is saved time that goes nowhere. If lots stay large and the freed hours go idle, nothing is gained. The sign is a changeover time that fell while inventory and lead time stayed the same.

The third is trusting a heroic anecdote. The best-known SMED story, a press cut from four hours to three minutes, is disputed by Isao Kato of Toyota, who places Shingo's main successes at other firms on smaller machines. Plants that expect a dramatic number everywhere are disappointed on large, awkward machines.

The fourth is buying hardware first. Automatic clamping and quick-change tooling are expensive, and many gains come from moving work off the stopped machine, which costs almost nothing.

Related and rival frameworks

  • Heijunka. Levels the mix and volume of production over time. Better to think of next, since it relies on the short changeovers SMED provides.
  • Theory of Constraints. Says where time is worth saving: at the bottleneck. Better first when a plant has many machines and must choose where to start.
  • Lean Thinking. The wider philosophy that treats batch inventory as waste. Better when the question is what to improve across the whole flow.