Takt Time

Layers of Management ThoughtLayer 9: Tools and TechniquesToolAlso known as Takt, Customer pace

A practice first used as a production management tool in the German aircraft industry in the 1930s and adopted widely at Toyota in the 1950s; no single person is credited.

Sets the pace of production at the available working time divided by customer demand, so every station works at the rhythm the customer buys at and the line neither runs ahead of demand nor falls behind it.

Takt time against the slowest station of a pump-kit line

The customer wants 200 kits a day and the line has 440 productive minutes. Takt is the minutes divided by the demand, and the slowest station must finish a kit inside it. Decide how fast the seal press, now 2.6 minutes a kit, must become, then set it and see whether the line keeps pace; demand and minutes can change too. Illustrative.

200 kits
440 min
2.6 min
Takt time: available minutes divided by demand
2.20 min
Does the line keep pace?
No: the slowest station sets the output below demandYes: every station finishes inside the takt
Kits short of demand each day
31 kits
Customer demand per daySlowest station's minutes per kitLow demandHigh demandToo slowWithin taktCustomer demand per daySlowest station's minutes per kitLow demandHigh demandToo slowWithin takt

Where the line landsToo slow: the slowest station takes longer than the takt, so the line falls short of demand.Within takt: the slowest station finishes a kit before the next one is needed.

An example

A line assembled water-pump kits for a customer who wanted 200 a day. After breaks and meetings the plant had 440 productive minutes a shift, and the supervisor divided one by the other: 2.2 minutes per kit. She then timed each of the six stations. Five ran between 1.8 and 2.1 minutes. The seal press took 2.6. The line had been shipping about 170 kits a day, and weekend overtime had covered the gap without anyone naming the cause.

With the number in front of them, the crew put a 2.2-minute timer at the line and looked at the press. One operator began preparing seals off the line, which cut the press's time to 2.1 minutes. The line met 200 kits on a normal shift, weekend overtime stopped, and the customer's orders shipped on the promised day.

The core idea

Takt time is the available production time divided by customer demand. A plant with 480 minutes a day and demand for 240 units has a takt time of two minutes: a finished unit is needed every two minutes, whatever the speed of any machine. If customers want two new products a month, the takt time is two weeks. The word is German and comes from music, where it names the beat that keeps players together.

The idea matters because it ties the pace of every station to the customer. Each station's cycle time, the time it takes to do its share of the work on one unit, is compared with the takt. A station whose cycle time is longer is the constraint and sets the output of the whole line. A station whose time is much shorter waits and builds nothing useful. Work is then balanced across stations so each one lands near the takt.

The thinking behind it

German aircraft industry in the 1930s, adopted at Toyota in the 1950s Takt began on German aircraft lines of the 1930s, where it set how often a plane advanced to the next station, according to the Lean Enterprise Institute's lexicon. Toyota took the idea up in the 1950s, and by the late 1960s its suppliers used it too. The lexicon describes Toyota revisiting each process's takt monthly and fine-tuning it roughly every ten days, and it states the purpose in one line: production should keep exact step with demand. No source names an inventor, so takt is credited to the manufacturing practice that carried it from aircraft to cars.

Where it sits in the layers

Takt time sits in Layer 9, Tools and Techniques, as a calculation that sets a pace for a line or a team. It serves the aim of the Toyota Production System in Layer 6 to make what the customer wants, when they want it, and it gives Just-in-Time a clock to pull against. In its own layer it pairs with Heijunka, which levels demand into a steady rate a takt can describe, and below, it is put into practice in the takt boards and shift meetings of Layer 10. The common mistake is asking takt to measure how fast people work. It is a target set by demand and available time, and a team that runs faster than takt builds stock nobody has asked for.

How organizations put it to work

Ownership sits with operations or industrial engineering, working with sales and planning, who supply the demand figure. The first step is to compute takt for each product family from a realistic demand number and honest available time, after breaks, meetings, planned maintenance, and changeovers. The second is to time every station and compare it with the takt, then rebalance work among stations until each fits.

The routines are visible. A takt board or timer sits at the line, and a signal system shows when a station falls behind. The takt is reviewed on a set rhythm, monthly in Toyota's practice, and the staffing changes with it, adding or removing people from the line. The measures are takt adherence, overtime hours, work in process between stations, and units per labor hour.

Sustaining it takes reliable demand data and a team that treats a miss against takt as a problem to solve, with a cause behind it. In the first year a leader should expect early arguments over what counts as available time, the first honest look at the slowest station, and a new view of how much of the day the line had been waiting.

Where it goes wrong

The first failure is a takt built on a wish. If the demand figure is optimistic or the available time ignores breakdowns and changeovers, the takt is faster than the plant can sustain. The sign is a line that meets takt on paper and runs overtime every week.

The second is treating takt as a speed limit for people. Pushing every worker to the takt with no slack for variation leads to rushed work and quality problems. The sign is rising rework and fatigue.

The third is ignoring changing demand. A takt set in January can be wrong in May. The sign is a line staffed for last quarter's rate.

The fourth is applying it where work content varies widely. In high-mix or custom work, where jobs differ in length by multiples, one takt hides more than it shows. The sign is stations whose workloads change sharply from one product to the next.

Related and rival frameworks

  • Heijunka. Levels volume and mix so the takt stays steady from day to day. Better to use alongside takt whenever demand swings from day to day.
  • Little's Law. Links work in process, throughput, and time in process. Better when the issue is how long work waits; takt answers how fast it should move.
  • Value Stream Mapping. Draws the whole flow, from order to delivery, with times at each step. Better for finding where in the chain the takt is missed.